The following data relate to direct labor costs for the current
period:
| Standard costs | 7,500 hours at $11.70 |
| Actual costs | 6,000 hours at $12.00 |
What is the direct labor time variance?
a.$18,000 unfavorable
b.$18,000 favorable
c.$17,550 unfavorable
d.$17,550 favorable
|
Labor time variance = (SH - AH) * SR = (7500 - 6000) * 11.70 = 17550 F Option D is the answer |
|
The following data relate to direct labor costs for the current period: Standard costs 7,500 hours...
The following data relate to direct labor costs for the current period: Standard costs 7,500 hours at $11.70 Actual costs 6,000 hours at $12.00 The direct labor time variance is a.$18,000 favorable b.$17,550 favorable c.$18,000 unfavorable d.$17,550 unfavorable
The following data relate to direct labor costs for the current period: Standard costs Actual costs 6,900 hours at $11.70 6,400 hours at $10.20 What is the direct labor rate variance? a. $15,450 unfavorable b. 59,600 favorable C. $15,450 favorable Od. 55,850 favorable
The following data relate to direct labor costs for the current period: Standard costs 7,100 hours at $11.60 6,300 hours at $10.50 Actual costs What is the direct labor time variance? Oa. $9,280 unfavorable Ob. $8,400 favorable Oc. $8,400 unfavorable Od. $9,280 favorable
The following data relate to direct labor costs for the current period: Standard costs Actual costs 36,000 hours at $22.00 35,000 hours at $23.00 What is the direct labor time variance? a. $35,000 unfavorable Ob. $36,000 unfavorable Oc. $22,000 favorable od. $23,000 favorable
The following data relate to direct labor costs for February: Actual costs 7,700 hours at $14 Standard costs 7,000 hours at $15 What is the direct labor rate variance? Group of answer choices $7,700 favorable $7,000 favorable $7,700 unfavorable $7,000 unfavorable
The following data relate to direct labor costs for August: Actual costs: 5,500 hours at $24.00 per hour. Standard costs: 5,000 hours at $23.70 per hour. What is the direct labor rate variance? Oa. $1,500 favorable ob. $1,650 favorable OC. $1,500 unfavorable od. $1,650 unfavorable
A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...
The standard costs and actual costs for direct labor in the manufacture of 2,500 units of product are as follows: Standard Costs Direct labor 7,500 hours @ $11.80 Actual Costs Direct labor 7,400 hours @ $11.40 The direct labor time variance is a.$1,140 favorable b.$1,180 unfavorable c.$1,180 favorable d.$1,140 unfavorable
The standard costs and actual costs for direct labor in the manufacture of 2,500 units of product are as follows: Standard Costs Direct labor 7,500 hours at $11.80 Actual Costs Direct labor 7,400 hours at $11.40 The direct labor time variance is a.$1,180 favorable b.$1,140 favorable c.$1,180 unfavorable d.$1,140 unfavorable
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.04 Standard yards per unit: standard, 4.63 yards; actual, 4.91 yards Units of production: 9,100 Calculate the direct materials quantity variance. a.$5,045.04 favorable b.$5,045.04 unfavorable c.$5,197.92 unfavorable d.$5,197.92 favorable Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 971 units were actually produced. Labor standards were...