Question

You are the project managers assistant on a construction site. The project manager is off site for the day and you are respo

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Given outside dimension = 16 base and 18 height, 18 feet long conceitratea Loaa (W) = 55000 lbf = 55 kips E =1sxloopsi AlumiWe know that Allowable deflection -0.611 (i) No, this beam will not support the design load without exceeding the allowable d
Reccomended solution to the problem.

If we have time then we should wait for the steel beam because steel beam is more efficient.

Explanation

Since the elastic modulus of Aluminium is about 1/3 that of Steel, for the same beam shape properties, for the same loading, for the same span and support conditions, the Aluminium beam deflection will be three times more.

Density of steel is coincidentally about three times more than that of aluminium and so the same beam in steel will be three times heavier.

If subjected to same loading and having same moment of inertia of the cross section, aluminum beam will deflect more.

The reality is that the relative cost of selecting one or other material depends on the required application. However, as a little background:
The cost of steel varies according to its grade. By weight commercial grades can cost anything from about 1/2 the cost of . However, aluminium is about 1/3rd the density of steel, which means it breaks even with even the cheapest steel .

Since the havier section is requred to meet the requirement so more time will be consumed for fabrication leading to the delay in project completion.

Add a comment
Know the answer?
Add Answer to:
You are the project manager's assistant on a construction site. The project manager is off site...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are the project manager's assistant on a construction site. The project manager is off site...

    You are the project manager's assistant on a construction site. The project manager is off site for the day and you are responsible for the ongoing progress of the site in her absence. Two similar beams are delivered to a construction site. Each beam is a hollow box beam, constructed of A36 structural steel, (E=29.0 x 106 psi, density of 490 lbm/ft?), each beam having outside dimensions of 16" base and 18" height, 18 feet long. Beam A has top...

  • You are the project manager's assistant on a construction site. The project manager is off site...

    You are the project manager's assistant on a construction site. The project manager is off site for the day and you are responsible for the ongoing progress of the site in her absence. Two similar beams are delivered to a construction site. Each beam is a hollow box beam, constructed of A36 structural steel, (E=29.0 x 106 psi, density of 490 lbm/ft?), each beam having outside dimensions of 16" base and 18" height, 18 feet long. Beam A has top...

  • Two similar beams are delivered to a construction site. Each beam is a hollow box beam,...

    Two similar beams are delivered to a construction site. Each beam is a hollow box beam, constructed of A36 structural steel, (E=29.0 x 106 psi, density of 490 lbm/ft?), each beam having outside dimensions of 16" base and 18" height, 18 feet long. Beam A has top and bottom wall thicknesses of 0.5" and side wall thickness of 0.375". Beam B has top and bottom wall thicknesses of 0.4375" and side wall thickness of 0.3125". The structure to be constructed...

  • the new Project manager is appointed you for the construction of a new warehouse on site....

    the new Project manager is appointed you for the construction of a new warehouse on site. question: define completion criteria, by providing clear outline of project deliverables and acceptable quality standards.

  • the project task: the new Project manager is appointed you for the construction of a new...

    the project task: the new Project manager is appointed you for the construction of a new warehouse on site. Question: brief explanation of the phases that the project will go through, the problem/reasons why a new warehouse is required, the background and project goals.

  • #2. Short Answer You are a project manager of a construction contractor. You have a supplier...

    #2. Short Answer You are a project manager of a construction contractor. You have a supplier who manufactures and delivers curtain walls to your site. Your supplier and you are working on a solution to reduce total supply chain costs. You found that the PPC (Planned Percent Complete) and PCR (Percent Constraint Removed), of the contractor in charge of structure work are 60% and 43% respectively for the last three months. How do you think such PPC and PCR make...

  • PROBLEM Authorities of the Atherton Tablelands in North Queensland proposes a glass covered 3m long walkway scenic lookout to cater for tourists. The glass panels are to be attached to an aluminium f...

    PROBLEM Authorities of the Atherton Tablelands in North Queensland proposes a glass covered 3m long walkway scenic lookout to cater for tourists. The glass panels are to be attached to an aluminium frame attached to a reinforced concrete beam. You are required to design the reinforced concrete beam Gla Safety post up Thick glas SIDE VIEW FRONT VIEW Figure 1. Schematic View of the Walkway Structure To hold the aluminium frame/glass panels and to allow the tourists to walk in...

  • Question 1: What is a joint venture and why might two construction firms choose to form...

    Question 1: What is a joint venture and why might two construction firms choose to form one? (4 points) Case Study 1: Please answer the first 4 questions with the following case data for Project 101 and Project 102. A construction company began operations on January 2, 2010. During the year the company was awarded three construction contracts. The company incurred $300,000 operating expenses for the year for which $275,000 has been paid while the balance is owed as of...

  • QUESTIONS 13-18 PLEASE! Maximum Storage Area DUE DATE: This project is worth 10% of your Unit...

    QUESTIONS 13-18 PLEASE! Maximum Storage Area DUE DATE: This project is worth 10% of your Unit 2 grade. Please review the Project FAQ handout for format and process. Problem Situation A construction company wishes to build a rectangular enclosure to store machinery and equipment. The site selected borders on a river that will be used as one of the sides of the rectangle. Fencing will be needed to form the other three sides. The company foot high chain-link fencing. The...

  • Write the conclusion based on the in the objectives that I uploaded & based on the observation in the site check li...

    Write the conclusion based on the in the objectives that I uploaded & based on the observation in the site check list AND also separate the positive and negative observation. *objectives are uploaded . *The checklists is upload also. Asap please ! oo00 Globe 10:06 PM Notes Objectives: 1.to evaluate if the company is complying with their safety precautionary measures that is being set in their work. 2.to determine if the company is concern with their inferior; if they monitor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT