Question

Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...

Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows:

At 12-31-2018 At 12-31-2019 At 12-31-2020
Percentage of completion 10 % 60 % 100 %
Costs incurred to date $ 368,000 $ 2,898,000 $ 4,889,000
Estimated costs to complete 3,312,000 1,932,000 0
Billings to Axelrod, to date 729,000 2,350,000 4,540,000

Required: 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years.

2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years.

3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. Thanks!
Curtis Construction Company 2018 2019
Ans to 1 and 2 Calculation of Gross Profit Journal Entries Debit $ Credit $ Debit $ Credit $
Particulars 2018 2019 2020 Costs Incurred CIP (Work-in-progress)       368,000 2,530,000
Contract Price           4,540,000          4,540,000          4,540,000 A Cash       368,000     2,530,000
Cost Incurred to date              368,000          2,898,000          4,889,000 B
Cost Incurred during the year              368,000          2,530,000          1,991,000 C Billing Accounts Receivable       731,000 1,621,000
(Cost incurred to date of the present year less Cost incurred to date of the previous year) Billing on CIP       731,000     1,621,000
Estimated cost to complete           3,312,000          1,932,000                        -   D
Estimated total cost           3,680,000          4,830,000          4,889,000 E=C+B Period end adjustments for Revenue Construction Expense       368,000
(Cost Incurred to date+ Estimated cost to complete ) (Gross Profit entry) CIP (Work-in-progress)         86,000
Percentage complete 10.00% 60.00% 100.00% F=B/E Construction Revenue       454,000
(Cost Incurred to date/Estimated total cost)
Revenue to be recognized              454,000          2,270,000          1,816,000 G Period end adjustments for Revenue Construction Expense 2,530,000
(Contract Price*Percentage complete)- revenue previously recognized (Gross Profit entry) CIP (Work-in-progress)        260,000
Year 2018: 10% completed. Revenue recognized = 10% x $ 4,540,000 = $ 454,000. Construction Revenue     2,270,000
Year 2019: 60% completed. Revenue recognized = 60% x $ 4,540,000 – $ 454,000 (previously recognized) = $ 2,270,000.
Year 2020: 100% completed. Revenue recognized = 100% x $ 4,540,000 – $ 454,000- $ 2,270,000 (previously recognized) = $ 1,816,000.
Gross Profit/(Loss)                86,000           (260,000)            (175,000) H=G-C
Billings to date        729,000.00    2,350,000.00    4,540,000.00
Billings during the year        731,000.00    1,621,000.00    2,190,000.00
(Billings to date of the present year less Billings to date of the previous year)
Workings for Balance Sheet
Ans to 3 CIP (Work-in-progress)
Balance Sheet (Partial) 2018 2019 Account Amount ($)
Current Assets: Cash                                    368,000
CIP (Work-in-progress)              454,000          2,724,000 Construction Revenue                                       86,000
             454,000         2,724,000 Balance at the end of 2018                                    454,000
Current Liabilities: Cash                                 2,530,000
Billing on CIP        731,000.00    2,352,000.00 Construction Revenue                                   (260,000)
       731,000.00 2,352,000.00 Balance at the end of 2019                                 2,724,000
Billing on CIP
Account Amount ($)
Accounts Receivable                                    731,000
Balance at the end of 2018                                    731,000
Accounts Receivable                                 1,621,000
Balance at the end of 2019                                 2,352,000
Add a comment
Know the answer?
Add Answer to:
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...

  • Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates...

    Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...

  • Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on...

    Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company,...

    Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,720,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Cons...

    Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The...

  • I need help completing this. Thank you!! Saved Help Save & Exit Submi Check my work...

    I need help completing this. Thank you!! Saved Help Save & Exit Submi Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,660,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT