Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows:
| At 12-31-2018 | At 12-31-2019 | At 12-31-2020 | |||||||||
| Percentage of completion | 10 | % | 60 | % | 100 | % | |||||
| Costs incurred to date | $ | 368,000 | $ | 2,898,000 | $ | 4,889,000 | |||||
| Estimated costs to complete | 3,312,000 | 1,932,000 | 0 | ||||||||
| Billings to Axelrod, to date | 729,000 | 2,350,000 | 4,540,000 | ||||||||
Required: 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years.
2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years.
3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs
| Please give positive ratings so I can keep answering. Thanks! |
| Curtis Construction Company | 2018 | 2019 | ||||||||||
| Ans to 1 and 2 | Calculation of Gross Profit | Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | ||||||
| Particulars | 2018 | 2019 | 2020 | Costs Incurred | CIP (Work-in-progress) | 368,000 | 2,530,000 | |||||
| Contract Price | 4,540,000 | 4,540,000 | 4,540,000 | A | Cash | 368,000 | 2,530,000 | |||||
| Cost Incurred to date | 368,000 | 2,898,000 | 4,889,000 | B | ||||||||
| Cost Incurred during the year | 368,000 | 2,530,000 | 1,991,000 | C | Billing | Accounts Receivable | 731,000 | 1,621,000 | ||||
| (Cost incurred to date of the present year less Cost incurred to date of the previous year) | Billing on CIP | 731,000 | 1,621,000 | |||||||||
| Estimated cost to complete | 3,312,000 | 1,932,000 | - | D | ||||||||
| Estimated total cost | 3,680,000 | 4,830,000 | 4,889,000 | E=C+B | Period end adjustments for Revenue | Construction Expense | 368,000 | |||||
| (Cost Incurred to date+ Estimated cost to complete ) | (Gross Profit entry) | CIP (Work-in-progress) | 86,000 | |||||||||
| Percentage complete | 10.00% | 60.00% | 100.00% | F=B/E | Construction Revenue | 454,000 | ||||||
| (Cost Incurred to date/Estimated total cost) | ||||||||||||
| Revenue to be recognized | 454,000 | 2,270,000 | 1,816,000 | G | Period end adjustments for Revenue | Construction Expense | 2,530,000 | |||||
| (Contract Price*Percentage complete)- revenue previously recognized | (Gross Profit entry) | CIP (Work-in-progress) | 260,000 | |||||||||
| Year 2018: 10% completed. Revenue recognized = 10% x $ 4,540,000 = $ 454,000. | Construction Revenue | 2,270,000 | ||||||||||
| Year 2019: 60% completed. Revenue recognized = 60% x $ 4,540,000 – $ 454,000 (previously recognized) = $ 2,270,000. | ||||||||||||
| Year 2020: 100% completed. Revenue recognized = 100% x $ 4,540,000 – $ 454,000- $ 2,270,000 (previously recognized) = $ 1,816,000. | ||||||||||||
| Gross Profit/(Loss) | 86,000 | (260,000) | (175,000) | H=G-C | ||||||||
| Billings to date | 729,000.00 | 2,350,000.00 | 4,540,000.00 | |||||||||
| Billings during the year | 731,000.00 | 1,621,000.00 | 2,190,000.00 | |||||||||
| (Billings to date of the present year less Billings to date of the previous year) | ||||||||||||
| Workings for Balance Sheet | ||||||||||||
| Ans to 3 | CIP (Work-in-progress) | |||||||||||
| Balance Sheet (Partial) | 2018 | 2019 | Account | Amount ($) | ||||||||
| Current Assets: | Cash | 368,000 | ||||||||||
| CIP (Work-in-progress) | 454,000 | 2,724,000 | Construction Revenue | 86,000 | ||||||||
| 454,000 | 2,724,000 | Balance at the end of 2018 | 454,000 | |||||||||
| Current Liabilities: | Cash | 2,530,000 | ||||||||||
| Billing on CIP | 731,000.00 | 2,352,000.00 | Construction Revenue | (260,000) | ||||||||
| 731,000.00 | 2,352,000.00 | Balance at the end of 2019 | 2,724,000 | |||||||||
| Billing on CIP | ||||||||||||
| Account | Amount ($) | |||||||||||
| Accounts Receivable | 731,000 | |||||||||||
| Balance at the end of 2018 | 731,000 | |||||||||||
| Accounts Receivable | 1,621,000 | |||||||||||
| Balance at the end of 2019 | 2,352,000 | |||||||||||
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...
Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...
Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...
Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,720,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
Fix
Problem 5-12 Long-term contract; revenue recognized over time;
loss projected on entire project [LO5-9]
Curtiss Construction Company, Inc., entered into a fixed-price
contract with Axelrod Associates on July 1, 2018, to construct a
four-story office building. At that time, Curtiss estimated that it
would take between two and three years to complete the project. The
total contract price for construction of the building is
$4,000,000. Curtiss concludes that the contract does not qualify
for revenue recognition over time. The...
I
need help completing this. Thank you!!
Saved Help Save & Exit Submi Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,660,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated...