| Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
| Westgate Construction Company | ||||
| Workings | Calculation of Gross Profit | |||
| Particulars | 2021 | 2022 | 2023 | |
| Contract Price | 10,000,000 | 10,000,000 | 10,000,000 | A |
| Cost Incurred during the year | 2,490,000 | 3,984,000 | 2,008,600 | C |
| Cost Incurred to date | 2,490,000 | 6,474,000 | 8,482,600 | |
| (Cost incurred to date of the present year less Cost incurred to date of the previous year) | ||||
| Estimated cost to complete | 5,810,000 | 1,826,000 | - | D |
| Estimated total cost | 8,300,000 | 8,300,000 | 8,482,600 | E=C+B |
| (Cost Incurred to date+ Estimated cost to complete ) | ||||
| Percentage complete | 30.00% | 78.00% | 100.00% | F=B/E |
| (Cost Incurred to date/Estimated total cost) | ||||
| Revenue to be recognized | 3,000,000 | 4,800,000 | 2,200,000 | G |
| (Contract Price*Percentage complete)- revenue previously recognized | ||||
| Year 2021: 30% completed. Revenue recognized = 20% x $ 10,000,000 = $ 3,000,000. | ||||
| Year 2022: 78% completed. Revenue recognized = 78% x $ 10,000,000 – $ 3,000,000 (previously recognized) = $ 4,800,000. | ||||
| Year 2023: 100% completed. Revenue recognized = 100% x $ 10,000,000 – $ 3,000,000- $ 3,800,000 (previously recognized) = $ 2,200,000. | ||||
| Gross Profit/(Loss) | 510,000 | 816,000 | 191,400 | H=G-C |
| Billings during the year | 2,030,000.00 | 4,444,000.00 | 3,526,000.00 | |
| Cash collections during the year | 1,815,000.00 | 3,900,000.00 | 4,285,000.00 |
| 2021 | 2022 | 2023 | |||||||
| Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | Debit $ | Credit $ | |||
| Costs Incurred | CIP (Work-in-progress) | 2,490,000 | 3,984,000 | 2,008,600 | |||||
| Cash | 2,490,000 | 3,984,000 | 2,008,600 | ||||||
| Billing | Accounts Receivable | 2,030,000 | 4,444,000 | 3,526,000 | |||||
| Billing on CIP | 2,030,000 | 4,444,000 | 3,526,000 | ||||||
| Receiving Payments | Cash | 1,815,000 | 3,900,000 | 4,285,000 | |||||
| Accounts Receivable | 1,815,000 | 3,900,000 | 4,285,000 | ||||||
| Period end adjustments for Revenue | Construction Expense | 2,490,000 | 3,984,000 | 2,008,600 | |||||
| (Gross Profit entry) | CIP (Work-in-progress) | 510,000 | 816,000 | 191,400 | |||||
| Construction Revenue | 3,000,000 | 4,800,000 | 2,200,000 | ||||||
| Completing the Project | Billing on CIP | 10,000,000 | |||||||
| CIP (Work-in-progress) | 10,000,000 | ||||||||
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,797,400 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $3,096,000 5,504,000 2,600,000 2,400,000 2022 $3,870,000 1,634,000 4,366,000 4,200,000 8 0247:45 3,034,000 3,400,000 Skipped Assume that Westgate Construction's contract with Santa...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 2023 $2,259,400 0 4,154,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does not...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,849, eee Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,072,00 5,328,000 2,160, eee 1,880, eee 2022 $2,738,000 2,590,000 2,650, eee 2,700,eee 5,190, eee 5,420, eee Westgate recognizes revenue over time...
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
2021
2022
2023
Cost incurred during the year
$
2,975,000
$
3,825,000
$
1,870,000
Estimated costs to complete as of year-end
5,525,000
1,700,000
0
Billings during the year
2,500,000
4,300,000
3,200,000
Cash collections during the year
2,300,000
4,100,000
3,600,000
Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...