80.90 seconds/Unit
Takt Time = Available Time to work/Demand
= (8*60*60)/356
= 28800/356
= 80.9 Seconds/Unit
An assembly line is to produce 356 items in a standard 8 hour day. What is...
Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...
A manufacturing company pays an assembly line worker $12 per hour. What is the proper classification of this labor cost O a. mixed cost Ob. foxed cost Oc. semivariable cost Od variable cost All work ved o BE to Dil Se + 44
2-8 A An assembly line can produce 80 units per hour. The line's hourly cost is $4250 on straight time (the first 8 hours). Workers are guaranteed a minimum of 5 hours. There is a 35% premium for overtime, however, productivity for overtime drops by 10%. What are the average and marginal costs per unit for the following daily quantities? (a) 350 (b) 500 (c) 640 (d) 850
An assembly line is to operate eight hours per day with a desired output of 160 units per day. The following table contains information on this product's task times and precedence relationships: IMMEDIATE PREDECESSOR TASK TIME (SECONDS) 100 TASK A 70 D 50 40 C C. D 70 140 G H b. What is the required workstation cycle time meet the desired output rate? (Round your answer to the nearest whole number.) Workstation cycle time seconds per unit c. Balance...
An assembly line can produce 90 units per hour. The line's hourly cost (total salaries of workers) is $4,248 an hour (the first 8 hours). Workers are guaranteed a minimum of 6 hours (i.e., they will be paid for 6 hours per day, even if they work less than 6 hours). There is a 50% premium for overtime (i.e., salary is increased 50% during overtime hours), however, productivity for overtime drops by 8% (i.e, the number of units produced per...
Information regarding tasks in an assembly line run for an 8-hour shift each day is provided: Task Proceeding Task (s) Tme (min) A - 5 B - 3 C - 2 D A 1 E B 4 F C 6 G D,E 7 H G 5 I F,G 6 J H,1 4 K I 3 a)What is the theoretical minimum number of stations for a shift output of 40 units? B)if the line is balanced according to the desired cycle...
1- An assembly line can produce 90 units per hour. The line’s hourly cost is $4,500 on straight time (the first 8 hours). Workers are guaranteed a minimum of 6 hours. There is a 50% premium for overtime, however, productivity for overtime drops by 5%. What are the average and marginal costs per unit for the following daily quantities? 450 600 720 900 2- Owning, operating and maintaining an automobile carries with it private internal costs to the driver, as...
Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 12 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 2.5 2.0 2.0 3.0 3.0 3.0 3.0 A,B, C b....
This problem is similar to Alt-Cat 8.2 and 8.3. An assembly line is to be designed to operate 9.5 hours per day and supply a steady demand of 450 units per day. Here are the tasks and their performance times: PERFORMANCE PRECEDING TASK PERFORMANCE TIME (SECONDS) 25 30 15 10 40 20 PRECEDING TASK TASKS TIME (SECONDS) TASK 56 40 38 15 39 20 h,i j, k b. What is the workstation cycle time? Hint: draw the diagram first. tion...
Problem 6-22 Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 24 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 1.0 1.0 2.5 1.5 A, B, C 1.5...