Question

Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of...

Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of Logan's manufacturing facility. Construction was begun on January 1, 2015 and was completed on December 31, 2015. Logan made the following payments to Reese, Inc. during 2015:

Date

Payment

June 1, 2015

$2,400,000

August 31, 2015

3,600,000

December 31, 2015

3,000,000

In order to help finance the construction, Logan issued $2,000,000 of 10-year, 9% bonds payable, issued at par on January 2, 2015, with interest payable annually on December 31.

In addition to the 9% bonds payable, the only debt outstanding during 2015 was a $500,000, 12% note payable dated January 1, 2010 and due January 1, 2020, with interest payable annually on January 1 and a $1,000,000, 10% bond payable dated July 1, 2011 due June 30, 2021 with interest paid annually.

Compute the amounts of each of the following (show computations):

  1. Weighted-average accumulated expenditures qualifying for capitalization of interest cost. Hint: $2,600,000
  1. Interest to be capitalized in 2015. Logan uses the specific interest method. Hint: $244,200

              

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution 1:

Solution 1:
Weighted-Average accumulated expenditure and interest capitalized
Date Expenditure Weigh Avearge
01 June 2015 $24,00,000 7/12 $14,00,000
31 August 2015 $36,00,000 4/12 $12,00,000
31 December 2015 $30,00,000 0/12 $0
Accumulated Expenditure $90,00,000 $26,00,000

Weighted-average accumulated expenditures = $2,600,000

Solution 2:

Weighted average interest rate of all other debt
Debt Amount Interest rate Interest amount
12% note payable $5,00,000 12% $60,000
10% Bond $10,00,000 10% $1,00,000
Totals $15,00,000 $1,60,000
Weighted average rate (total interets/ total debt) 10.67%
Year 2018: Interest Capitalized
Average Interest Rate Capitalized Interest
Avearge Accumulated Expenditure $26,00,000
Specific $20,00,000 9.00% $1,80,000
Other debt $6,00,000 10.67% $64,020
Total Interest Capitalized $2,44,020
Add a comment
Know the answer?
Add Answer to:
Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date June 1, 2020 August 31, 2020 December 31, 2020 Payment $2,280,000 3,420,000 2,850,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,938,000 of 10-year, 9% bonds payable, issued at par...

  • Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date Payment June 1, 2017 $2,000,000 August 31, 2017 3,000,000 December 31,2017 2,500,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $1,700,000 of 10-year, 9% bonds payable, issued at par on...

  • Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $1,680,000 August 31, 2020 2,520,000 December 31, 2020 2,100,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,428,000 of 10-year, 9% bonds payable, issued at par...

  • Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date June 1, 2017 August 31, 2017 December 31, 2017 Payment $6,156,000 9,168,000 7,404,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $5,190,000 of 10-year, 9% bonds payable, issued at par...

  • Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of...

    Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of Qatar’s manufacturing facility. Construction began on June 1, 2020, and was completed on December 31, 2020. Qatar made the following payments to Emirate Ltd. during 2020: Date Payment June 1, 2020$ 3,300,000 August 31, 20204,800,000 December 31, 20204,000,000 In order to help finance the construction, Qatar issued the following during 2020: 1.$ 2,000,000, ten-year, 9% bonds payable, issued at par on May 31, 2020,...

  • Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of...

    Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of Qatar’s manufacturing facility. Construction began on June 1, 2020, and was completed on December 31, 2020. Qatar made the following payments to Emirate Ltd. during 2020: Date Payment June 1, 2020$ 3,300,000 August 31, 20204,800,000 December 31, 20204,000,000 In order to help finance the construction, Qatar issued the following during 2020: 1.$ 2,000,000, ten-year, 9% bonds payable, issued at par on May 31, 2020,...

  • Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a...

    Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Payment Date $1,600,000 June 1, 2020 2,400,000 August 31, 2020 December 31, 2020 2,000,000 In order to help finance the construction, Dobbs issued the following during 2020 1. $1,360,000 of 10-year, 9% bonds payable,...

  • Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a...

    Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $2,200,000 August 31, 2020 3,300,000 December 31, 2020 2,750,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,870,000 of 10-year, 9% bonds payable,...

  • 4. total interest to be capitalize during 2010 Early in 2010, Dobbs Corporation engaged Kiner, Inc....

    4. total interest to be capitalize during 2010 Early in 2010, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2010 and was completed on December 31, 2010. Dobbs made the following payments to Kiner, Inc. during 2010: Date Payment June 1, 2010 $3,600,000 August 31, 2010 5,400,000 December 31, 2010 4,500,000 In order to help finance the construction, Dobbs issued the following during 2010: 1. $3,000,000...

  • . 2017 and was Question Early in 2017. Dobbs Corporation engaged Kiner, Inc. to design and...

    . 2017 and was Question Early in 2017. Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobb's manufacturing facility. Construction was begun completed on December 31, 2017. Dobbs made the following payments to the during 2017: Payment June 1, 2017 $5,772,000 August 31, 2017 9,000,000 December 31, 2017 7,572,000 Date In order to help finance the construction, Dobbs issued the following during 2017: 1. $5.000.000 of 10-year bonds payable, issued at pron May 31, 2017,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT