Show step by step solutions.

(a) Complete the expected duration, standard deviation and variance for activities A and B and enter them into the table (provided above).
(b) Draw the Activity-on-node (AON) including the Start & Finish diagram and use the expected activity durations to complete a forward and backward pass (show calculations for ES,EF,LS,LF), create a table and show your work.
Show step by step solutions. (a) Complete the expected duration, standard deviation and variance for activities...
Choose an event or significant task and prepare an activities
list following a format similar to that used in the text, Table
9.3, Chapter 9, page 391. Be sure to include the immediate
predecessors.
Then, create a project network similar to that shown in Figure
9.7, Chapter 9, page 392.
Do NOT include times for the activities and do NOT attempt to
determine the critical path.
Examples of events you might consider (there are many
others):
formal dinner for 5...