Use this information to answer the question that
follow.
The following data relate to direct materials costs for
February:
Materials cost per yard: standard, $1.98; actual, $2.03
Standard yards per unit: standard, 4.62 yards; actual, 5.06
yards
Units of production: 9,100
Calculate the direct materials quantity variance.
a.$8,128.12 favorable
b.$7,927.92 unfavorable
c.$7,927.92 favorable
d.$8,128.12 unfavorable
Myers Corporation has the following data related to direct materials costs for November: actual costs for 4,600 pounds of material, $5.00 and standard costs for 4,470 pounds of material at $6.10 per pound.
What is the direct materials quantity variance?
a.$793 unfavorable
b.$5,060 favorable
c.$5,060 unfavorable
d.$793 favorable
Flapjack Corporation had 7,696 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 956 units were actually produced. Labor standards were 7.4 hours per completed unit at a standard rate of $12.96 per hour.
The direct labor rate variance is
$4,309.76 unfavorable
$4,309.76 favorable
$7,709.02 unfavorable
$7,709.02 favorable
| direct material quantity variance = (standard quantity-actual quantity)*standard price | ||||||||
| standarad quantity = (9100*4.62) = 42042 | ||||||||
| actual quantity = (9100*5.06) = 46046 | ||||||||
| quantity variance = (42042-46046)*1.98 = 7927.92 U | ||||||||
| Option "c" is correct | ||||||||
| direct material quantity variance = (standard quantity-actual quantity)*standard price | ||||||||
| direct material quantity variance = (4470-4600)*6.10 = 793 Unfavorable | ||||||||
| Option "a" is correct | ||||||||
| Direct labor rate variance = (standard rate-actual rate)*actual hour | ||||||||
| direct labor rate variance = (12.96-12.40)*7696 = 4309.76 Favorable | ||||||||
| Option "b" is correct | ||||||||
Please give a thumbs up if it is helpful & let me know if any doubt
Use this information to answer the question that follow. The following data relate to direct materials...
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.04 Standard yards per unit: standard, 4.63 yards; actual, 4.91 yards Units of production: 9,100 Calculate the direct materials quantity variance. a.$5,045.04 favorable b.$5,045.04 unfavorable c.$5,197.92 unfavorable d.$5,197.92 favorable Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 971 units were actually produced. Labor standards were...
Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.94; actual, $2.05 Standard yards per unit: standard, 4.60 yards; actual, 5.20 yards Units of production: 9,100 Calculate the direct materials price variance. Oa. $5,205.20 favorable Ob. $4,604.60 favorable Oc. $1,001.00 unfavorable Od. $5,205.20 unfavorable
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.93; actual, $2.05 Yards per unit: standard, 4.63 yards; actual, 5.07 yards Units of production: 9,300 The direct materials quantity variance is a. $7,897.56 favorable b. $7,897.56 unfavorable c. $8,388.60 unfavorable d. $8,388.60 favorable
A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...
Myers Corporation has the following data related to direct materials costs for November: actual costs for 4,600 pounds of material, $5.10; and standard costs for 4,410 pounds of material at $6.20 per pound. What is the direct materials price variance? a. $5,060 unfavorable b. $1,178 unfavorable c. $5,060 favorable d. $1,178 favorable
Myers Corporation has the following data related to direct materials costs for November: actual costs for 4,660 pounds of material, $5.20; and standard costs for 4,470 pounds of material at $6.00 per pound. What is the direct materials price variance? a.$1,140 favorable b.$3,728 favorable c.$3,728 unfavorable d.$1,140 unfavorable
The following company information is available. The direct materials quantity variance is: Direct materials used for prodution Standard quantity for units produced Standard cost per gallon of direct material Actual cost per gallon of direct material 35,000 gallons 33,400 gallons $11.00 $11.20 Multiple Choice $17600 unfavorable. $17200 favorable $24,600 unfavorable Multiple Choice $17,600 unfavorable. $17.200 favorable. $24,600 unfavorable. $24,600 favorable. $17,200 unfavorable Use the following data to find the direct labor rate variance if the company produced 3,500 units during...
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.93 Actual, $2.04 Standard yards per unit: Standard, 4.74 yards; actual, 4.95 yards Units of production: 9,100 Calculate the Direct materials price variance A. $3,898.44 Favorable B. $3,688.23 Unfavorable C. $3,688.23 Favorable D. $3,898.44 Unfavorable
The following information describes production activities of Mercer Manufacturing for the year. Actual direct materials used 22,000 lbs. at $4.35 per lb. 6,575 hours for a total of Actual direct labor used $128,870 Actual units produced 36,000 Budgeted standards for each unit produced are 0.50 pounds of direct material at $4.30 per pound and 10 minutes of direct labor at $20.60 per hour. AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price AH...