Question

During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job...

During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$424,200

$820,500

$1,077,000

Estimated costs to complete

585,800

273,500

–0–

Billings to date

297,000

894,000

1,580,000

Collections to date

273,000

816,000

1,419,000

Instructions:

  1. Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
  2. Prepare all necessary journal entries for 2020, 2021, and 2022.
  3. Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

1. Compute the amount of gross profit to be recognised each year, using percentage of completion method.

2020 2021 2022
Contract price $1,580,000 $1,580,000 $1,580,000
Less: Estimated cost to date ($424,200) ($820,500) ($1,077,000)
Estimated cost to complete ($585,800) ($273,500) 0
Estimated total costs ($1,010,000) ($1,094,000) ($1,077,000)
Estimated gross profit $570,000 $486,000 $503,000
Percentage completed 42% 75% 100%
Revenue recognised in prior year - $239,400 $125,100
Total revenue recognised $239,400 $364,500 $503,000
Gross profit recognised $239,400 $125,100 $377,900

2. Journal entries

To record cost of construction

Construction in process(820,500-424,200) $396,300
Materials,cash, payables etc $396,300

To record process Billings

Accounts receivable(894,000-297,000) $597,000
Billings on construction in process $597,000

To record collections

Cash(816,000-273,000) $543,000
Accounts receivable $543,000

To recognise revenue and gross profit

Construction in process $396,300
Construction expenses $125,100
Revenue from long term contracts $521,400

3. Amount of gross profit to be recognised each year, assuming the completed-contract method

2020 2021 2022

Gross profit recognised

(1,600,000-1,077,000)

0 0 $503,000

____×____

All the best

Add a comment
Know the answer?
Add Answer to:
During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

  • During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The job...

    During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $373,700 $902,000 $1,070,000 Estimated costs to complete 636,300 198,000 –0– Billings to date 303,000 899,000 1,620,000 Collections to date 273,000 807,000 1,412,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amountenter...

  • During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

  • During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...

  • Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000....

    Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available. 20172018 2019 Costs incurred to date Estimated costs to complete Billings to date Collections to date $366,300 $802,270 $1,080,000 623,700 296,730 297,000 906,000 1,580,000 270,000 802,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 Gross profit recognized in...

  • During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job...

    During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...

  • During 2020, Sunland Company started a construction job with a contract price of $1.590,000. The job...

    During 2020, Sunland Company started a construction job with a contract price of $1.590,000. The job was completed in 2022. The following information is available Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 2021 2022 $410,000 $901,180 $1,067.000 590.000 197,820 -0- 297.000 903,000 1.590,000 271.000 805,000 1.434.000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used Gross profit recognized in 2020 $ Gross profit recognized...

  • During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job...

    During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $380,000 $847,770 $1,069,000 Estimated costs to complete 620,000 253,230 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 272,000 812,000 1,418,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...

  • During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was complete...

    During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...

  • Pronghorn Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Pronghorn Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $894,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $274,160 $417,200 $607,000 Estimated costs to complete 321,840 178,800 –0– Progress billings to date 272,000 550,000 894,000 Cash collected to date...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT