Question

The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

The Lakeside Company uses a weighted-average process costing system. The following data are available:

Beginning inventory -0-
Units started in production 20,200
Units finished during the period 16,100
Units in process at the end of the period
(complete as to materials,
¼ complete as to labor and overhead)

4,100
Cost of materials used $ 36,180
Labor and overhead costs $ 41,100

Total cost of the 16,100 units finished is:

Multiple Choice

  • $67,477.

  • $71,772.

  • $77,319.

  • $66,852.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Materials Labor and overhead
Unit finished 16100 16100

(+) Equivalent units in the ending inventory [ Ending inventory units * Fraction Completed ]

4100

[ 4100 * 1 ]

1025

[ 4100 * 1 / 4 ]

Equivalent units of production 20200 17125
Materials Labor and overhead
Cost of beginning inventory 0 0
(+) Cost added during the period 36180 41100
Total cost 36180 41100
(/) Equivalent units of production 20200 17125
Cost per equivalent unit 1.7911 2.4000
Materials Labor and overhead Total

Cost of units finished [ Units finished * Cost per equivalent unit ]

28837

[ 16100 * 1.7911 ]

38640

[ 16100 * 2.4000 ]

67477

Answer : $67,477
Add a comment
Know the answer?
Add Answer to:
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 24,000 Units finished during the period 17,900 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 6,100 Cost of materials used $ 60,500 Labor and overhead costs $ 62,480 Total cost of the 17,900 units finished is: Multiple Choice $102,698. $111,447. $123,011. $109,467.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,000 Units finished during the period 16,000 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,000 Cost of materials used $ 35,200 Labor and overhead costs $ 37,400 Equivalent units of production for labor and overhead are: Multiple Choice 20,000. 17,000. 16,000. 19,000.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,000 Units finished during the period 16,000 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,000 Cost of materials used $ 35,200 Labor and overhead costs $ 37,400 Total cost of the 4,000 units of the ending inventory: Multiple Choice $9,240. $14,520. $8,910. $15,840.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 23,800 Units finished during the period 17,900 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,900 Cost of materials used $ 59,130 Labor and overhead costs $ 61,110 Cost per equivalent unit of materials is: Multiple Choice $2.48. $2.57. $3.15. $2.82.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,400 Units finished during the period 16,200 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,200 Cost of materials used $ 37,370 Labor and overhead costs $ 39,675 Cost per equivalent unit of labor and overhead is: $2.07. $1.94. $2.30. $2.45.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 23,000 Units finished during the period 17,500 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,500 Cost of materials used $ 53,750 Labor and overhead costs $ 55,755 Cost per equivalent unit of materials is: $2.95. $2.66. $2.42. $2.34.

  • The Lakeside Company uses a weighted average process costing system. The following data are available: 22,800...

    The Lakeside Company uses a weighted average process costing system. The following data are available: 22,800 17,400 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 5,400 $52,430 $45,060 Cost per equivalent unit of materials is: Multiple Choice O $2.30. O O $2.40. O $2.21. O $198.

  • The Lakeside Company uses a weighted average process costing system. The following data are available: 23,200...

    The Lakeside Company uses a weighted average process costing system. The following data are available: 23,200 17,500 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 5,700 $55,080 $57,075 Total cost of the 17,500 units finished is:

  • The Lakeside Company uses a welghted-average process costing system. The following data are available: -- 23,800...

    The Lakeside Company uses a welghted-average process costing system. The following data are available: -- 23,800 17,800 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 6,000 $59,130 $61,110 Total cost of the 17,800 units finished is: Multiple Choice $109,060. $107,080. $120,272. $100,584

  • The Lakeside Company uses a welghted-average process costing system. The following data are available: -0- 20,000...

    The Lakeside Company uses a welghted-average process costing system. The following data are available: -0- 20,000 16,000 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 4,000 $35,200 $37,400 Total cost of the 4,000 units of the ending Inventory: Multiple Choice $9,240. $14,520. $8.910. $15,840.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT