Earned value (EV) = 0.92 x 25600 +0.52 x 150600 + 0
= 23552 + 78312
=101864
Actual cost (AV) = 177000
Planned value (PV) = 25600 + 0.88 x 150600 + 0
= 158128
SV = EV - PV = 101864 -158128
= -56264
SPI = EV / PV = 101864 / 158128
= 0.644
CV = EV - AC = 101864 - 177000
= -75136
CPI = EV / AC = 101864 / 177000
= 0.5755
Problem 5-5 Your project to obtain charitable donations is now 40 days into a planned 50-day...
Problem 5-5 Your project to obtain charitable donations is now 41 days into a planned 51-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 34 days of the project and to bring in $25,700. Even though we are 41 days into the project, we still see that we have only 90% of this activity complete. The second activity relates to company donations and is...
Your project to obtain charitable donations is now 43 days into a planned 53-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 37 days of the project and to bring in $25,900. Even though we are 43 days into the project, we still see that we have only 89% of this activity complete. The second activity relates to company donations and is scheduled to...
Problem 5-5 Your project to obtain charitable donations is now 38 days into a planned 48-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 33 days of the project and o bring in S25 300. ven though we are 38 days to the pro ect we stil see hat we have only 8 % of his activity complete. The second activity relates company donations...
For a project, in X day, planned value, earned value and actual cost of the tasks are given in dollar in the table below. Planned $1000 to complete project. Task Actual Cost Work Performed Budgeted Cost Work Scheduled 50 70 30 100 50 2 3 4 5 Budgeted Cost Work Performed 50 70 30 50 0 Total: 250 a. Find schedule and cost variance. Explain what it means? b. Find schedule and cost performance index. c. Find estimate to complete...
2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. The planners were expecting to be only58 % through the third activity at this time. The first activity involves prepping the site for the bridge....
Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were only expecting to be 57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was...
Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3 4 2 1 3 Normal Time (days) 6 8 4 3 7 5 3 6 7 10 10 Dr. John Watage, deputy director of the family planning Research Center in Nigeria's Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new...
Question #1: Some of the tasks in this project can be done in
parallel. Prepare a diagram showing the required network of tasks
and define the critical path. What is the length of the project
without crashing? Do not just answer, but show the whole
process.
Question #2: If the critical path is longer than 29 days, what
is the least additional amounting that Dr. Watage can spend and
still achieve this schedule objective (29 days)? Do not just
answer,...
Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager, which option would you select? What risks are involved with your choice and with ACL’s request? Shell Case Fabricators BACKGROUND Shell Case Fabricators (SCF) designs and builds shell casings that enclose electronic products such as calculators, cell phones, modems. Typically the cases are plastic or plastic compounds. SCF has six different production lines that cover different types of product. For example, the largest high...
Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241 through 246). Question 2 Prepare a plan for the remainder of the project in response to Adams’ memo (lines 241 through 246). Your answers to the above will be assessed in terms of the level of communication displayed, the insights and inferences drawn, and your ability to...