Question

The following data is given for the Stringer Company: Budgeted production 900 units Actual production   1,056...

The following data is given for the Stringer Company:

Budgeted production 900 units
Actual production   1,056 units
Materials:
    Standard price per ounce $1.9
    Standard ounces per completed unit 12
    Actual ounces purchased and used in production 13,052
    Actual price paid for materials $26,757
Labor:
    Standard hourly labor rate $14.30 per hour
    Standard hours allowed per completed unit 5.0
    Actual labor hours worked 5,438.4
    Actual total labor costs $82,936
Overhead:
    Actual and budgeted fixed overhead $1,153,000
    Standard variable overhead rate $28.00 per standard labor hour
    Actual variable overhead costs $152,275
Overhead is applied on standard labor hours.

The direct materials quantity variance is


0 0
Add a comment Improve this question Transcribed image text
Answer #1

Materials Quantity Variance

= (Standard Quantity - Actual quantity) * Standard price

= (1056*12 - 13052) * 1.9

= (12,672 - 13,052) * 1.9

= 722 Unfavorable

Add a comment
Know the answer?
Add Answer to:
The following data is given for the Stringer Company: Budgeted production 900 units Actual production   1,056...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units...

    The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units Materials:     Standard price per ounce $1.82     Standard ounces per completed unit 12     Actual ounces purchased and used in production 12,805     Actual price paid for materials $26,250 Labor:     Standard hourly labor rate $14.95 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,335.4     Actual total labor costs $81,365 Overhead:     Actual and budgeted fixed overhead $1,110,000     Standard variable overhead rate $28.00 per...

  • 22. The following data is given for the Stringer Company: Budgeted production 917 units Actual production...

    22. The following data is given for the Stringer Company: Budgeted production 917 units Actual production   1,002 units Materials:     Standard price per ounce $1.75     Standard ounces per completed unit 11     Actual ounces purchased and used in production 11,353     Actual price paid for materials $23,274 Labor:     Standard hourly labor rate $14.38 per hour     Standard hours allowed per completed unit 5.0     Actual labor hours worked 5,160.3     Actual total labor costs $78,695 Overhead:     Actual and budgeted fixed overhead $1,124,000     Standard variable overhead rate...

  • The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units...

    The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units Materials:     Standard price per ounce $1.919     Standard ounces per completed unit 11     Actual ounces purchased and used in production 10,616     Actual price paid for materials $21,763 Labor:     Standard hourly labor rate $14.76 per hour     Standard hours allowed per completed unit 4.3     Actual labor hours worked 4,826     Actual total labor costs $78,423 Overhead:     Actual and budgeted fixed overhead $1,025,000     Standard variable overhead rate $24.00 per...

  • Use this information for Stringer Company to answer the question that follow. The following data are...

    Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 920 units Actual production   1,021 units Materials:     Standard price per ounce $1.81     Standard ounces per completed unit 11     Actual ounces purchased and used in production 11,568     Actual price paid for materials $23,714 Labor:     Standard hourly labor rate $14.51 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,258.15     Actual total labor costs $80,187 Overhead:...

  • Use this information for Stringer Company to answer the question that follow. The following data are...

    Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...

  • The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production   906...

    The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production   906 units Materials:     Standard price per pound $1.866     Standard pounds per completed unit 11      Actual pounds purchased and used in production 9,667     Actual price paid for materials $19,817 Labor:     Standard hourly labor rate $14.62 per hour     Standard hours allowed per completed unit 4.0      Actual labor hours worked 4,665.9     Actual total labor costs $71,155 Overhead:     Actual and budgeted fixed overhead $1,181,000     Standard variable overhead rate $26.00...

  • The following data is given for the Bahia Company: Budgeted production (at 100% of normal capacity)...

    The following data is given for the Bahia Company: Budgeted production (at 100% of normal capacity) 1,077 units Actual production   917 units Materials:     Standard price per pound $1.76     Standard pounds per completed unit 12     Actual pounds purchased and used in production 10,674     Actual price paid for materials $21,882 Labor:     Standard hourly labor rate $14.01 per hour     Standard hours allowed per completed unit 4.3     Actual labor hours worked 4,722.55     Actual total labor costs $72,019 Overhead:     Actual and budgeted fixed overhead $1,035,000...

  • 2. The following data have been provided by Lopus Corporation: Budgeted production Standard machine-hours per unit Sta...

    2. The following data have been provided by Lopus Corporation: Budgeted production Standard machine-hours per unit Standard lubricants Standard supplies 4,000 units 4.1 machine-hours 5.60 per machine-hour 4.30 per machine-hour $ $ Actual production Actual machine-hours Actual lubricants (total) Actual supplies (total) 4,300 units 9,480 machine-hours $ 54,833 $40,239 Required: Compute the variable overhead rate variances for lubricants and for supplies. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect...

  • 1,005 units 956 units $1.90 11 10,201 $20,912 The following data are given for Bahia Company:...

    1,005 units 956 units $1.90 11 10,201 $20,912 The following data are given for Bahia Company: Budgeted production (at 100% of normal capacity) Actual production Materials: Standard price per pound Standard pounds per completed unit Actual pounds purchased and used in production Actual price paid for materials Labor: Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked Actual total labor costs Overhead: Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs...

  • 1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the...

    1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT