Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:
Hours | |
Wait time | 13.7 |
Process time | 2.8 |
Inspection time | 0.4 |
Move time | 3.4 |
Queue time | 7.1 |
The delivery cycle time was:
Multiple Choice
10.5 hours
3.4 hours
27.4 hours
24.2 hours
Calculation of Delivery Cycle Time:
Delivery cycle time=Wait time+Process time+Inspection time+Move time+Queue time
= (13.7+2.8+0.4+3.4+7.1)
= 27.4 hours.
Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular...
Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below. Wait time Process time Inspection time Move time Queue time Hours 12.9 2.0 0.4 4.6 6.3 The delivery cycle time was: Multiple Choice 0 10.9 hours O 23 8 hours Schapp Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below. Move time Wait time Queue time Process time Inspection time...
to fill orders. Data concerning 5) Santoyo Corporation keeps careful track of the time required to a particular order appear below: Hours 28.0 1.0 Inspection time 0.4 Move time 3.2 Queue time Wait time Process time 5.1 The delivery cycle time was: A) 8.3 hours B) 3.2 hours C) 37.7 hours D) 36.3 hours 35) Simkin Corporation keeps careful track of the time required to fill orders. Data concem a particular order appear below: Hours 20.6 1.9 0.1 Wait time...
Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below. Hours 21.9 5.8 Wait time Process time Inspection time Move time Queue time 4.0 The manufacturing cycle efficiency (MCE) was closest to:
Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 22.0 Process time 6.1 Inspection time 1.5 Move time 4.1 Queue time 6.2 The manufacturing cycle efficiency (MCE) was closest to:
Tanouye Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 28.4 Process time 3.6 Inspection time 0.6 Move time 4.2 Queue time 9.7 The throughput time was:
Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below. Wait time Process time Inspection time Move time Queue time Hours 22.5 7.6 2.0 4.6 6.7 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculations to 1 decimal place.) Multiple Choice O O 0.36 O O 0.93 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculations to 1 decimal place.) Ο Ο Ο Ο Ο
Schapp Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below Hours 2.8 10.6 Move time Wait time Queue time Process time Inspection time The throughput time was:
Schapp Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours 4.6 12.4 Move time Wait time Queue time Process time Inspection time 8.8 3.5 2.4 The throughput time was: Multiple Choice 19.3 hours 31.7 hours 0 212 hours 10.5 hours
Vandenheuvel Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours Move time 2.3 Wait time 19.3 Queue time 11.4 Process time 1.3 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculations to 1 decimal place.) Multiple Choice 0.16 0.02 0.08 0.34
Vandenheuvel Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours Move time 3.3 Wait time 19.7 Queue time 9.9 Process time 1.7 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: 0.11 0.31 0.19 0.05