Question

Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Compa


Use this information to answer the question that follow. The following data relate to direct materials costs for February: Ma
Japan Company produces lamps that require 2 standard hours per unit at an hourly rate of $19.30 per hout Production of 5,600
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Standard Price per ounce =$1.77
Standard quantity =1061 units*10 =10,610 ounce
Actual Price per pound =$2.05
Actual quantity =10,928 pounds
Material Price variance = (Standard price - Actual Price)*Actual quantity
Material Price variance = ($1.77 - $2.05)*10,928 =$3,059.84(U)
So Option A is answer
Standard Price per yard =$1.92
Standard quantity =9000 units*4.61 =41,490 yards
Actual Price per pound =$2.03
Actual quantity =46,620 yards
Material quantity variance = Standard price(Standard Quantity - Actual Quantity)
Material quantity variance = $1.92(41,490 yards - 46,620 yards) =$9,849.60(U)
So Option D is answer
Standard Rate per hour =$19.30 per hour
Standard Hours =2.80 hours*3,500 =11,200 hours
Actual Rate per hour =$18.90 per hour
Actual hours worked =11,420 hours
Labor rate variance =Actual hours(Standard rate - Actual rate)
Labor efficiency variance =Standard Rate(Actual Hours - Standard Hours)
Direct labor variance =(Standard rate*Standard hours) - (Actual Rate*Actual hours)
Labor rate variance =11,420 hours*($19.30 - $18.90) =$4,568(F)
Labor efficiency variance =$19.30*(11,420 - 11,200) =$4,246(U)
Direct labor variance =($19.30*11,200) - ($18.90*11,420) =$322(F)
Add a comment
Know the answer?
Add Answer to:
Use this information for Stringer Company to answer the question that follow. The following data are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use this information for Stringer Company to answer the question that follow. The following data are...

    Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 920 units Actual production   1,021 units Materials:     Standard price per ounce $1.81     Standard ounces per completed unit 11     Actual ounces purchased and used in production 11,568     Actual price paid for materials $23,714 Labor:     Standard hourly labor rate $14.51 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,258.15     Actual total labor costs $80,187 Overhead:...

  • The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units...

    The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units Materials:     Standard price per ounce $1.82     Standard ounces per completed unit 12     Actual ounces purchased and used in production 12,805     Actual price paid for materials $26,250 Labor:     Standard hourly labor rate $14.95 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,335.4     Actual total labor costs $81,365 Overhead:     Actual and budgeted fixed overhead $1,110,000     Standard variable overhead rate $28.00 per...

  • The following data is given for the Stringer Company: Budgeted production 900 units Actual production   1,056...

    The following data is given for the Stringer Company: Budgeted production 900 units Actual production   1,056 units Materials:     Standard price per ounce $1.9     Standard ounces per completed unit 12     Actual ounces purchased and used in production 13,052     Actual price paid for materials $26,757 Labor:     Standard hourly labor rate $14.30 per hour     Standard hours allowed per completed unit 5.0     Actual labor hours worked 5,438.4     Actual total labor costs $82,936 Overhead:     Actual and budgeted fixed overhead $1,153,000     Standard variable overhead rate $28.00...

  • Use this information to answer the question that follow. The following data relate to direct materials...

    Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.03 Standard yards per unit: standard, 4.62 yards; actual, 5.06 yards Units of production: 9,100 Calculate the direct materials quantity variance. a.$8,128.12 favorable b.$7,927.92 unfavorable c.$7,927.92 favorable d.$8,128.12 unfavorable Myers Corporation has the following data related to direct materials costs for November: actual costs for 4,600 pounds of material, $5.00 and standard costs for...

  • 22. The following data is given for the Stringer Company: Budgeted production 917 units Actual production...

    22. The following data is given for the Stringer Company: Budgeted production 917 units Actual production   1,002 units Materials:     Standard price per ounce $1.75     Standard ounces per completed unit 11     Actual ounces purchased and used in production 11,353     Actual price paid for materials $23,274 Labor:     Standard hourly labor rate $14.38 per hour     Standard hours allowed per completed unit 5.0     Actual labor hours worked 5,160.3     Actual total labor costs $78,695 Overhead:     Actual and budgeted fixed overhead $1,124,000     Standard variable overhead rate...

  • The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98;...

    The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.04 Standard yards per unit: standard, 4.63 yards; actual, 4.91 yards Units of production: 9,100 Calculate the direct materials quantity variance. a.$5,045.04 favorable b.$5,045.04 unfavorable c.$5,197.92 unfavorable d.$5,197.92 favorable Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 971 units were actually produced. Labor standards were...

  • The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units...

    The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units Materials:     Standard price per ounce $1.919     Standard ounces per completed unit 11     Actual ounces purchased and used in production 10,616     Actual price paid for materials $21,763 Labor:     Standard hourly labor rate $14.76 per hour     Standard hours allowed per completed unit 4.3     Actual labor hours worked 4,826     Actual total labor costs $78,423 Overhead:     Actual and budgeted fixed overhead $1,025,000     Standard variable overhead rate $24.00 per...

  • 1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the...

    1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...

  • Use this information to answer the question that follow. The following data relate to direct materials...

    Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.94; actual, $2.05 Standard yards per unit: standard, 4.60 yards; actual, 5.20 yards Units of production: 9,100 Calculate the direct materials price variance. Oa. $5,205.20 favorable Ob. $4,604.60 favorable Oc. $1,001.00 unfavorable Od. $5,205.20 unfavorable

  • The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production   906...

    The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production   906 units Materials:     Standard price per pound $1.866     Standard pounds per completed unit 11      Actual pounds purchased and used in production 9,667     Actual price paid for materials $19,817 Labor:     Standard hourly labor rate $14.62 per hour     Standard hours allowed per completed unit 4.0      Actual labor hours worked 4,665.9     Actual total labor costs $71,155 Overhead:     Actual and budgeted fixed overhead $1,181,000     Standard variable overhead rate $26.00...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT