Question
Only requirement 2 please. Thank you
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below 2018 2019 Costs incurred during the year Estinated costs to complete as of 12/31 Billings during the year Cash collections during the year $356,000 $2,135,000 1.424,000 475,000 1,760,000 278,000 1,820,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortel recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming Nortel recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming this project does not qualify for revenue recognition over time.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution

Nortel Networks

Requirement 2:

Computation of the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming this project does not qualify for revenue recognition over time:

The contract does not quality for revenue recognition in 2018- gross profit for 2018 is zero, as the contract is not yet completed.

Revenue for 2019 - $2,700,000

Gross profit, 2019 = revenue – total estimated cost

= $2,700,000 - $2,491,000 = $209,000

Workings:

2018

2019

Contract Price

$2,700,000

$2,700,000

Actual Costs to Date

$356,000

$2,491,000

Estimated Cost to Complete

$1,424,000

0

Total Estimated Costs

$1,780,000

$2,491,000

Gross profit estimated in 2018

$920,000

$209,000

Add a comment
Know the answer?
Add Answer to:
Only requirement 2 please. Thank you Assume Nortel Networks contracted to provide a customer with Internet...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Requirement 3 please Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000....

    Requirement 3 please Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 356,000 $2,135,000 2019 Costs incurred during the year Estinated costs to complete as of 12/31 illings during the year Cash collections during the year 1,424,000 475, 000 1,760,000 278,000 1,820,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 356,000 $ 2,135,000 Estimated costs to complete as of 12/31 1,424,000 0 Billings during the year 475,000 1,760,000 Cash collections during the year 415,000 1,820,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year $ 300,000 1,575,000 1,200,000 380,000 1,620,000 250,000 1,750,000 Required 1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2019 2018 356,000 $2,135,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 1,424,000 475,000 1,760, 000 278,000 1,820,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2016 and was completed in 2017. Data relating to the contract are summarized below:Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2016 and 2017 assuming Nortel recognizes revenue over time according to percentage of completion.2. Compute the amount of revenue and gross profit or loss to be recognized in 2016 and 2017 assuming this project does...

  • Help Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,760,000. The p...

    Help Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,760,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2018 364,000 $2,175,000 1,456,000 520,000 282,000 2019 0 1,780,000 1,830,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2018...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405.000 300,000 1.670.000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...

  • Please show all calculations! Assume Nortel Networks contracted to provide a customer with Internet Infrastructure for...

    Please show all calculations! Assume Nortel Networks contracted to provide a customer with Internet Infrastructure for $2600,000. The project began In 2018 and was completed In 2019. Data relating to the contract are summarized below: 2018 2819 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year $ 348,90e $1,995,8ee 1, 392,8ee 465,888 1,748,888 274,808 1,818,888 Requlrec 1. Compute the amount of revenue and gross profit or loss to...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405,000 300,000 1,670,000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,500,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized b...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,500,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year $ 340,000 $ 1,940,000 Estimated costs to complete as of 12/31 1,360,000 0 Billings during the year 451,000 1,720,000 Cash collections during the year 270,000 1,800,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT