Question

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,500,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized b...

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,500,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below:

2018 2019
Costs incurred during the year $ 340,000 $ 1,940,000
Estimated costs to complete as of 12/31 1,360,000 0
Billings during the year 451,000 1,720,000
Cash collections during the year 270,000 1,800,000


Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortel recognizes revenue over time according to percentage of completion.
2. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming this project does not qualify for revenue recognition over time.
3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming Nortel recognizes revenue over time according to percentage of completion.
4. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming this project does not qualify for revenue recognition over time.

1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
Ans 1) Percentages of completion
Numerator/ Denominator = % complete to date
Cost incurred to date/ Total estimated cost =
2018 340,000 1700000 20%
2019 2,280,000 2,280,000 100%
2018
To date Recognized in pys Recognized in 2018
Construction revenue 500000 0 500000
Construction expense 340000 0 340000
Gross profit (loss) 160000 0 160000
2019
To date Recognized in pys Recognized in 2018
Construction revenue 2,500,000 500000 2,000,000
Construction expense 2,280,000 340000 1,940,000
Gross profit (loss) 220,000 160000 60000
Ans 2) Revenue Gross profit (Loss)
2018 0 0
2019 2,500,000 220,000
Ans 3) BALANCE SHEET PARTIAL-DECEMBER 31, 2018:
Current assets:
Costs and profit in excess of billings 49000
Accounts receivable 181000
Ans 4) BALANCE SHEET PARTIAL-DECEMBER 31, 2018:
Current assets:
Accounts receivable 101000
Add a comment
Know the answer?
Add Answer to:
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,500,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized b...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,500,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 3

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,500,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 20212022Costs incurred during the year$340,000$1,940,000Estimated costs to complete as of 12/311,360,0000Billings during the year451,0001,720,000Cash collections during the year371,0001,800,000 Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion.2. Compute the amount of...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below: 2018 2019 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year $ 300,000 1,575,000 1,200,000 380,000 1,620,000 250,000 1,750,000 Required 1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405,000 300,000 1,670,000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405.000 300,000 1.670.000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2016 and was completed in 2017. Data relating to the contract are summarized below:Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2016 and 2017 assuming Nortel recognizes revenue over time according to percentage of completion.2. Compute the amount of revenue and gross profit or loss to be recognized in 2016 and 2017 assuming this project does...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,910,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 376,000 $ 2,265,000 Estimated costs to complete as of 12/31 1,504,000 0 Billings during the year 535,000 1,810,000 Cash collections during the year 500,000 1,845,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 356,000 $ 2,135,000 Estimated costs to complete as of 12/31 1,424,000 0 Billings during the year 475,000 1,760,000 Cash collections during the year 415,000 1,820,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 324,000 $ 1,800,000 Estimated costs to complete as of 12/31 1,296,000 0 Billings during the year 410,000 1,680,000 Cash collections during the year 310,000 1,780,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 336,000 $ 1,870,000 Estimated costs to complete as of 12/31 1,344,000 0 Billings during the year 446,000 1,710,000 Cash collections during the year 361,000 1,795,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 352,000 $ 2,025,000 Estimated costs to complete as of 12/31 1,408,000 0 Billings during the year 470,000 1,750,000 Cash collections during the year 405,000 1,815,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT