a.) Evaluate a 5-year project costing $32,000 and returning $5,000 annually using the payback period technique and a 4-year cutoff.

b.) Evaluate the project above using the NPV method and a 13% required rate.

c.) Evaluate the project in part "a" using the profitability index method and a 10% required return.

Please show formulas used (not a spreadsheet) and how you worked out the problem, thank you!

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a: The cumulative cash flows are

Year 1 = -32000+5000 = -27000

Year 2 = -27000+5000 = -22000

Year 3 = -22000+5000 = -17000

Year 4 = -17000+5000=-12000

Year 5 = -12000+5000 = -7000

The project cannot be accepted since investment is not recovered till cut off period of year 4

b: NPV= C0+ CF1/(1+r)^1 + CF2/(1+r)^2 …………CFn/(1+r)^n

= -32000+5000/1.13^1+5000/1.13^2+5000/1.13^3+5000/1.13^4+5000/1.13^5=

-14413.84

Reject the project since NPV is negative

c: PI = PV of inflows/Initial cost = 5000/1.1^1+5000/1.1^2+5000/1.1^3+5000/1.1^4+5000/1.1^5/32000

=0.59

Reject the project since Profitability index is less than 1

Add a comment
Know the answer?
Add Answer to:
Question 1.) a.) Evaluate a 5-year project costing $32,000 and returning $5,000 annually using the payback...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1: Part a: Evaluate a 4 - year project costing $25,000 and returning $8,000 annually...

    Question 1: Part a: Evaluate a 4 - year project costing $25,000 and returning $8,000 annually using the payback period technique and a 3-year cutoff. Part b: Evaluate the project above using the NPV method and a 12% required rate. Part c: Evaluate the project in part "a" using the IRR method and a 10% required rate. Please show written work (if possible) and formulas used, thank you!

  • Question 1: Part a: Evaluate a 4 - year project costing $25,000 and returning $8,000 annually...

    Question 1: Part a: Evaluate a 4 - year project costing $25,000 and returning $8,000 annually using the payback period technique and a 3-year cutoff. Answer: 3.125 Years Part b: Evaluate the project in Problem #1 using the profitability index method and a 10% required return. Part c: Evaluate the project in part "a" using the IRR method and a 10% required rate Please show work and formula used

  • 1. Evaluate a 4-year project costing $25,000 and returning $8000 annually using the payback period technique...

    1. Evaluate a 4-year project costing $25,000 and returning $8000 annually using the payback period technique and a 3- year cutoff. (5) 2. Evaluate the project above using the NPV method and a 12% required rate. (10) 3. Bonus: Evaluate the project in Problem #1 using the IRR method and a 10% required rate. (5)

  • 10A. The profitability index for a project costing $100,000 and returning $32,000 annually for four years...

    10A. The profitability index for a project costing $100,000 and returning $32,000 annually for four years at an opportunity cost of capital of 10% is .... 10B. The profitability index for a project costing $100,000 and returning $40,000 annually for five years at an opportunity cost of capital of 10% is.....

  • Please show your work with the formulas written out. Please answer as if you can not...

    Please show your work with the formulas written out. Please answer as if you can not use a calculator, or only use a four function calculator (because that is how I have to learn it). Do not just put down the calculator keystrokes I need to see every step and number to learn how to do it. 1. Evaluate a 4-year project costing $25,000 and returning $8000 annually using the payback period technique and a 3- year cutoff. (5) 2....

  • a. What is the payback period for Project A? b.What is the payback period for Project...

    a. What is the payback period for Project A? b.What is the payback period for Project B? c. What is the discounted payback period for Project A? d. What is the discounted payback period for Project B? e. What is the NPV for Project A? f. What is the NPV for Project B? g. What is the IRR for Project A? h. What is the IRR for Project B? i. What is the profitability index for Project A? j. What...

  • Senior management asks you to recommend a decision on which project(s) to accept based on the...

    Senior management asks you to recommend a decision on which project(s) to accept based on the cash flow forecasts provided.The firm uses a 3-year cutoff when using the payback method. The hurdle rate used to evaluate capital budgeting projects is 15%. Assume the projects are independent and answer the following: Calculate the payback period for each project. Which project(s) would you accept based on the payback criterion? Calculate the internal rate of return (IRR) for each project. Which projects would...

  • Use investment criteria and capital budgeting techniques to evaluate the following project. The project involves equipment...

    Use investment criteria and capital budgeting techniques to evaluate the following project. The project involves equipment that costs $300,000 and will last five (5) years before it must be replaced. The 5 year project is expected to produce after-tax cash flows of $60,000 in the first year, and increase by $20,000 annually; the after-tax cash flow in year 5 will reach $140,000. The equipment will have no salvage value after five-years. The discount rate is 15%. Do not forget to...

  • PLEASE SHOW ALL WORK 1.  (35 points) You are considering the following two mutually exclusiveprojects. Both projects...

    PLEASE SHOW ALL WORK 1.  (35 points) You are considering the following two mutually exclusiveprojects. Both projects will be depreciated using straight-line depreciation to a zero book value over the life of the project. Neither project has any salvage value. Year Project(A) Project (B) 0 -$30,000 -$30,000 1 13,000 5,000 2 11,000 5,000 3 9,000 5,000 4 7,000 5,000 5 0 5,000 6 7 8 9 10 0 0 0 0 0 5,000 5,000 5,000 5,000 5,000                      The required rate...

  • 6 Instructions Your manager wants you to evaluate two mutually exclusive projects. The cash flows of...

    6 Instructions Your manager wants you to evaluate two mutually exclusive projects. The cash flows of the project is given in the flowing tables. 8 Project 1 $ uomi Cash flow (30,000) 8,000 10,000 11,000 17,000 12,000 + Onm Project 2 Cash flow $ (15,000) 2,000 5,000 7,000 2,000 25,000 20 The required rate of return is 15%. The first step is too evaluate the project using NPV, IRR, payback rule 21 You will do so in each tab named...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT