The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project.
Table 1: The time-cost information for the activities
|
Activity |
Normal Completion Time (weeks) |
Immediate Predecessor |
Crash Time (weeks) |
Normal cost for activities |
Crash cost for activities/week |
|
A |
2 |
- |
1 |
1200 |
400 |
|
B |
3 |
- |
1 |
1400 |
500 |
|
C |
4 |
A |
4 |
1500 |
600 |
|
D |
3 |
B, A |
2 |
1600 |
1300 |
|
E |
8 |
D |
7 |
1400 |
1200 |
|
F |
3 |
C |
2 |
1100 |
1000 |
|
G |
2 |
E |
2 |
1400 |
1100 |
|
H |
3 |
F, G |
2 |
1200 |
400 |
Questions:
a.

b.
| Activity | ES | EF |
| A | 0 | 2 |
| B | 0 | 3 |
| C | 2 | 6 |
| D | 3 | 6 |
| E | 6 | 14 |
| F | 6 | 9 |
| G | 14 | 16 |
| H | 16 | 19 |
c.
| Activity | LS | LF |
| A | 1 | 3 |
| B | 0 | 3 |
| C | 9 | 13 |
| D | 3 | 6 |
| E | 6 | 14 |
| F | 13 | 16 |
| G | 14 | 16 |
| H | 16 | 19 |
d.
| Activity | ES | EF | LS | LF | Slack |
| A | 0 | 2 | 1 | 3 | 1 |
| B | 0 | 3 | 0 | 3 | 0 |
| C | 2 | 6 | 9 | 13 | 7 |
| D | 3 | 6 | 3 | 6 | 0 |
| E | 6 | 14 | 6 | 14 | 0 |
| F | 6 | 9 | 13 | 16 | 7 |
| G | 14 | 16 | 14 | 16 | 0 |
| H | 16 | 19 | 16 | 19 | 0 |
Slack = LS-ES=LF-EF
Critical path = B-D-E-G-H which is the longest path and has slack = 0
e.
The table below defines the activities and the normal time duration for each activities within a...
Question 8-10, CHAPTER 18: A home-remodeling project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Activity Predecessor(s) Normal Time Crash Time Normal Cost $400 Crash Cost $700 1600 2000 800 1100 1000 NNW 600 1200 1450 800 800 500 650 400 600 900 1300 F G H1 1000 650 8. Draw the network for this project. (10 points) 9. Please indicate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish on the...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 7 7 N/A B none 3 2 $500 C A 5 3 $1000 D A, B 6 4 $2000 E C, D 4 3 $1250 F D 3 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...
Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...
Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as… Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...
Consider the following set of activities: Time Predecessor Activity Required Activities A 5 None B 4 A C 5 B D 8 B E 9 C F 6 C,D G 8 D H 3 E,F,G a. Draw the CPM network for this problem. b. Calculate and summarize the earliest and latest start and finish times, the slack for each activity, and the critical activities. c. What is the earliest time that the project can be completed? d. If the project needed to be completed...