Higher is a producer of kites and wind socks. Relevant data on the bottleneck operation in the shop for the upcoming fiscal year are given in the following table:
| Item | Kites | Wind Socks |
| demand forecast | 30,000 units/yr | 15,000 units/yr |
| lot size | 20 units | 60 units |
| standard processing time | 0.4 hours/unit | 0.5 hours/unit |
| standard setup time | 3 hours/lot | 4 hours/lot |
The shop works two shifts per day, 8 hours per shift, 180 days per year. Currently, the company operates 4 machines, and desires a 25 percent capacity cushion. How many machines should be purchased to meet the upcoming year's demand without resorting to any short-term capacity solutions?
Answer:
Kites:
Wind Socks:
Higher is a producer of kites and wind socks. Relevant data on the bottleneck operation in...
Problem 8 : Question Help Up, Up, and Away is a producer of kites and wind socks. Relevant data on the bottleneck operation in the shop for the upcoming fiscal year are given in the following table: Item Demand forecast Lot size Standard processing time Standard setup time Kites 30,000 units/year 20 units 0.3 hour/unit 3.0 hours/lot Wind Socks 12,000 units/year 70 units 0.8 hour/unit 4.0 hours/lot The shop works two shifts per day, 8 hours per shift, 180 days...
A manager is trying to decide whether to buy one machine or two. If only one machine is purchased and demand proves to be excessive, the second machine can be purchased later. Some sales would be lost, however, because the lead time for delivery of this type of machine is six months. In addition, the cost per machine will be lower if both machines are purchased at the same time. The probability of low demand is estimated to be 0.20...
Macon Controls produces three different types of control units
used to protect industrial equipment from overheating. Each of
these units must be processed by a machine that Macon considers to
be their process bottleneck. The plant operates on two 8-hour
shifts, 5 days per week, 52 weeks per year. The table below
provides the time standards at the bottleneck, lot sizes, and
demand forecasts for the three units. Because of demand
uncertainties, the operations manager obtained three demand
forecasts (pessimistic,...
Knott's Industries manufactures standard and super premium backyard swing sets. Currently it has four identical swing-set-making machines, which are operated 250 days per year and 8 hours each day. A capacity cushion of 15 percent is desired. The following information is also known: i Standard Model Super Premium Model Annual Demand 20,000 10,000 Standard Processing Time 7 min 20 min Average Lot Size 25 Standard Setup Time per Lot 30 min 45 min a. Does Knott's have sufficient capacity to...
A company is currently producing a carpet shampooer that sells about 4,000 units per year. It takes 2 hours to produce the unit, but 8 hours to set up the line for that process. This device is produced in batches of 100. Management is considering producing a second type of shampooer, for which it estimates that demand would 2,000 units per year, processing time would be 2.8 hours per unit, with a setup time of 16 hours per batch, and...
Consider the following Product Structure De Dom Nuct Structure Data Demand Data, Routing and sembles the products A and B Product Structure Data Complete the following tables in order to determine the capacity requirements by using Capacity Bills method. (30 points) Routing and Standard Data Standard Lot Standard Operation Center Work Setup Product Setup Hours Standard Product Hours per unit Total Hours per unit Hours per unit Tofi of 1003 1003 100 010 lof 2002 3002 23001 0,35 0,45 0.30...
Best Bicycles manufactures three different types of bikes: the Tiny Tike, the Adult Aero, and the Mountain Monger. Assume that Best Bicycles operates two shifts, each with 1,300 hours per year. Bike Demand Forecast (units/year) Processing Time (minutes/unit) Lot Size (# of bikes) Setup Time (minutes/setup) Tiny Tike 13,920 9.5 8 22 Adult Aero 89,470 40.8 46 44 Mountain Monger 17,290 34.0 14 56 Calculate the required capacity for this year’s production. Note that the times are given for assembly...
3. Consider the followine Product Structure Data, Demand Data. Routing and Standard data for a company that assembles two products, A and B. Product Structure Data F (3 required 3 requiredil Complete the following tables in order to determine the capacity requirements by using Capacity Bills method. (30 points) Routine and Standard Data Total Standard Setup Hours per unit Operation Hours Sizes per unit с End Lot Work Standard Standard Product Center Setup Production Hours Hours per unit 501 of...
3. Consider the following Product Structure Data, Demand Data, Routing and Standard data for a company that assembles two products, A and B. Product Structure Data | A B E (2 required) D Ε . (2 required) F (3 required) 3 required) Complete the following tables in order to determine the capacity requirements by using Capacity Bills method. (30 points) Routing and Standard Data End Product Lot Sizes Operation Work Center Standard Setup Hours Standard Production Hours per unit Standard...
Alpha Assemblies produces a wide variety of products in their central Nebraska facility. Many of these products fit within a line of standard truck and trailer parts. Within this is a set of hitches that can be made in two sizes (1-1/4 and 2) and three strengths (light duty, medium duty, and heavy duty). All of the hitches in this line have "natural" finishes so no additional steps are necessary after they are cast. The machine used to cast these...