ANSWER:
a) The Project Completion time = 24 days
b) The Earliest Start time, ES, of Activity G = 15
days
c) The Latest Finish time, LF, of Activity C = 11
days
d) The critical activities are = ACEGH
CALCULATION:
We calculate the ES, EF, LS, and LF of the given CPM network as below.

Critical path is A->C->E->G->H
Project completion time = Sum of duration of the critical activities = 4+7+4+6+3 = 24 days
QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start...
QUESTION 5 Given is a CPM project network diagram as shown below. A F Start H End B D G B Activity days Start 0 A 2 H D 3 E 4 F 2 G 3 6 8 End 0 2 a) The Project Completion time days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity C- days. d) The critical activities are (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)
QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E H End B D G Start A B C D E F G H End Activity day 0 6 زر 8 7 4 9 4 6 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in...
Given is a CPM project network diagram as shown below. A וד H End Start التا B D G A F H Activity day Start 0 B 8 с 3 D 5 E 6 وانما | End 0 8 4 a) The Project Completion time = days b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days d) The critical activities are = (ex. Fill in answer as:...
Given is a CPM project network diagram as shown below.
Activity
Start
A
B
C
D
E
F
G
H
End
day
0
5
6
9
6
9
8
5
4
0
a) The Project Completion time = days.
b) The Earliest Start time, ES, of Activity G = days.
c) The Latest Finish time, LF, of Acitivity C = days..
d) The critical activities are = (ex. Fill in answer as: ABCD)
End Start
QUESTION 5 Given is a CPM project network diagram as shown below. А C F Start E Н. End B D G A B D E F G H Activity day Start 0 с 8 End 0 6 3 7 4 9 4 6 a) The Project Cor etion time = days b) The Earliest Start time, ES, of Activity G- days. c) The Latest Finish time, LF, of Acitivity - days. d) The critical activities are = (ex. Fill...
please show answers clearly
12 points Save Answer QUESTION 5 Given is a CPM project network diagram as shown below. F А H End E Start G B D E F Activity day Start 0 A 5 B 6 Ula G 5 H 4 End 0 ON 9 8 days. a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days.. c) The Latest Finish time, LF, of Acitivity C = d) The critical...
Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End Time 0 1.35 3.65 4.327 .36 8.25 1.394 .68 3.250 a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, Es, of Activity G- (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C (in 2 decimal places) d) The critical activities are (ex. type in critical activities as ABCD no comma, no space)
Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15 me 10 13 12 20 a) The Project Completion time = b) The Earliest Start time, ES, of Activity F- c) The Earliest Start time, ES, of Activity K = d) The Latest Start time, LS, of Activity. E = e) The non-critical activities are comma, no space) (ex. type in critical activities as ABCD, no
Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...