The Lakeside Company uses a weighted-average process costing system. The following data are available:

Beginning inventory -0-
Units started in production 20,400
Units finished during the period 16,200
Units in process at the end of the period
(complete as to materials,
¼ complete as to labor and overhead)

4,200
Cost of materials used $ 37,370
Labor and overhead costs $ 39,675

Cost per equivalent unit of labor and overhead is:

  • $2.07.

  • $1.94.

  • $2.30.

  • $2.45.

1 0
Add a comment Improve this question Transcribed image text
Answer #1
Cost per Equivalent Unit of Production
Conversion
During the month costs $   39,675.00
Total cost Costs $   39,675.00
÷ Equivalent units of production EUP 17250
Cost per equivalent unit of production $             2.30

Answer: $ 2.30

Workings:

Equivalent Units of Production (EUP) - Weighted Average Method
Units % Conv. EUP- Conv.
Units completed and transferred out 16200 100% 16200
Units in ending inventory 4200 25% 1050
Equivalent units of production 17250

Note: Labor + Overhead = Conversion Cost

Add a comment
Know the answer?
Add Answer to:
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,000 Units finished during the period 16,000 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,000 Cost of materials used $ 35,200 Labor and overhead costs $ 37,400 Equivalent units of production for labor and overhead are: Multiple Choice 20,000. 17,000. 16,000. 19,000.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 23,000 Units finished during the period 17,500 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,500 Cost of materials used $ 53,750 Labor and overhead costs $ 55,755 Cost per equivalent unit of materials is: $2.95. $2.66. $2.42. $2.34.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 23,800 Units finished during the period 17,900 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,900 Cost of materials used $ 59,130 Labor and overhead costs $ 61,110 Cost per equivalent unit of materials is: Multiple Choice $2.48. $2.57. $3.15. $2.82.

  • The Lakeside Company uses a weighted average process costing system. The following data are available: 22,800...

    The Lakeside Company uses a weighted average process costing system. The following data are available: 22,800 17,400 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 5,400 $52,430 $45,060 Cost per equivalent unit of materials is: Multiple Choice O $2.30. O O $2.40. O $2.21. O $198.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,200 Units finished during the period 16,100 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,100 Cost of materials used $ 36,180 Labor and overhead costs $ 41,100 Total cost of the 16,100 units finished is: Multiple Choice $67,477. $71,772. $77,319. $66,852.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 24,000 Units finished during the period 17,900 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 6,100 Cost of materials used $ 60,500 Labor and overhead costs $ 62,480 Total cost of the 17,900 units finished is: Multiple Choice $102,698. $111,447. $123,011. $109,467.

  • The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

    The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,000 Units finished during the period 16,000 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,000 Cost of materials used $ 35,200 Labor and overhead costs $ 37,400 Total cost of the 4,000 units of the ending inventory: Multiple Choice $9,240. $14,520. $8,910. $15,840.

  • The Lakeside Company uses a weighted average process costing system. The following data are available: 23,200...

    The Lakeside Company uses a weighted average process costing system. The following data are available: 23,200 17,500 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 5,700 $55,080 $57,075 Total cost of the 17,500 units finished is:

  • The Lakeside Company uses a welghted-average process costing system. The following data are available: -- 23,800...

    The Lakeside Company uses a welghted-average process costing system. The following data are available: -- 23,800 17,800 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 6,000 $59,130 $61,110 Total cost of the 17,800 units finished is: Multiple Choice $109,060. $107,080. $120,272. $100,584

  • The Lakeside Company uses a welghted-average process costing system. The following data are available: -0- 20,000...

    The Lakeside Company uses a welghted-average process costing system. The following data are available: -0- 20,000 16,000 Beginning inventory Units started in production Units finished during the period Units in process at the end of the period (complete as to materials, % complete as to labor and overhead) Cost of materials used Labor and overhead costs 4,000 $35,200 $37,400 Total cost of the 4,000 units of the ending Inventory: Multiple Choice $9,240. $14,520. $8.910. $15,840.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT