(a)

.
(b)
Critical path is the longest path in the network. All the activities on critical path have 0 slack.
Critical path is: A-D-F-H
Project length = Length of critical path = 5+6+3+8 = 22 weeks
.
(c)
For each activity, calculate the expected time, te =(optimistic + 4 * most likely + pessimistic)/6
Variance = (pessimistic - Optimistic)2/36
| Activity | Predecessor | Optimistic | Most likely | Pessimistic | Expected Time, te | Variance (σ2) |
| A | 3 | 5 | 7 | 5 | 0.44 | |
| B | 3 | 3 | 3 | 3 | 0 | |
| C | A | 7 | 7 | 7 | 7 | 0 |
| D | A | 2 | 6 | 10 | 6 | 1.78 |
| E | B | 4 | 7 | 10 | 7 | 1 |
| F | D | 1 | 3 | 5 | 3 | 0.44 |
| G | D,E | 10 | 10 | 10 | 10 | 0 |
| H | C,F | 8 | 8 | 8 | 8 | 0 |
We see that expected time remain same as deterministic time.
Project's expected completion time = 5+6+3+8 = 22
Critical path remains same, i.e. A-D-F-H
Project variance = SUM of variances of critical activities
= 0.44+1.78+0.44+0
= 2.67
.
Standard deviation = square root of variance
= sqrt(2.67)
= 1.63
Deadline = 25 weeks
z value = (25-22)/1.63
= 1.84
P(z) = NORMSDIST(1.84)
= 0.97
Probability of team failing to meet the deadline = 1 - P(z)
= 1 - 0.97
= 0.03
or, 3 %
.
(e)
For 90%, z value = NORMSINV(0.90)
= 1.28
Completion time = 22 + 1.28*1.63
= 24 weeks
You have recently been hired to help with planning for a music festival in Sydney, Australia...
You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Activity A B C D E F G...
need help
Crashing 6. When deciding on whether or not to crash project activities, a project manager was faced with the following information. Activities of the critical path are highlighted with an asterisk: 1992 Normal Crashed Activity A B* Extra Cost $4,000 $3,000 $3,500 D* Cost $5,000 $10,000 $3,500 $4,500 $1,500 $7,500 $3,000 $2,500 Duration 4 weeks 5 weeks 2 weeks 6 weeks 3 weeks 8 weeks 7 weeks 6 weeks $4,000 $2,500 Duration 3 weeks 4 weeks 1 week...
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...
Use the following information for questions 15 to 24. Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...
Use the following information for questions 1 to 10. Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...
Suppose that Rafay is only given 7 weeks (instead of 10) to
complete the project . By how many weeks should each activity be
crashed in order to meet the deadline? Assume that you can crash an
activity down to 0 weeks duration.
Activity
Each Activity Should be Reduced BY (weeks)
A
(weeks)- ?
B
(weeks)- ?
C
(weeks)- ?
D
(weeks)- ?
E
(weeks)- ?
F
(weeks)- ?
What is the total crashing cost ?
The following is a...
PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers. The project has been laid out with durations (in weeks), predecessors, and costs included: Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A 11 10 $1,500 $1,650 - B 7 5 $1,200 $2,490 - C 5 4 $900 $1,200 B D 4 2 $2,100 $3,000 A E 2 1 $550 $1,250 B F 4 3 $660 $1,050 E G 10...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 7 7 N/A B none 3 2 $500 C A 5 3 $1000 D A, B 6 4 $2000 E C, D 4 3 $1250 F D 3 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...