Problem 9.1. Given the following jobs that are to be processed on a single processor: rocesS Burst Time in ms Arri Time in ms 0 2 6 16 20 12 3 6 10 a. Show the schedule using the scheduling algorithms shortest p rocess next, a non- preemptive algorithm, and shortest remaining time, a preemptive algorithm. Use a GANTT chart to show the schedules in a manner similar to the FCFS schedule shown below: (1 unit 2 ms) 16 b. Compute the turnaround time and relative delay for each algorithm Solution: Solution for p9.1. goes here

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:- a)

2. 2. Is 22 3マ40 4422

b.) Turnaround time:- Turnaround time is the time difference between completion time and arrival time.

Turn Around Time = Completion Time - Arrival Time

TurnAround time for non preemptive algorithm

Turnaround time for process p1= 4-0=4

Turnaround time for process p2=16-2=14

Turnaround time for process p3=30-6=24

Turnaround time for process p4 22-16=6

Turnaround time for process p5= 40-20=20

Total average turn around time = (4+14+24+6+20)/5=68/5=13..23

Waiting time :- Waiting time is the time difference between turn around time and burst time.

Waiting Time = Turn Around Time - Burst Time

Waiting time for non-preemptive algorithm

Wating time for p1= 4-4=0

Wating time for p2=14-12=2

Wating time for p3=24-8=14

Wating time for p4=6-6=0

Wating time for p5=10

Turn around time for preemptive algorithm

Turnaround time for process p1= 4-0=4

Turnaround time for process p2=30-2=28

Turnaround time for process p3=14-6=8

Turnaround time for process p4 22--16=6

Turnaround time for process p5= 40-20=20

Total average turnAround time=13.2

Waiting time for preemptive algorithm

Wating time for p1= 4-4=0

Wating time for p2=16

Wating time for p3=0

Wating time for p4=0

Wating time for p5=10

Add a comment
Know the answer?
Add Answer to:
Problem 9.1. Given the following jobs that are to be processed on a single processor: rocesS...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following set of processes, with the length of the CPU-burst time given in milliseconds:

    Consider the following set of processes, with the length of the CPU-burst time given in milliseconds:Processburst TimePriorityP1103P211P323P414P552For each of the scheduling algorithms, FCFS, Shortest-Job-First (SJF, non-preemptive), Priority (smaller priority number implies higher scheduling priority), and RR (quantum = 1) do the following.Draw a Gantt chart to show how these processes would be scheduled.Give the turnaround time (total time from the first arrival into ready state until CPU-burst is completed) of each process.Give the waiting time (total time spent in the Ready state) of each process.Give...

  • 5. [27pts.] Given the following set of processes, with arrival times, priorities, and the length of...

    5. [27pts.] Given the following set of processes, with arrival times, priorities, and the length of the CPU burst in ms: Priority Burst time Arrival Time Process 3 P1 4 P2 2 10 P3 P4 (Note: a lower number means higher priority) Draw a Gantt chart showing a FCFS scheduling algorithm. a. b. Draw a Gantt chart showing a non-preemptive Priority scheduling algorithm. c. Draw a Gantt chart showing a Round Robin Scheduling algorithm with quantum of 4ms d. Compute...

  • C language show all work 1. [50 pts] Given the following set of processes, with arrival...

    C language show all work 1. [50 pts] Given the following set of processes, with arrival times, priorities, and the length of the CPU burst in ms: Priority Arrival Time Burst time Process P1 P2 P3 P4 4. 3 2 0 0 10 (Note: lower number means higher priority, processes P1, P2, P3, and P4 arrive at the same time, in the given order). a. Draw a Gantt chart showing a FCFS scheduling algorithm. b. Draw a Gantt chart showing...

  • Opearting system 5. [27pts.] Given the following set of processes, with arrival times, priorities, and the...

    Opearting system 5. [27pts.] Given the following set of processes, with arrival times, priorities, and the length of the CPU burst in ms: Process Arrival Time Burst time Priority P1 P2 P3 2 10 P4 (Note: a lower number means higher priority; processes P2- P4 arrive at the same time, in the given order) a. Draw a Gantt chart showing a FCFS scheduling algorithm. b. Draw a Gantt chart showing a non-preemptive Priority scheduling algorithm. Draw a Gantt chart showing...

  • Three processes P1, P2 and P3 with related information are given in the following table: Process...

    Three processes P1, P2 and P3 with related information are given in the following table: Process Burst Time (ms) Arrival Time(ms) P1400 P2 3 0 10 P3 L T 20 T is a positive integer (T>0). If you use a preemptive shortest job first scheduling algorithm to schedule the three processes, make a Gantt chart, and calculate different waiting times of three processes. Please show a professional perfect solution with necessary details.

  • Operating Siytem Concepts Homework No. 1 Variant No. 1 Student Cristian Anchei Paraschine (academic group, name,...

    Operating Siytem Concepts Homework No. 1 Variant No. 1 Student Cristian Anchei Paraschine (academic group, name, surname) I got the task.... (date, signature) Homework Submission Date: November 6th, 2019 Assignment: Consider the following set of processes, with the length of the CPU burst time given in milliseconds!: Process CPU burst time, ms Arrival time, ms Priority P 2 2 2 7 Ps 3 3 Draw a Gantt chart that illustrates process scheduling for these algorithms: a) First Come - First...

  • Consider the following set of processes, with the length of the CPU-burst time given in milliseconds:...

    Consider the following set of processes, with the length of the CPU-burst time given in milliseconds: Process            Burst Time      Priority P1                    10                    3 P2                    1                     1 P3                    2                     3 P4                    1                     4 P5                    5                     2 The processes are assumed to have arrived in the order P1, P2, P3, P4, P5, all at time 0. a. Draw four Gantt charts illustrating the execution of these processes using FCFS, SJF (SPN), a...

  • Consider the following set of processes, with the length of the CPU burst given in milliseconds:

    Consider the following set of processes, with the length of the CPU burst given in milliseconds:ProcessBurst TimePriorityP1 54P231P312P472P543The processes are assumed to have arrived in the order P1 , P2 , P3 , P4 , P5 , all at time 0. a. Draw four Gantt charts that illustrate the execution of these processes using the following scheduling algorithms: FCFS, SJF, nonpreemptive priority (a larger priority number implies a higher priority), and RR (quantum = 2). b. What is the turnaround time of each...

  • QUESTION 3 Consider the following set of processes: Priority Process Arrival Time A 0 B 1...

    QUESTION 3 Consider the following set of processes: Priority Process Arrival Time A 0 B 1 C 6 * Lower number means higher priority Burst Time (ms) 5 3 4 Draw in a paper sheet 4 Gantt charts that illustrate the execution of these processes using the following scheduling algorithms: FCFS, Non-Preemptive SJF, Shortest-Remaining-Time-First (SRTF), Non-Preemptive Priority (NPP), and RR (quantum time = 2) scheduling algorithms, then fill the following tabic accordingly. (Note: If a new process arrives at the...

  • luuent Name: 1. (100 points) Three processes P1, P2 and P3 with related information are given...

    luuent Name: 1. (100 points) Three processes P1, P2 and P3 with related information are given in the following table: Process Burst Time (ms) Arrival Time (ms) P1 T 0 P2 30 20 P3 20 T is a positive integer (T>0). Please use a non-preemptive shortest job first scheduling algorithm to make Gantt charts, and calculate different waiting times of three processes for different cases. Please write a professional perfect solution with detailed steps. 30

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT