QUESTION 17 The critical path of the projected below as been determine what they Activity Time Immediate Predecessor A 7 8 C


QUESTION 17 A B The critical path of the project outlined below has been mined of B-F-H. What is the slack time for activity
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Slack time for critical path activities is always 0

So if the critical path is determined as B-F-H then the slack time for activity F is "0".

Please give thumbs up/ likes if you find this answer helpful. Thank you!

  

Add a comment
Know the answer?
Add Answer to:
QUESTION 17 The critical path of the projected below as been determine what they Activity Time...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT