Review the graph showing the contractor's estimate at completion
(EAC) for the armament Work Breakdown Structure (WBS) element,
along with the Government's optimistic (best case) and pessimistic
(worst case) EACs. Based on the graph, does the contractor's EAC
appear to be reasonable?
(IMAGE DESCRIPTION: EAC chart, with dollars in the millions.
Pessimistic EAC is $7.5M, Optimistic EAC is $5.7M, and Contractor's
EAC is $5.0M.) *
Yes, the contractor?s EAC is below the optimistic EAC calculated by the Government.
It is not possible to tell from the graph where the contractor?s EAC falls.
No, the contractor?s EAC is below the range of EACs calculated by the Government.
No, the contractor?s EAC is above the pessimistic EAC calculated by the Government.
No, the contractor?s EAC is below the range of EACs calculated by the Government.
We see from the graph that the contractor's EAC is below both the optimistic and pessimistic EAC computed by the Government. This shows that it is not realistic since it does not lie between the range computed by the Government.
Review the graph showing the contractor's estimate at completion (EAC) for the armament Work Breakdown Structure...