Answer 1)
Correct answer is Option A. WACC - The firms' required return. It is used as a discount rate in NPV and is used to compare to IRR
Answer 2)
Correct answer is Option C. It ignores time value of money.
Answer 3)
NPV is given by:

Hence,
NPV = -500 + 200 / 1.06^1 + 300 / 1.06^2 + 250 / 1.06^3 + 125 / 1.06^4
So correct answer is Option C.
Answer 4)
The discount rate at which NPV = 0 is known as IRR
Hence,
0 = -500 + 125 / (1 + irr)^1 + 250 / (1 + irr)^2 + 175 / (1 + irr)^3 + 195 / (1 + irr)^4
So correct answer is Option A.
Question 1 5 pts What is WACC? Why is it important? O The firm's required return....
2 pts Question 5 Your required return is 10%. Should you accept a project with the following cash flows? 2 3 Year Cash Flow -$25 +$7 +$8 +$15 O Yes, because the NPV is $5. Yes, because the IRR is 12.45% Yes, because the IRR is 30%. No, because the IRR is only 8.48%. No, because the IRR is 10.31%
Question 3 5 pts Our firm's cost of capital is 10%. We are thinking about taking a project that gives a 10% rate of return. Which of the following statements are correct. The NPV of this project is zero. The firm will increase its value if it takes this project. The firm should not take this project because it will lose value if the project is taken. The IRR of the project is greater than the cost of capital. Two...
Question 10 5 pts What is Project B's Internal Rate of Return (IRR) with a WACC of 7.75%? YEAR CASH FLOWS Project A Project B 0 -$1050 -$1050 1 675 360 1 2 650 360 3 360 4 360 HTML Editora BTA - A - IEE 32. * DoPNV GODT 12pt Paragraph
Dropdown options first 2 blanks: (internal rate of return IRR,
required rate of return, modified internal rate of return MIRR)
Dropdown options 3rd blank: (NPV method, IRR method)
If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. always Projects Y and...
First Blank: always, sometimes, never
Second Blank: IRR, MIRR, required rate of return
Third Blank: IRR, MIRR, required rate of return
Fourth Blank: IRR method, NPV method
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree....
D Question 21 1 pts You have a required return of 12%. A project that you are considering offers an IRR of 10.97%. Should you accept or reject this project? Accept Reject Question 22 1 pts You have a project that with an npv of 56,478. Should you accept or reject the project? Accept Reject
? Question 3 4 pts Consider the two cash flow streams below: 0 2 Option Y: 2,000900 -900 Option Z:-2,500 13001300 Which project has the higher IRR? Which project has the higher NPV if required return is 10.4%? O Option Y has higher IRR: Option Y has higher NPV O Option Y has higher IRR: Option Z has higher NPV O Option Z has higher IRR; Option Y has higher NPV O Option Z has higher IRR: Option Z has...
Question 1 2 pts A project costs $100,000, will be depreciated straight-line to zero over its 4 year life, and will require a networking capital investment of $5.000 up-front. The firm has a tax rate of 35% and a required return of 15%. The project generates an annual operating cash flow (OCF) of $45,000. What is the project's NPV? $-18,633.12 $ 23,474.03 o $ 26,332.79 $ 28,474.03 O $ 45,603.09 Question 2 2 pts Calculate the NPV of the following...
If a project returns Exactly the required rate of return (x) then: 1. NPV will be ____. 2. PI will be _____. 3. IRR will be ____. options: x 0 1
Question 7 5 pts Use the following after-tax cash flows for project A and B to answer the following question: (Numbers in parentheses are negative cash flows). These two projects are independent Year Cash Flow of A Cash Flow of B 0 ($2,400) ($4,500) 1 $999 $800 2 $950 $950 3 ($150) $950 $910 $800 5 $990 $900 6 ($500) $1980 What is the approximate payback of project B if the required rate of return is 10%? 4.56 years 6...