| Solution 1: | |||
| Weighted-Average accumulated expenditure | |||
| Date | Amount | Capitalization period | Weighted Average Accumulated Expenditures |
| 01 June 2017 | $61,56,000 | 7/12 | $35,91,000 |
| 31 August 2017 | $91,68,000 | 4/12 | $30,56,000 |
| 31 December 2017 | $74,04,000 | 0/7 | $0 |
| Total | $2,27,28,000 | $66,47,000 | |
Solution 2:
| Computation of Avoidable Interest | |||
| Debt | Weighted Average Accumulated Expenditures | Interest rate | Avoidable Interest amount |
| From 9% Bond | $51,90,000 | 9% | $4,67,100 |
| From 12% Note | $12,60,000 | 12% | $1,51,200 |
| Totals | $64,50,000 | $6,18,300 | |
Solution 3:
| Computation of Actual Interest cost incurred | |||
| Debt | Weighted Average Accumulated Expenditures | Interest rate | Actual Interest |
| From 9% Bond (for 7 months) | $51,90,000 | 9% | $2,72,475 |
| From 12% Note | $12,60,000 | 12% | $1,51,200 |
| Totals | $64,50,000 | $4,23,675 | |
| Total amount of Interest cost to be capitalized for 2017 (Lower of actual interest or Avoidable interest) | $4,23,675 | ||
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date Payment June 1, 2017 $2,000,000 August 31, 2017 3,000,000 December 31,2017 2,500,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $1,700,000 of 10-year, 9% bonds payable, issued at par on...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design
and construct a complete modernization of Dobbs's manufacturing
facility. Construction was begun on June 1, 2020 and was completed
on December 31, 2020. Dobbs made the following payments to Kiner,
Inc. during 2020:
Date
Payment
June 1, 2020
$1,680,000
August 31, 2020
2,520,000
December 31, 2020
2,100,000
In order to help finance the construction, Dobbs issued the
following during 2020:
1.
$1,428,000 of 10-year, 9% bonds payable, issued at par...
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date June 1, 2020 August 31, 2020 December 31, 2020 Payment $2,280,000 3,420,000 2,850,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,938,000 of 10-year, 9% bonds payable, issued at par...
Testbank Problem 140
Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design
and construct a complete modernization of Dobbs's manufacturing
facility. Construction was begun on June 1, 2020 and was completed
on December 31, 2020. Dobbs made the following payments to Kiner,
Inc. during 2020:
Date
Payment
June 1, 2020
$2,200,000
August 31, 2020
3,300,000
December 31, 2020
2,750,000
In order to help finance the construction, Dobbs issued the
following during 2020:
1.
$1,870,000 of 10-year, 9% bonds payable,...
Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Payment Date $1,600,000 June 1, 2020 2,400,000 August 31, 2020 December 31, 2020 2,000,000 In order to help finance the construction, Dobbs issued the following during 2020 1. $1,360,000 of 10-year, 9% bonds payable,...
. 2017 and was Question Early in 2017. Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobb's manufacturing facility. Construction was begun completed on December 31, 2017. Dobbs made the following payments to the during 2017: Payment June 1, 2017 $5,772,000 August 31, 2017 9,000,000 December 31, 2017 7,572,000 Date In order to help finance the construction, Dobbs issued the following during 2017: 1. $5.000.000 of 10-year bonds payable, issued at pron May 31, 2017,...
4.
total interest to be capitalize during 2010
Early in 2010, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2010 and was completed on December 31, 2010. Dobbs made the following payments to Kiner, Inc. during 2010: Date Payment June 1, 2010 $3,600,000 August 31, 2010 5,400,000 December 31, 2010 4,500,000 In order to help finance the construction, Dobbs issued the following during 2010: 1. $3,000,000...
Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of Qatar’s manufacturing facility. Construction began on June 1, 2020, and was completed on December 31, 2020. Qatar made the following payments to Emirate Ltd. during 2020: Date Payment June 1, 2020$ 3,300,000 August 31, 20204,800,000 December 31, 20204,000,000 In order to help finance the construction, Qatar issued the following during 2020: 1.$ 2,000,000, ten-year, 9% bonds payable, issued at par on May 31, 2020,...
Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of Qatar’s manufacturing facility. Construction began on June 1, 2020, and was completed on December 31, 2020. Qatar made the following payments to Emirate Ltd. during 2020: Date Payment June 1, 2020$ 3,300,000 August 31, 20204,800,000 December 31, 20204,000,000 In order to help finance the construction, Qatar issued the following during 2020: 1.$ 2,000,000, ten-year, 9% bonds payable, issued at par on May 31, 2020,...
Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of Logan's manufacturing facility. Construction was begun on January 1, 2015 and was completed on December 31, 2015. Logan made the following payments to Reese, Inc. during 2015: Date Payment June 1, 2015 $2,400,000 August 31, 2015 3,600,000 December 31, 2015 3,000,000 In order to help finance the construction, Logan issued $2,000,000 of 10-year, 9% bonds payable, issued at par on January 2, 2015, with...