Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...

Problem 10-14 Measures of Internal Business Process Performance [LO10-3]

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.

Month

1

2

3

4

Throughput time (days)

?

?

?

?

Delivery cycle time (days)

?

?

?

?

Manufacturing cycle efficiency (MCE)

?

?

?

?

Percentage of on-time deliveries

81

%

77

%

74

%

71

%

Total sales (units)

3180

3044

2888

2778

Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:

Average per Month (in days)

1

2

3

4

Move time per unit

0.8

0.5

0.6

0.6

Process time per unit

3.5

3.3

3.2

3.0

Wait time per order before start of production

22.0

24.1

27.0

29.2

Queue time per unit

4.2

4.7

5.3

6.0

Inspection time per unit

0.6

0.7

0.7

0.6


Required:

1-a. Compute the throughput time for each month.

1-b. Compute the delivery cycle time for each month.

1-c. Compute the manufacturing cycle efficiency (MCE) for each month.

2. Evaluate the company’s performance over the last four months.

3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE.

3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.

Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:

Average per Month (in days)

1

2

3

4

Move time per unit

0.8

0.5

0.6

0.6

Process time per unit

3.5

3.3

3.2

3.0

Wait time per order before start of production

22.0

24.1

27.0

29.2

Queue time per unit

4.2

4.7

5.3

6.0

Inspection time per unit

0.6

0.7

0.7

0.6


Required:

1-a. Compute the throughput time for each month.

1-b. Compute the delivery cycle time for each month.

1-c. Compute the manufacturing cycle efficiency (MCE) for each month.

2. Evaluate the company’s performance over the last four months.

3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE.

3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Part 1-a

Throughput time

Month 1

9.1

days

Month 2

9.2

days

Month 3

9.8

days

Month 4

10.2

days

Explanation:

1

2

3

4

Throughput time in days:

Process time

3.5

3.3

3.2

3.0

Inspection time

0.6

0.7

0.7

0.6

Move time

0.8

0.5

0.6

0.6

Queue time

4.2

4.7

5.3

6.0

Total throughput time

9.1

9.2

9.8

10.2

Part 1-b

Delivery cycle time

Month 1

31.1

days

Month 2

33.3

days

Month 3

36.8

days

Month 4

39.4

days

Explanation:

1

2

3

4

Delivery cycle time in days:

Wait time

22.0

24.1

27.0

29.2

Total throughput time

9.1

9.2

9.8

10.2

Total delivery cycle time

31.1

33.3

36.8

39.4

Part 1-c

Manufacturing cycle efficiency (MCE):

Process time ÷ Throughput time

Month 1

(3.5/9.1) = 38.5

%

Month 2

(3.3/9.2)=35.9

%

Month 3

(3.2/9.8)=32.7

%

Month 4

(3.0/10.2)=29.4

%

Part 2

The throughput time measure displays

Favorable

Trends

The delivery cycle time days measure displays

Favorable

trends

Manufacturing cycle efficiency days measure displays

Unfavorable

trends

Part 3-a

Month 5

Throughput Time

4.2

days

Manufacturing cycle efficiency (MCE)

71.4

%

Part 3-b

Month 6

Throughput Time

3.6

days

Manufacturing cycle efficiency (MCE)

83.3

%

Explanation for 3-a and 3-b:

5

6

Throughput time in days

Process time

3.0

3.0

Inspection time

0.6

0

Move time

0.6

0.6

Queue time

0.0

0.0

Total throughput time

4.2

3.6

5

6

Manufacturing cycle efficiency (MCE):Process time ÷ Throughput time

71.4%

(3.0/4.2)

83.3%

(3.0/3.6)

Add a comment
Know the answer?
Add Answer to:
Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...

    Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations....

  • Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...

    Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations....

  • Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...

    Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations....

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4   Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible...

    DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountere relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing cycle efficiency...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT