During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job was completed in 2022. The following information is available.
|
2020 |
2021 |
2022 |
||||
|
Costs incurred to date |
$424,200 |
$820,500 |
$1,077,000 |
|||
|
Estimated costs to complete |
585,800 |
273,500 |
–0– |
|||
|
Billings to date |
297,000 |
894,000 |
1,580,000 |
|||
|
Collections to date |
273,000 |
816,000 |
1,419,000 |
Instructions:
1. Compute the amount of gross profit to be recognised each year, using percentage of completion method.
| 2020 | 2021 | 2022 | |
| Contract price | $1,580,000 | $1,580,000 | $1,580,000 |
| Less: Estimated cost to date | ($424,200) | ($820,500) | ($1,077,000) |
| Estimated cost to complete | ($585,800) | ($273,500) | 0 |
| Estimated total costs | ($1,010,000) | ($1,094,000) | ($1,077,000) |
| Estimated gross profit | $570,000 | $486,000 | $503,000 |
| Percentage completed | 42% | 75% | 100% |
| Revenue recognised in prior year | - | $239,400 | $125,100 |
| Total revenue recognised | $239,400 | $364,500 | $503,000 |
| Gross profit recognised | $239,400 | $125,100 | $377,900 |
2. Journal entries
To record cost of construction
| Construction in process(820,500-424,200) | $396,300 | |
| Materials,cash, payables etc | $396,300 |
To record process Billings
| Accounts receivable(894,000-297,000) | $597,000 | |
| Billings on construction in process | $597,000 |
To record collections
| Cash(816,000-273,000) | $543,000 | |
| Accounts receivable | $543,000 |
To recognise revenue and gross profit
| Construction in process | $396,300 | |
| Construction expenses | $125,100 | |
| Revenue from long term contracts | $521,400 |
3. Amount of gross profit to be recognised each year, assuming the completed-contract method
| 2020 | 2021 | 2022 | |
|
Gross profit recognised (1,600,000-1,077,000) |
0 | 0 | $503,000 |
____×____
All the best
During 2020, Pronghorn Company started a construction job with a contract price of $1,580,000. The job...
During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Pharoah Company started a construction job with a
contract price of $1,620,000. The job was completed in 2022. The
following information is available.
2020
2021
2022
Costs incurred to date
$373,700
$902,000
$1,070,000
Estimated costs to complete
636,300
198,000
–0–
Billings to date
303,000
899,000
1,620,000
Collections to date
273,000
807,000
1,412,000
Compute the amount of gross profit to be recognized each year,
assuming the percentage-of-completion method is used.
Gross profit recognized in 2020
$enter a dollar amountenter...
During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
Question 1 During 2017, Nash Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available. 20172018 2019 Costs incurred to date Estimated costs to complete Billings to date Collections to date $366,300 $802,270 $1,080,000 623,700 296,730 297,000 906,000 1,580,000 270,000 802,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 Gross profit recognized in...
During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
During 2020, Sunland Company started a construction job with a contract price of $1.590,000. The job was completed in 2022. The following information is available Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 2021 2022 $410,000 $901,180 $1,067.000 590.000 197,820 -0- 297.000 903,000 1.590,000 271.000 805,000 1.434.000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $380,000 $847,770 $1,069,000 Estimated costs to complete 620,000 253,230 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 272,000 812,000 1,418,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
Pronghorn Construction Company has entered into a contract
beginning January 1, 2020, to build a parking complex. It has been
estimated that the complex will cost $596,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $894,000. The following data pertain to the construction
period.
2020
2021
2022
Costs to date
$274,160
$417,200
$607,000
Estimated costs to complete
321,840
178,800
–0–
Progress billings to date
272,000
550,000
894,000
Cash collected to date...