Question


Screen Shot 2020-04-20 at 3.45.19 PM Z o @ Q Search A project for improving a billing process has the following precedence re

Please help me find the critical path and the slack. I've been struggling on this for awhile

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

CRITICAL

A

4

0

4

0

4

0

YES

B

7

0

7

2

9

2

C

5

4

9

4

9

0

YES

D

11

9

20

9

20

0

YES

E

9

7

16

12

21

5

F

4

20

24

20

24

0

YES

G

3

16

19

21

24

5

H

9

24

33

24

33

0

YES

ES = MAX(EF OF ALL PREDECESSORS); 0 FOR FIRST ACTIVITY

EF = ES + DURATION

LF = MIN(LS OF ALL SUCCESSOR ACTIVITIES); MAX EF AS LF FOR LAST ACTIVITY

LS = LF - DURATION

SLACK = LF- EF

CRITICAL PATH = LONGEST PATH WITH 0 SLACK:

CRITICAL PATH = A--C--D--F--H

DURATION OF PROJECT = 33

** Leaving a thumbs-up would really help me out. Let me know if you face any problems.

Add a comment
Know the answer?
Add Answer to:
Please help me find the critical path and the slack. I've been struggling on this for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT