Job Costs Using Activity-Based Costing
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows:
| Activity | Cost | Driver | Amount of Driver | ||
| Materials handling | $56,250 | Number of moves | 2,500 | ||
| Engineering | 142,500 | Number of change orders | 9,500 | ||
| Other overhead | 209,100 | Direct labor hours | 51,000 |
Heitger worked on four jobs in July. Data are as follows:
| Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | |||||
| Beginning balance | $21,400 | $19,400 | $4,500 | $0 | ||||
| Direct materials | $5,600 | $9,700 | $12,700 | $9,600 | ||||
| Direct labor cost | $810 | $990 | $1,700 | $110 | ||||
| Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | |||||
| Number of moves | 43 | 48 | 27 | 7 | ||||
| Number of change orders | 32 | 44 | 24 | 15 | ||||
| Direct labor hours | 810 | 990 | 1,700 | 110 | ||||
By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.
Required:
1. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.
| Materials handling rate | $ per move |
| Engineering rate | $ per change order |
| Other overhead rate | $ per direct labor hour |
Feedback
1. In job-order costing, departmental overhead rates and activity-based costing affect only the application of overhead which is put on the job-order costing sheet and must include all drivers for which overhead is applied.
2. Prepare job-order cost sheets for each job showing all costs through July 31.
When required, round your answers to the nearest dollar. If an amount is zero, enter "0".
| Heitger Company | ||||
| Job-Order Cost Sheets | ||||
| Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | |
| Balance, July 1 | $ | $ | $ | $ |
| Direct materials | ||||
| Direct labor cost | ||||
| Materials handling | ||||
| Engineering | ||||
| Other overhead | ||||
| Total | $ | $ | $ | $ |
3. Calculate the balance in Work in Process on
July 31.
$
4. Calculate the cost of goods sold for
July.
$
5. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46?
$ lower
| 1) | Activity rates | |||||||
| Materials handling rate | 22.5 | per move | ||||||
| engineering rate | 15 | per change order | ||||||
| other overhead rate | 4.1 | per direct labor hour | ||||||
| 2) | Job order cost sheet | |||||||
| job 13-43 | job 13-44 | job13-45 | job 13-46 | |||||
| Balance,july 1 | 21,400 | 19,400 | 4,500 | 0 | ||||
| direct materials | 5,600 | 9,700 | 12,700 | 9,600 | ||||
| direct labor cost | 810 | 990 | 1700 | 110 | ||||
| materials handling | 968 | 1080 | 608 | 158 | ||||
| engineering | 480 | 660 | 360 | 225 | ||||
| other overhead | 3321 | 4059 | 6970 | 451 | ||||
| total | 32,579 | 35,889 | 26,838 | 10,544 | ||||
| 3) | Balance of work in process july 31 | 37,381 | ||||||
| (job 45 and job 46) | ||||||||
| 4) | cost of goods sold for july | 68,468 | ||||||
| (job 43 and 44) | ||||||||
| 5) | difference in cost will be | 225 | ||||||
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $56,250 Number of moves 2,500 Engineering 142,500 Number of change orders 9,500 Other overhead 209,100 Direct labor hours 51,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a
job-order costing firm that uses activity-based costing to apply
overhead to jobs. Heitger identified three overhead activities and
related drivers. Budgeted information for the year is as follows:
Activity Cost Driver Amount of Driver Materials handling $55,000
Number of moves 2,500 Engineering 101,500 Number of change orders
7,000 Other overhead 180,000 Direct labor hours 50,000
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $121,000 Number of moves 5,000 Engineering 125,250 Number of change orders 7,500 Other overhead 272,600 Direct labor hours 47,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $92,400 Number of moves 4,000 Engineering 93,600 Number of change orders 6,000 Other overhead 230,300 Direct labor hours 49,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $71,100 Number of moves 3,000 Engineering 105,300 Number of change orders 6,500 Other overhead 238,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $49,400 Number of moves 2,000 Engineering 129,000 Number of change orders 7,500 Other overhead 321,300 Direct labor hours 51,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $ 72,000 Number of moves 3,000 Engineering 165,000 Number of change orders 10,000 Other overhead 280,000 Direct labor hours 50,000 Heitger worked on four jobs in July. Data are as follows: Beginning balance $0 Job...
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $48,200 Number of moves 2,000 Engineering 157,700 Number of change orders 9,500 Other overhead 256,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance...
How would you answer this?
Calculator Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $ 72,000 Number of moves 3,000 Engineering Number of change orders 10,000 165,000 280,000 Other overhead Direct labor hours 50,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job...
Beginning $24,100 $17,600 $3,700 $0 balance Direct $6,000 materials $8,800 $10,500 $9,700 Direct labor $980 cost $980 $1,660 $150 Job 13- Job 13- Job 13- Job 13- 43 44 45 46 Number of moves 43 54 26 5 Number of 29 39 17 16 change orders Direct labor hours 980 980 1,660 150 By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process, Required: 1. Calculate the activity rates for each...