Job Costs Using Activity-Based Costing
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows:
| Activity | Cost | Driver | Amount of Driver | ||
| Materials handling | $92,400 | Number of moves | 4,000 | ||
| Engineering | 93,600 | Number of change orders | 6,000 | ||
| Other overhead | 230,300 | Direct labor hours | 49,000 |
Heitger worked on four jobs in July. Data are as follows:
| Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | |||||
| Beginning balance | $23,900 | $18,200 | $2,000 | $0 | ||||
| Direct materials | $5,400 | $9,100 | $10,200 | $9,800 | ||||
| Direct labor cost | $880 | $1,020 | $1,560 | $120 | ||||
| Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | |||||
| Number of moves | 47 | 53 | 31 | 6 | ||||
| Number of change orders | 33 | 35 | 21 | 15 | ||||
| Direct labor hours | 880 | 1,020 | 1,560 | 120 | ||||
By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.
. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.
| Materials handling rate | |
| Engineering rate | |
| Other overhead rate |
2. Calculate the balance in Work in Process on
July 31.
3. Calculate the cost of goods sold for
July.
4. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46? How would the cost of the other jobs be affected?
Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.
| Activity | Cost | Amount of Driver | Activity Rate | |
| Materials handling | 92,400 | 4,000 | 23.10 | per move |
| Engineering | 93,600 | 6,000 | 15.60 | per change order |
| Other overhead | 2,30,300 | 49,000 | 4.70 | per direct labor hour |
2. Calculate the balance in Work in Process on July 31.
| Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | |
| Beginning balance | 23,900 | 18,200 | 2,000 | 0 |
| Direct materials | 5,400 | 9,100 | 10,200 | 9,800 |
| Direct labor cost | 880 | 1,020 | 1,560 | 120 |
| Material handling @23.10 | 1,086 | 1,224 | 716 | 139 |
| Engineering @ 15.60 | 514.8 | 546 | 327.6 | 234 |
| Other overhead @ 4.70 | 4,136 | 4,794 | 7,332 | 564 |
| Total costs | 35,917 | 34,884 | 22,136 | 10,857 |
| Balance in Work in Process on July 31 | Cost of Jobs |
| Job 13-45 | 22,136 |
| Job 13-46 | 10,857 |
| balance in Work in Process on July 31 | 32,992 |
3. Calculate the cost of goods sold for July.
| Cost of goods sold for July | |
| Job 13-43 | 35,917 |
| Job 13-44 | 34,884 |
| Cost of goods sold for July | 70,801 |
4. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46? How would the cost of the other jobs be affected?
| Job 13-46 | |
| Beginning balance | 0 |
| Direct materials | 9,800 |
| Direct labor cost | 120 |
| Material handling @23.10 | 139 |
| Other overhead @ 4.70 | 564 |
| New Total costs | 10,623 |
The cost of the other jobs will get increased
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $49,400 Number of moves 2,000 Engineering 129,000 Number of change orders 7,500 Other overhead 321,300 Direct labor hours 51,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a
job-order costing firm that uses activity-based costing to apply
overhead to jobs. Heitger identified three overhead activities and
related drivers. Budgeted information for the year is as follows:
Activity Cost Driver Amount of Driver Materials handling $55,000
Number of moves 2,500 Engineering 101,500 Number of change orders
7,000 Other overhead 180,000 Direct labor hours 50,000
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $121,000 Number of moves 5,000 Engineering 125,250 Number of change orders 7,500 Other overhead 272,600 Direct labor hours 47,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $71,100 Number of moves 3,000 Engineering 105,300 Number of change orders 6,500 Other overhead 238,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $56,250 Number of moves 2,500 Engineering 142,500 Number of change orders 9,500 Other overhead 209,100 Direct labor hours 51,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $ 72,000 Number of moves 3,000 Engineering 165,000 Number of change orders 10,000 Other overhead 280,000 Direct labor hours 50,000 Heitger worked on four jobs in July. Data are as follows: Beginning balance $0 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $56,250 Number of moves 2,500 Engineering 142,500 Number of change orders 9,500 Other overhead 209,100 Direct labor hours 51,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $48,200 Number of moves 2,000 Engineering 157,700 Number of change orders 9,500 Other overhead 256,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance...
How would you answer this?
Calculator Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $ 72,000 Number of moves 3,000 Engineering Number of change orders 10,000 165,000 280,000 Other overhead Direct labor hours 50,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job...
Beginning $24,100 $17,600 $3,700 $0 balance Direct $6,000 materials $8,800 $10,500 $9,700 Direct labor $980 cost $980 $1,660 $150 Job 13- Job 13- Job 13- Job 13- 43 44 45 46 Number of moves 43 54 26 5 Number of 29 39 17 16 change orders Direct labor hours 980 980 1,660 150 By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process, Required: 1. Calculate the activity rates for each...