Question

The information about a project is shown below. Duration Immediate Budgeted Cost Activity (weeks) Predecessor(s) ($/week) A T
NOTE: Do not use any comma in your answer. The cumulative budgeted cost at the end of week 4 is dollars The cumulative budget
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Week1 Week2 Week3 Week4 Week5 Week6 Week7 Week8 Week9 Week10
A 40000 40000 40000
B 22000 22000 22000
C 17000 17000
D 27000 27000 27000
E 16000 16000 16000 16000 16000
Total in Period 40000 40000 40000 39000 39000 38000 43000 43000 43000 16000
Cumulative from start 40000 80000 120000 159000 198000 236000 279000 322000 365000 381000

Cumulative budgeted cost at the end of week 4= 159000

Cumulative budgeted cost at the end of week 6= 236000

Cumulative budgeted cost at the end of week 7= 279000

Cumulative budgeted cost at the end of week 4= 365000

The total budgeted cost = 381000

Activity time cost/week Early Start Early Finish Late Start Late Finish Slack
Project 10
A 3 40000 0 3 0 3 0
B 3 22000 3 6 4 7 1
C 2 17000 3 5 3 5 0
D 3 27000 6 9 7 10 1
E 5 16000 5 10 5 10 0

The project takes 10 days from the calculation

The cumulative cost formula is simply the addition of weekly cost to the point where the question asks

For example CBC for week 4 = 40000(A)+40000(A)+40000(A)+22000(B)+17000(C)= 159000

Please comment if any doubt

Rate me

Thanks

Add a comment
Know the answer?
Add Answer to:
The information about a project is shown below. Duration Immediate Budgeted Cost Activity (weeks) Predecessor(s) ($/week)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8...

    A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?

  • A project has five activities. From the project plan, you know that the total budgeted cost...

    A project has five activities. From the project plan, you know that the total budgeted cost for the activities are: Activity A, $73,000 activity B, $93,000 activity C, $81,000 activity D, $120,000 activity E, $72,000 The project has been going on for 8 weeks. The progress report at the end of week 8 shows the following information Activity A is 80% completed, activity B is 100% completed activity C is 70% completed activity D is 20% completed, and activity E...

  • The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity...

    The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity Immediate Predecessor(s) Time (weeks) = C, E WLUI WNVN = n a a) Choose the correct network to represent this situation. OA. OB b) The critical path is B-E-F-H c) The length of the critical path is . weeks.

  • Also solve for the minimum total cost associated with finishing the project in 13 weeks and...

    Also solve for the minimum total cost associated with finishing the project in 13 weeks and the total project's duration (and of each activity according to the minimum cost schedule) The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penalty cost of $8,000 per week will be incurred by your company for every week the...

  • For the following project: Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks 4. Activity...

    For the following project: Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks 4. Activity Predecessor (weeks) $2,600 $2,800 $2,000 $2,200 $500 $2,300 $900 $3,000 $500 $2,600 $1,200 $4,200 $1,400$2,000 4 D, E How long will the project take? What is the total cost to complete the project in normal time? If the project is to be shortened by 1 week, which activity will be reduced and how much will the cost be increased? What is the maximum time...

  • A project has 80 activities. At the end of penod 11, activity A is 70% completed. activity B is 9...

    A project has 80 activities. At the end of penod 11, activity A is 70% completed. activity B is 95% completed, activity C is 100% completed, and activity D is 40% completed The budgeted costs for these activities are shown below Activity Total Budgeted Cost ($) 30,000 80,000 60,000 70,000 According to the project plan, the cumulative budgeted cost at the end of period 11 is $268,000 and the total project budgeted cost is $2,500,000. The cumulative actual cost at...

  • Prepare a cost exhibit showing cumulative cost by time period for the project shown below. Activity...

    Prepare a cost exhibit showing cumulative cost by time period for the project shown below. Activity Immediate Predecessors Duration Activity Budget Cost 1.0 4 1,000 2.1 1.0 3 6,000 2.2 1.0 4 5,000 2.3 1.0 2 1,500 3.0 2.1 4 3,200 4.0 2.2 2.3 3 4,800 5.0 3.0   4.0 4 800 6.1 5.0 3 7,200 6.2 5.0 2 1400 6.3 5.0 1 1,200 7.0 6.1 6.2 6.3 2 2,100 What is the budgeted cumulative cost at the end of period...

  • Problem 13 Question Help urasn 'me (days) Activity (days) Normal Cost ($) Immediate Predecessor(s) 1,000 2,200...

    Problem 13 Question Help urasn 'me (days) Activity (days) Normal Cost ($) Immediate Predecessor(s) 1,000 2,200 1,500 1,500 1,500 1,400 1,000 500 1,000 A, B 1,200 1,500 1,300 C, D 300 a. What is the project's duration if only normal times are used? The project duration is 22 day(s). (Enter your response as an integer.) b. What is the minimum-cost schedule? With the minimum-cost schedule, the project duration is day s). (Enter your response as an integer.)

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT