Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Pred...

Using the information shown in the table below, what is the latest start time for activity E?

ACTIVITY Immediate Predecessor ACTIVITY TIME EARLIEST START EARLIEST FINISH LATEST START LATEST FINISH SLACK
A None 2 0 0 2 0
B A 1 2 3 3 4 1
C A 3 2 5 2 5 0
D B 7 3 10 4 11
E B, C 3 5 8 11
F C 5 11 5 11 0
G D ,E, F 4 11 15 11 15 0

5

6

8

7

0 0
Add a comment Improve this question Transcribed image text
Answer #1

For any activity, the slack is the difference between the earliest finish and earliest start or the latest finish and latest start. For activity E, the earliest finish and earliest start is 8 and 5. Hence the slack is 8-5 is 3. The difference between latest finish and latest start should also be 3. Hence we have 11 - Latest Start = 3. Hence Latest start for E is 11-3 = 8.

Thus the latest start time for activity E is 8.

Add a comment
Know the answer?
Add Answer to:
Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Pred...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

  • A. ACFG B. ABEG C. ACEG D. ABDG B 1 D G 4 E 3 С...

    A. ACFG B. ABEG C. ACEG D. ABDG B 1 D G 4 E 3 С 3 F Activity Time Earliest Start Earliest Finish Latest Finish Latest Start Slack Activity A 2 0 0 2 0 B 1 2 3 3 4 1 C 3 2 5 2 5 0 D 7 3 10 4 11 E 3 5 8 11 3 F 5 11 5 11 0 G 4 11 15 11 15 0 Refer to the figure above....

  • Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates...

    Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...

  • 11 The following activity times are given: Determine the following a) Earliest start time b) Earliest...

    11 The following activity times are given: Determine the following a) Earliest start time b) Earliest finish time c) Latest Start Time d) Latest finish time e) Critical Path Activity Completion time( in months) 1-2 5 1-3 6 1-4 2 2-5 3 2-6 1 3-5 3 4-5 0 4-7 2 5-8 9 5-7 5 7-8 4 6-9 7 8-9 3

  • Activity D is the immediate predecessor of activities K and M. If the latest start time...

    Activity D is the immediate predecessor of activities K and M. If the latest start time of K is at the end of day 99 and the latest start time of M is at the end of day 106, the latest finish time of D should be at the end of day

  • What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest...

    What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest finish) of activity E? o o ООООО < N N What is the LS (latest start) of activity E? ООООО The list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Immediate Predecessor Activity Time A L - L 4 B - 1 2 C - A, B F DL 4 G C, D, E What...

  • Consider the following set of activities: Time Predecessor Activity Required Activities A 5 None B 4...

    Consider the following set of activities: Time Predecessor Activity Required Activities A 5 None B 4 A C 5 B D 8 B E 9 C F 6 C,D G 8 D H 3 E,F,G a.     Draw the CPM network for this problem. b.     Calculate and summarize the earliest and latest start and finish times, the slack for each activity, and the critical activities. c.     What is the earliest time that the project can be completed? d.     If the project needed to be completed...

  • Figure to accompany Table 7.1 Table 7.1 Activity Slack 0 в 1 1 1 Activity Earliest...

    Figure to accompany Table 7.1 Table 7.1 Activity Slack 0 в 1 1 1 Activity Earliest Earliest Latest Time Start Finish Latest Start Finish 2 0 02 2 3 3 4 312 5 12 15 7 3 10 4 35 11 | 11 | 5 11 4 11 15 11 15 1 G 0 Refer to the Figure to accompany Table 7.1. Which one of the following is the critical path? O ACFG ABDG ABEG ACEG

  • The table below defines the activities and the normal time duration for each activities within a...

    The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT