Total load for each product = (Demand / Lot size) * Standard setup time + Demand * Standard processing time
= Demand * (Standad setup time / Lot size + Standard processing time)
Total load for Kites = 30000*(3/20+0.3)
= 13,500 hours
Total load for Kites = 12000*(4/70+0.8)
= 10,286 hours (rounded-off)
Total load for both products = 13500+10286
= 23,786 hours
Capacity of each machine per year = 180*2*8 = 2880 hours
Net capacity per machine considering 25% capacity cushion = 2880*(1-.25) = 2160 hours
Total number of machines required = Total load for both products / Net capacity per machine
= 23786 / 2160
= 11 machines
The number of additional machines required = Total number of machines required - current number of machines
= 11 - 4
= 7 machines
Problem 8 : Question Help Up, Up, and Away is a producer of kites and wind...
Higher is a producer of kites and wind socks. Relevant data on the bottleneck operation in the shop for the upcoming fiscal year are given in the following table: Item Kites Wind Socks demand forecast 30,000 units/yr 15,000 units/yr lot size 20 units 60 units standard processing time 0.4 hours/unit 0.5 hours/unit standard setup time 3 hours/lot 4 hours/lot The shop works two shifts per day, 8 hours per shift, 180 days per year. Currently, the company operates 4 machines,...
A manager is trying to decide whether to buy one machine or two. If only one machine is purchased and demand proves to be excessive, the second machine can be purchased later. Some sales would be lost, however, because the lead time for delivery of this type of machine is six months. In addition, the cost per machine will be lower if both machines are purchased at the same time. The probability of low demand is estimated to be 0.20...
Macon Controls produces three different types of control units
used to protect industrial equipment from overheating. Each of
these units must be processed by a machine that Macon considers to
be their process bottleneck. The plant operates on two 8-hour
shifts, 5 days per week, 52 weeks per year. The table below
provides the time standards at the bottleneck, lot sizes, and
demand forecasts for the three units. Because of demand
uncertainties, the operations manager obtained three demand
forecasts (pessimistic,...
A company is currently producing a carpet shampooer that sells about 4,000 units per year. It takes 2 hours to produce the unit, but 8 hours to set up the line for that process. This device is produced in batches of 100. Management is considering producing a second type of shampooer, for which it estimates that demand would 2,000 units per year, processing time would be 2.8 hours per unit, with a setup time of 16 hours per batch, and...
Knott's Industries manufactures standard and super premium backyard swing sets. Currently it has four identical swing-set-making machines, which are operated 250 days per year and 8 hours each day. A capacity cushion of 15 percent is desired. The following information is also known: i Standard Model Super Premium Model Annual Demand 20,000 10,000 Standard Processing Time 7 min 20 min Average Lot Size 25 Standard Setup Time per Lot 30 min 45 min a. Does Knott's have sufficient capacity to...
Adam (with the same machine) performs tasks 1 and 2. After
running a setup on the machine, he performs task 1 on every unit in
a batch. Then, he runs another setup on the same machine before
performing task 2 on every unit in the batch. After that, either
Brad or Chloe performs task 3 on the units. Finally, Dorothee does
task 4. Tasks 3 and 4 are done by the workers only so they do not
require any setups....
ннен CALOULATOR MESSAGE HY IRSTRICTOR FULL SCREEN PRONTER VRS1ON 4 ACE NEXE Exercise 8-14 Wind's Wind Toys manufactures decorative ktes, banners, and windsacks. During the month of January, Wind receivewd arders for 3,c00 Valentice's Day banners and 1,200 Eastar kites Because several sewing machines are in the shop for repairs, wind has only 1,000 sewing machine hours available for produrtion of these orders. Each Valentine's Day banner sels for $12. The banners take one hour to sew and have a...
A workstation consisting of 12 machines in parallel, each having a mean process time of 2 hours. The station works 16 hours a day in 2 shifts; each is 8 hours. There is one hour break in each shift. You need to produce a lot of 48 jobs per day. Calculate the capacity in jobs per day of this station. A workstation with 12 machines in parallel, each having a mean process time of 2 hours. The station works 16...
Best Bicycles manufactures three different types of bikes: the Tiny Tike, the Adult Aero, and the Mountain Monger. Assume that Best Bicycles operates two shifts, each with 1,300 hours per year. Bike Demand Forecast (units/year) Processing Time (minutes/unit) Lot Size (# of bikes) Setup Time (minutes/setup) Tiny Tike 13,920 9.5 8 22 Adult Aero 89,470 40.8 46 44 Mountain Monger 17,290 34.0 14 56 Calculate the required capacity for this year’s production. Note that the times are given for assembly...
Problem 16.1 : Question Help Carol Cagle has a repetitive manufacturing plant producing trailer hitches in Arlington, Texas. The plant has an average inventory turnover of only 12 times per year. He has therefore determined that he will reduce his component lot sizes. He has developed the following data for one component, the safety chain clip Setup labor cost $30 per hour Annual holding cost $14 per unit Daily production 960 units/8 hour day Annual demand 33,000 (275 days each...