Manufacturing cycle efficiency
= Value added time (or Process time) ÷ Manufacturing cycle time
where:
Manufacturing cycle time = Process time + Inspection time + Move
time + Queue time
So the manufacturing cycle efficiency(MCE)
= 5.8 /(5.8 + 1.4 + 4 + 6.1)
= 5.8/17.3
= 0.3352
= 33.5%
Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular...
Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 22.0 Process time 6.1 Inspection time 1.5 Move time 4.1 Queue time 6.2 The manufacturing cycle efficiency (MCE) was closest to:
Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below. Wait time Process time Inspection time Move time Queue time Hours 22.5 7.6 2.0 4.6 6.7 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculations to 1 decimal place.) Multiple Choice O O 0.36 O O 0.93 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculations to 1 decimal place.) Ο Ο Ο Ο Ο
to fill orders. Data concerning 5) Santoyo Corporation keeps careful track of the time required to a particular order appear below: Hours 28.0 1.0 Inspection time 0.4 Move time 3.2 Queue time Wait time Process time 5.1 The delivery cycle time was: A) 8.3 hours B) 3.2 hours C) 37.7 hours D) 36.3 hours 35) Simkin Corporation keeps careful track of the time required to fill orders. Data concem a particular order appear below: Hours 20.6 1.9 0.1 Wait time...
Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below. Wait time Process time Inspection time Move time Queue time Hours 12.9 2.0 0.4 4.6 6.3 The delivery cycle time was: Multiple Choice 0 10.9 hours O 23 8 hours Schapp Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below. Move time Wait time Queue time Process time Inspection time...
Vandenheuvel Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours Move time 3.3 Wait time 19.7 Queue time 9.9 Process time 1.7 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: 0.11 0.31 0.19 0.05
Vandenheuvel Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours Move time 2.3 Wait time 19.3 Queue time 11.4 Process time 1.3 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculations to 1 decimal place.) Multiple Choice 0.16 0.02 0.08 0.34
Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 13.7 Process time 2.8 Inspection time 0.4 Move time 3.4 Queue time 7.1 The delivery cycle time was: Multiple Choice 10.5 hours 3.4 hours 27.4 hours 24.2 hours
Tanouye Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 28.4 Process time 3.6 Inspection time 0.6 Move time 4.2 Queue time 9.7 The throughput time was:
Question 19 (4 points) Ebsen Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Wait time........ Process time ..... Inspection time ..... Move time ...... Queue time.... Hours 16.6 1.3 0.3 2.9 9.4 The manufacturing cycle efficiency (MCE) was closest to: Inspection time.... Move time..... Queue time ..... 0.3 2.9 9.4 The manufacturing cycle efficiency (MCE) was closest to: 0.84 0.04 0.17 0.09 Question 18 (4 points) Newhart Enterprises recently used...
Measures of Internal Business Process Performance Pumpkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 20.6 Process time 1.9 Inspection time 0.1 Move time 2.7 Queue time 4.8 INSTRUCTIONS: (Show your work) 1) Which of the above items are value - added - activities? 2) Compute the throughput time in hours. 3) Compute the delivery cycle time in hours. 4) Compute the manufacturing cycle efficiency (MCE). 5)...