Your answer 11 and 12 are correct
So only 13 to 15 are answered as below
Answer 13: B $135750
| Total cost of job no. 83-50 | ||
| Opening WIP | $ 54,000 | |
| Direct material | $ 45,000 | |
| Direct labor | =51000*3500/8500 | $ 21,000 |
| Overhead applied | =3500*4.50 | $ 15,750 |
| Total cost of job no. 83-50 | $ 135,750 | |
Answer 14 : B 38250
Calculated as
Overhead applied = DLH total x Predetermined overhead rate
= 8500*4.50
= $38250
Answer 15 C. $5.05 per DLH
Calculated as
Predetermined overhead on normal activity = $606000/120000 = $5.05 per DLH
Questions 11 through 15 are based on the following information. Bachr Company manufacturing company with a...
Sheridan Company estimates that annual manufacturing overhead costs will be $902,000. Estimated annual operating activity bases are direct labor cost $400,000, direct labor hours 40,000, and machine hours 100,000. Compute the predetermined overhead rate for each activity base. (Round answers to 2 decimal places, eg. 10.50) Overhead rate per direct labor cost Overhead rate per direct labor hour $ Overhead rate per machine hour Coronado Company uses a job order cost system and applies overhead to production on the basis...
Required information [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March-Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as Required Complete the T-accounts. (LO 7-3) 7-52. Analysis of Overhead Using a Predetermined Rate follows. Direct labor-hours Variable overhead costs. Fixed overhead costs Total overhead. 150,000 $1,050,000 648,000 $1,698,000 180,000 $1,260,000 648,000 $1,908,000 210,000 $1,470,000...
Waterway and Associates, a CPA firm, uses job order costing to capture the costs of its audit jobs. There were no audit jobs in process at the beginning of November. Listed below are data concerning the three audit jobs conducted during November. Direct materials Auditor labor costs Auditor hours Waters Inc. $690 $5,600 77 Renolds Inc. $480 $6,900 89 Bayfield Inc. $250 $3,675 46 Overhead costs are applied to jobs on the basis of auditor hours, and the predetermined overhead...
Problem 15-01A (Part Level Submission) Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,200, direct labor $12,120, and manufacturing overhead $16,160. As of January 1, Job 49 had been completed at a cost of $90,900 and was part of finished goods...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,200,000 $ 1,440,000 $ 1,680,000 Fixed overhead costs 702,000 702,000 702,000 Total overhead $ 1,902,000 $ 2,142,000 $ 2,382,000 The expected volume is 180,000 direct...
Page 1 of 1 Job Order Costing (Practice B) man Manufacturing Company uses a job order cost system. Degelman applies overhead to production on the basis of direct labor cost. man estimates total manufacturing overhead costs of $505,750, direct labor costs 395,000, and direct labor hours of 17,000 for the fiscal year ended January 31, 2020. on January 1, 2020. Job 50 was the only iob in process. The costs incurred prior to January 1 on Job 50 were as...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,200, direct labor $13,920, and manufacturing overhead $18,560. As of January 1, Job 49 had been completed at a cost of $104,400 and was part of finished goods inventory. There was a $17,400...
Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On Janu 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $24.000, direct labor $14,400, and manufacturing overhead $19,200. As of January 1, Job 49 had been completed at a cost of $108,000 and was part of finished goods inventory. There was a $18,000...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,600, direct labor $12,960, and manufacturing overhead $17,280. As of January 1, Job 49 had been completed at a cost of $97,200 and was part of finished goods inventory. There was a $16,200...