Question – a:
The activity network is:

Question – b:
Cycle time = time available/demand
Time available = 8 hours = 8*3600 seconds = 28800 seconds
Demand = 400
Cycle time = 28800/400 = 72 seconds
Minimum number of workstations = sum total of all task time/cycle time
Sum total of all task time = (50 + 40 + 20 + 45 + 20 + 25 + 10 + 35) = 245 seconds
Minimum number of workstations = 245/72 = 3.40 = 4
Answer is: 4
Question – c:
Arranging the tasks in decreasing order of task time:
|
Task |
Time |
Predecessors |
|
A |
50 |
- |
|
D |
45 |
C |
|
B |
40 |
- |
|
H |
35 |
B, F, G |
|
F |
25 |
D |
|
C |
20 |
A |
|
E |
20 |
C |
|
G |
10 |
E |
Now allotting the tasks to workstations:

********
IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!
IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!
OPERATIONS AND SUPPLY CHAIN MANAGEMENT L06-4 SOLVED PROBLEM 2 TASKS THAT MUST PRECEDE TASK TIME (SECONDS)...
TASK SECONDS TASKS THAT MUST PRECEDE A 25 — B 15 A C 20 B D 29 B E 16 C F 8 D G 35 E, F H 32 G The workday is 10.5 hours long. Demand for completed product is 900 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical number of workstations required to meet the desired output rate? (Round...
The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 18 — B 10 A C 25 B D 15 B E 14 C F 17 D G 12 E, F H 20 G The workday is 6.25 hours long. Demand for completed product is 750 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) The minimum cycle...
QUESTION 37 A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Task Predecessor Time (seconds) 50 А B А 20 С А 26 D 40 B, C C E 30 a. Draw the network described in the table. b. What is the required...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) I have not been...
Information regarding tasks in an assembly line run for an 8-hour shift each day is provided: Task Proceeding Task (s) Tme (min) A - 5 B - 3 C - 2 D A 1 E B 4 F C 6 G D,E 7 H G 5 I F,G 6 J H,1 4 K I 3 a)What is the theoretical minimum number of stations for a shift output of 40 units? B)if the line is balanced according to the desired cycle...
Could Problem 9P, Chapter 5 of Managing Operations Across the Supply Chain (3rd. Edition) be solved please? Thank you! Chapter 5, Problem 9P: The Office Interiors Company has developed a new, modern office chair. Initial sales forecasts are for 50 chairs per day. The assembly operations will run for two eight-hour shifts. The process engineer and operations manager are working together to balance the line to make the new chair as efficiently as possible. The process engineer suggests using the...
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.) Minimum cycle time minutes Maximum cycle time minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the...
An assembly line with 17 tasks is to be balanced. The longest task is 2.3 minutes, and the total time for all tasks is 18 minutes. The line will operate for 490 minutes per day. a. What is the minimum number of workstations needed if the output rate is to be 170 units per day? (Round the final answer to the next whole number.) Number of workstation b. What cycle time will provide an output rate of 126 units per...
A company is designing a product layout for a new product. It
plans to use this production line eight hours a day in order to
meet a schedule of 400 units per day. The tasks necessary to
produce this product are detailed in the table below.
a. Draw the network described in the table.
b. What is the required cycle time (in seconds) in order to meet the schedule?
c. What is the theoretical minimum number of workstations needed to...