Prepare a cost exhibit showing cumulative cost by time period for the project shown below.
|
Activity |
Immediate Predecessors |
Duration |
Activity Budget Cost |
|
1.0 |
4 |
1,000 |
|
|
2.1 |
1.0 |
3 |
6,000 |
|
2.2 |
1.0 |
4 |
5,000 |
|
2.3 |
1.0 |
2 |
1,500 |
|
3.0 |
2.1 |
4 |
3,200 |
|
4.0 |
2.2 2.3 |
3 |
4,800 |
|
5.0 |
3.0 4.0 |
4 |
800 |
|
6.1 |
5.0 |
3 |
7,200 |
|
6.2 |
5.0 |
2 |
1400 |
|
6.3 |
5.0 |
1 |
1,200 |
|
7.0 |
6.1 6.2 6.3 |
2 |
2,100 |
Let's create the table and the gantt chart first

a)
At the end of period 5 the budgeted cost should cover
100% completion of activity 1.o
33.3% completion of activity 2.1
25% completion of activity 2.2
50% completion of activity 2.3
Thus the budgeted cost is 1000 + (1/3)*6000 + (1/4)*5000 + (1/2)*1500 = 5000
b)
At the end of period 11 the following is budgeted to be completed. Activities 1.0, 2.1, 2.2, 2.3, 3.0, and 4.0. Thus the total cost is 21500
c)
Activity 5 is supposed to finish at the end of period 15. This means the budgeted cost of work scheduled is 22300 at this point. However, if it takes additional 1 period then it will complete at end of period 16.
Budgeted cost of work scheduled (BCWS) at the end of period 16 is
22300 + (1/3)*7200 + (1/2)*1400 + 1200 = 26600
However, the Budgeted cost of work performed (BCWP) is only till activity 5. That means it is 22300.
The formula for schedule variance is
SV = BCWP – BCWS = 22300 – 26600 = -4300
d)
Actual cost of work performed (ACWP) incurred is 22300+300 = 22600
The formula for cost variances
CV = BCWP – ACWP = 22300 – 22600 = -300
Prepare a cost exhibit showing cumulative cost by time period for the project shown below. Activity...
A project has 80 activities. At the end of penod 11, activity A is 70% completed. activity B is 95% completed, activity C is 100% completed, and activity D is 40% completed The budgeted costs for these activities are shown below Activity Total Budgeted Cost ($) 30,000 80,000 60,000 70,000 According to the project plan, the cumulative budgeted cost at the end of period 11 is $268,000 and the total project budgeted cost is $2,500,000. The cumulative actual cost at...
A project has 101 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity A B с D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
The information about a project is shown below. Duration Immediate Budgeted Cost Activity (weeks) Predecessor(s) ($/week) A T 3 none 40,000 в з А 22,000 C2A 17,000 D 3 B 27,000 E5C 16,000 The above table shows that the budgeted cost of activity E is $16,000 per week. NOTE: Do not use any comma in your answer. The cumulative budgeted cost at the end of week 4 is dollars The cumulative Juugeleu cost at the NOTE: Do not use any...
Using the data below, create a time-phased budget for
the project. Show how much the daily and cumulative costs for the
project are, just as the monthly and cumulative costs are shown in
Exhibit 10.9.
Immediate Duration Hourly Hours per Week WBS Activity Predecessor in Weeks Resource Cost Operational definition Research literature Becky 1.1 3 $35 30 1.2 Identify and define terms Ann $60 1.1 1 30 $50 1.3 Obtain approval of definition Clive 1.2 2 Target Selection 2 Solicit...
A project has 98 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity А B с D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
A project has 69 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity Dis 80% completed. The budgeted costs for these activities are shown in the following table. Activity B Total Budgeted Cost(5) 20 15 100 35 С D According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the total project...
• 1. What are the quarterly growth rates (Percentage Change From Preceding Period in Real Gross Domestic Product) for the U.S. economy for the last six quarters? Report those numbers in your submission 2. What is the average of those 6 quarters? . 3. Is the average of those growth rates above or below the long-run U.S. annual growth rate of 3.5 percent? Bureau of Economke Analysis Table 1.1.1. Percent Change From Preceding Period in Real Gross Domestic Product Percent...
Use the following crashing table to answer Project time Period cost Cumulative cost A B C D E F G H I J 37 0 0 36 60 120 1 35 80 200 1 1 34 80 280 2 2 33 80 360 3 2 32 135 495 3 1 2 1 31 180 675 1 4 1 2 1 30 180 855 2 5 1 2 1 29 733.33 1588.33 1 2 5 1 2 1 28 983.33 2571.67...
Use the following crashing table to answer Project time Period cost Cumulative cost A B C D E F G H I J 37 0 0 36 60 120 1 35 80 200 1 1 34 80 280 2 2 33 80 360 3 2 32 135 495 3 1 2 1 31 180 675 1 4 1 2 1 30 180 855 2 5 1 2 1 29 733.33 1588.33 1 2 5 1 2 1 28 983.33 2571.67...
The table below gives the optimistic, most-likely, and pessimistic time estimates (in weeks) for all activities in a project. (Statistical tables are available in appendix I) Activ Predecessor totm t 2.0 5.0 8.0 3.0 4.0 5.0 4.06.08.0 5.0 6.0 7.0 3.0 6.0 9.0 D, E (i) Calculate the estimated time and variance for each task (ii) Draw the AON diagram and identify the critical path. (iii) What is the expected critical path duration and estimate a standard deviation for the...