Question

What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-EndWhat is the EF (earliest finish) of activity E? o o ООООО < N NWhat is the LS (latest start) of activity E? ОООООThe list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Imme

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity Duration Early start=Max of early finish of last activities Early finish = early start + duration Late finish= Min of late start of after activities Late start= late finish - duration Total slack= late finish – early finish Critical activity, activities with 0 slack time
A 4 0 4 4 0 0 Yes
B 2 0 2 7 5 5 No
C 5 0 5 11 6 6 No
D 3 4 7 7 4 0 Yes
E 2 4 6 9 7 3 No
F 4 7 11 11 7 0 Yes
G 2 7 9 11 9 2 No

Answer: Project compltion time is the highest of EF, 11 weeks

Answer: Critical path activities are start-A-D-F-end

Answer: LS of activity E= 7

Answer: EF of activity E= 6

Please ask, if you have any doubts through the comment section. Do rate the answer

Add a comment
Know the answer?
Add Answer to:
What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b....

    Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b. A-B-C-F C. A-B-E-F Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) c. Which of these activities should the project manager track most closely? A. A-B-E-F b. A-D-E-F c. A-B-C-F Problem 15.6 Task Duration Estimate (in Days) Immediate Predecessors None А B A B and D E and C Earliest...

  • PLEASE SOLVE FOR ALL :) determine ES, EF, LS, LF, and slack for each Dave Fletcher...

    PLEASE SOLVE FOR ALL :) determine ES, EF, LS, LF, and slack for each Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) E 4 A R 6 5 C A G 10 C, E D 1 A H 6 D.F Dave's...

  • Consider the following project. Activity ImmediateActivity Time (days) Predecessor CD E,F What is the critical path? O ACFG O ADFG OBEG ACDFG What is the latest finish time for activity F? 0 9 O...

    Consider the following project. Activity ImmediateActivity Time (days) Predecessor CD E,F What is the critical path? O ACFG O ADFG OBEG ACDFG What is the latest finish time for activity F? 0 9 O 13 O 16 What is the latest possible time that Activity E can be started without delaying the completion of the project? What is the latest time that activity B can finish without delaying any other activities? 4 What is the latest time that activity B...

  • Start End TRUE If the Earliest Start (ES) of activity A is zero, and the duration...

    Start End TRUE If the Earliest Start (ES) of activity A is zero, and the duration of activity Bis longer than the duration of activity then which of the following statements must a. Earliest Finish time (EF) of activity D = duration of A+ duration of B+ duration of D b. Earliest Finish time (EF) of activity D duration of A+ duration of C+ duration of D O c Earliest Finish time (EF) of activity D = duration of A+...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Pred...

    Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Predecessor ACTIVITY TIME EARLIEST START EARLIEST FINISH LATEST START LATEST FINISH SLACK A None 2 0 0 2 0 B A 1 2 3 3 4 1 C A 3 2 5 2 5 0 D B 7 3 10 4 11 E B, C 3 5 8 11 F C 5 11 5 11 0 G D ,E, F 4...

  • Question 13 The following table provides a list of activities in a project, along with their...

    Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max            Crash cost             Activity                           Predecessors          Time (weeks)             Crash*    per week                   A                                none                                    7                          7         N/A                   B                                none                                    3                          2        $500                   C                                A                                       5                          3      $1000                   D                                A, B                                    6                          4      $2000                   E                                 C, D                                    4                          3      $1250                   F                                D                                       3                          2      $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT