-
The following data are given for Stringer Company:
Budgeted production
909 units
Actual production
1,036 units
Materials:
Standard price per ounce
$1.82
Standard ounces per completed unit
12
Actual ounces purchased and used in
production
12,805
Actual price paid for materials
$26,250
Labor:
Standard hourly labor rate
$14.95 per hour
Standard hours allowed per completed
unit
4.4
Actual labor hours worked
5,335.4
Actual total labor costs
$81,365
Overhead:
Actual and budgeted fixed overhead
$1,110,000
Standard variable overhead rate
$28.00 per...
-
22.
The following data is given for the Stringer Company:
Budgeted production
917 units
Actual production
1,002 units
Materials:
Standard price per ounce
$1.75
Standard ounces per completed unit
11
Actual ounces purchased and used in
production
11,353
Actual price paid for materials
$23,274
Labor:
Standard hourly labor rate
$14.38 per hour
Standard hours allowed per completed
unit
5.0
Actual labor hours worked
5,160.3
Actual total labor costs
$78,695
Overhead:
Actual and budgeted fixed overhead
$1,124,000
Standard variable overhead rate...
-
The following data are given for Harry Company:
Budgeted production
1,054 units
Actual production
937 units
Materials:
Standard price per ounce
$1.919
Standard ounces per completed unit
11
Actual ounces purchased and used in
production
10,616
Actual price paid for materials
$21,763
Labor:
Standard hourly labor rate
$14.76 per hour
Standard hours allowed per completed
unit
4.3
Actual labor hours worked
4,826
Actual total labor costs
$78,423
Overhead:
Actual and budgeted fixed overhead
$1,025,000
Standard variable overhead rate
$24.00 per...
-
Use this information for Stringer Company to answer the
question that follow.
The following data are given for Stringer Company:
Budgeted production
920 units
Actual production
1,021 units
Materials:
Standard price per ounce
$1.81
Standard ounces per completed unit
11
Actual ounces purchased and used in
production
11,568
Actual price paid for materials
$23,714
Labor:
Standard hourly labor rate
$14.51 per hour
Standard hours allowed per completed
unit
4.4
Actual labor hours worked
5,258.15
Actual total labor costs
$80,187
Overhead:...
-
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...
-
The following data is given for the Bahia Company:
Budgeted production
1,040 units
Actual production
906 units
Materials:
Standard price per pound
$1.866
Standard pounds per completed unit
11
Actual pounds purchased and used
in production
9,667
Actual price paid for materials
$19,817
Labor:
Standard hourly labor rate
$14.62 per hour
Standard hours allowed per completed
unit
4.0
Actual labor hours worked
4,665.9
Actual total labor costs
$71,155
Overhead:
Actual and budgeted fixed overhead
$1,181,000
Standard variable overhead rate
$26.00...
-
The following data is given for the Bahia Company:
Budgeted production (at 100% of normal capacity)
1,077 units
Actual production
917 units
Materials:
Standard price per pound
$1.76
Standard pounds per completed unit
12
Actual pounds purchased and used in
production
10,674
Actual price paid for materials
$21,882
Labor:
Standard hourly labor rate
$14.01 per hour
Standard hours allowed per completed
unit
4.3
Actual labor hours worked
4,722.55
Actual total labor costs
$72,019
Overhead:
Actual and budgeted fixed overhead
$1,035,000...
-
2.
The following data have been provided by Lopus Corporation: Budgeted production Standard machine-hours per unit Standard lubricants Standard supplies 4,000 units 4.1 machine-hours 5.60 per machine-hour 4.30 per machine-hour $ $ Actual production Actual machine-hours Actual lubricants (total) Actual supplies (total) 4,300 units 9,480 machine-hours $ 54,833 $40,239 Required: Compute the variable overhead rate variances for lubricants and for supplies. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect...
-
1,005 units 956 units $1.90 11 10,201 $20,912 The following data are given for Bahia Company: Budgeted production (at 100% of normal capacity) Actual production Materials: Standard price per pound Standard pounds per completed unit Actual pounds purchased and used in production Actual price paid for materials Labor: Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked Actual total labor costs Overhead: Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs...
-
1)
2)
3)
4)
5)
A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...