The following data relate to direct materials costs for
February:
Materials cost per yard: standard, $1.98; actual, $2.04
Standard yards per unit: standard, 4.63 yards; actual, 4.91
yards
Units of production: 9,100
Calculate the direct materials quantity variance.
a.$5,045.04 favorable
b.$5,045.04 unfavorable
c.$5,197.92 unfavorable
d.$5,197.92 favorable
Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 971 units were actually produced. Labor standards were 7.4 hours per completed unit at a standard rate of $12.75 per hour.
Round your answer to the nearest cent.
The direct labor time variance is
$2,718.80 unfavorable
$2,718.80 favorable
$7,428.15 unfavorable
$7,428.15 favorable
The following data are given for Bahia Company:
| Budgeted production (at 100% of normal capacity) | 1,049 units |
| Actual production | 956 units |
| Materials: | |
| Standard price per pound | $1.93 |
| Standard pounds per completed unit | 12 |
| Actual pounds purchased and used in production | 11,128 |
| Actual price paid for materials | $22,812 |
| Labor: | |
| Standard hourly labor rate | $14.95 per hour |
| Standard hours allowed per completed unit | 4.6 |
| Actual labor hours worked | 4,923.4 |
| Actual total labor costs | $75,082 |
| Overhead: | |
| Actual and budgeted fixed overhead | $1,038,000 |
| Standard variable overhead rate | $27.00 per standard labor hour |
| Actual variable overhead costs | $137,855 |
| Overhead is applied on standard labor hours. | |
Round your final answer to the nearest dollar.
The fixed factory overhead volume variance is
a.$92,024 unfavorable
b.$92,024 favorable
c.$19,120 unfavorable
d.$19,120 favorable
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98;...
Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.03 Standard yards per unit: standard, 4.62 yards; actual, 5.06 yards Units of production: 9,100 Calculate the direct materials quantity variance. a.$8,128.12 favorable b.$7,927.92 unfavorable c.$7,927.92 favorable d.$8,128.12 unfavorable Myers Corporation has the following data related to direct materials costs for November: actual costs for 4,600 pounds of material, $5.00 and standard costs for...
A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.93; actual, $2.05 Yards per unit: standard, 4.63 yards; actual, 5.07 yards Units of production: 9,300 The direct materials quantity variance is a. $7,897.56 favorable b. $7,897.56 unfavorable c. $8,388.60 unfavorable d. $8,388.60 favorable
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.93 Actual, $2.04 Standard yards per unit: Standard, 4.74 yards; actual, 4.95 yards Units of production: 9,100 Calculate the Direct materials price variance A. $3,898.44 Favorable B. $3,688.23 Unfavorable C. $3,688.23 Favorable D. $3,898.44 Unfavorable
The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production 906 units Materials: Standard price per pound $1.866 Standard pounds per completed unit 11 Actual pounds purchased and used in production 9,667 Actual price paid for materials $19,817 Labor: Standard hourly labor rate $14.62 per hour Standard hours allowed per completed unit 4.0 Actual labor hours worked 4,665.9 Actual total labor costs $71,155 Overhead: Actual and budgeted fixed overhead $1,181,000 Standard variable overhead rate $26.00...
The following data is given for the Bahia Company: Budgeted production (at 100% of normal capacity) 1,077 units Actual production 917 units Materials: Standard price per pound $1.76 Standard pounds per completed unit 12 Actual pounds purchased and used in production 10,674 Actual price paid for materials $21,882 Labor: Standard hourly labor rate $14.01 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,722.55 Actual total labor costs $72,019 Overhead: Actual and budgeted fixed overhead $1,035,000...
1,005 units 956 units $1.90 11 10,201 $20,912 The following data are given for Bahia Company: Budgeted production (at 100% of normal capacity) Actual production Materials: Standard price per pound Standard pounds per completed unit Actual pounds purchased and used in production Actual price paid for materials Labor: Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked Actual total labor costs Overhead: Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs...
1)
2)
3)
4)
5)
A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...
Flapjack Corporation had 7,921 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 984 units were actually produced. Labor standards were 7.4 hours per completed unit at a standard rate of $12.77 per hour. The direct labor rate variance is $6,099.17 unfavorable $6,099.17 favorable $8,177.70 unfavorable $8,177.70 favorable