Custom Computers, Inc. assembles custom home computer systems. The fan assemblies needed are bought for $24 each. Annual dema

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question: Custom Computers, Inc. assembles custom home computer systems. The fan assemblies needed are bought for $24 each. Annual demand is 7500 fan assemblies, the annual inventory holding cost rate is $4 per unit, and the cost to place an order is estimated to be $60.

Answer:

**Please note: Rounded EOQ is taken for entire calculations. Refer accordingly.

Given that:

Annual Demand(D) = 7500

Order Cost (S) = 60

Holding Cost (H) = 4

Economic Order Quantity EOQ is given by:

EOQ = Sqrt(2 x D x S / H)

Therefore:

EOQ = Sqrt(2 x 7500 x 60 / 4)

EOQ = Sqrt(225000)

EOQ = 474.34 = 474

a. Average inventory level:

Average Inventory (AI) is given by:

AI = EOQ / 2

Therefore:

AI = 474 / 2

AI = 237

b. The number of orders placed per year

Number of orders placed per year is given by:

Number of ordersplaced per year = D / EOQ

Therefore:

Number of orders placed per year = 7500 / 474

Number of orders placed per year = 16

c. The total annual inventory holding cost

Total annual holding cost (THS) is given by:

THC = (EOQ / 2) x H

Therefore:

THC = (474 / 2) x 4

THC = 948

d. The total annual ordering cost:

Total annual ordering cost (TOC) is given by:

TOC = (D / EOQ) x S

Therefore:

TOC = (7500 / 474) x 60

TOC = 949.367089 = 949.37

e. The total annual cost:

The total annual cost (TC) is given by:

TC = THC + TOC

Therefore:

TC = 948 + 949.37

TC = 1897.37

**Please note: Rounded EOQ is taken for entire calculations. Refer accordingly.

Add a comment
Know the answer?
Add Answer to:
Custom Computers, Inc. assembles custom home computer systems. The fan assemblies needed are bought for $24...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Practice Problem 1 Custom Computers, Inc. assembles custom home computer systems. The fan assemblies needed are...

    Practice Problem 1 Custom Computers, Inc. assembles custom home computer systems. The fan assemblies needed are bought for $24 each. Annual demand is 7500 fan assemblies, the annual inventory holding cost rate is $4 per unit, and the cost to place an order is estimated to be $60. Assuming that the fan assemblies are ordered in quantities of 1500 units, calculate the following: a. Average inventory level b. The number of orders placed per year c. The total annual inventory...

  • The Boilermakers is a manufacturing company that uses gear assemblies to produce four different models of...

    The Boilermakers is a manufacturing company that uses gear assemblies to produce four different models of mountain bikes. One of these gear assemblies, the "Smooth Shifter," is used for the two most expensive models, and has an estimated annual demand of 540 units. The Boilermakers estimates the cost to place an order is $100, and the holding cost for each assembly is $10 per month. a) Currently, not knowing about EOQ, the purchasing manager places an order for the Smooth...

  • Bell Computers purchases integrated chips at $350 per chip. The holding cost is $37 per unit...

    Bell Computers purchases integrated chips at $350 per chip. The holding cost is $37 per unit per year, the ordering cost is $122 per order and sales are steady at 400 per month. The company's supplier, Rich Blue Chip Manufacturing, Inc., decides to offer price concessions in order to attract larger orders. The price structure is shown below. Rich Blue Chip's Price Structure Quantity Purchased Price/Unit 1-99 units $350 100-199 units $325 200 or more units $300 a) What is...

  • Bell Computers purchases integrated chips at $350.00 per chip. The holding cost is $35.00 per unit...

    Bell Computers purchases integrated chips at $350.00 per chip. The holding cost is $35.00 per unit per year, the ordering cost is $120.00 per order, and sales are steady at 400 per month. The company's supplier, Rich Blue Chip Manufacturing, Inc, decides to offer price concessions in order to attract larger orders. The pric structure is shown below Rich Blue Chip's Price Structure Quantity Purchased 1-99 units 100-199 units 200 or more units Price/Unit $350 $325 $300 a) What is...

  • a) What is the optimal order quantity and the minimum annual cost for Bell Computers to...

    a) What is the optimal order quantity and the minimum annual cost for Bell Computers to order, purchase, and hold these integrated chips? The optimal order quantity after the change in pricing structure is ________ units (enter your response as a whole number). The total annual cost for Bell computers to order, purchase, and hold the integrated chips is $____________ (round your response to the nearest whole number). b) Bell Computers wishes to use a 10% holding cost rather than...

  • The Burdell Company is a small manufacturing company that uses gear assemblies to produce four different...

    The Burdell Company is a small manufacturing company that uses gear assemblies to produce four different models of mountain bikes. One of these gear assemblies, the "Smooth Shifter", is used for the two most expensive of Burdell's four models, and has an estimated weekly demand of 7 units. Currently, this assembly is purchased in lots of 100 units. Burdell estimates the cost to place an order is $40, and the holding cost for each assembly is $5/unit/month. The company operates...

  • Parker Hi-Fi Systems Parker Hi-Fi Systems, located in Wellesley, Massachusetts, a Boston suburb, assembles and sells...

    Parker Hi-Fi Systems Parker Hi-Fi Systems, located in Wellesley, Massachusetts, a Boston suburb, assembles and sells the very finest home theater systems. The systems are assembled with components from the best manufacturers worldwide. Although most of the components are procured from wholesalers on the east coast, some critical items, such as LCD screens, come directly from their manufacturer. For instance, the LCD screens are shipped via air from Foxy, Ltd., in Taiwan, to Boston’s Logan airport, and the top-of-the-line speakers...

  • Bell Computers purchases integrated chips at $350 per chip. The holding cost is $34 per unit...

    Bell Computers purchases integrated chips at $350 per chip. The holding cost is $34 per unit per year, the ordering cost is $118 per order, and sales are steady at 405 per month. The company's supplier, Rich Blue Chip Manufacturing, Inc., decides to offer price concessions in order to attract larger orders. The price structure is shown below. Rich Blue Chip's Price Structure Quantity Purchased 1-99 units 100-199 units 200 or more units Price/Unit $350 $325 $300 a) What is...

  • Please Explain Thank you Bell Computers purchases integrated chips at $350 per chip. The holding cost...

    Please Explain Thank you Bell Computers purchases integrated chips at $350 per chip. The holding cost is $35 per unit per year, the ordering cost is $122 per order, and sales are steady at 395 per month. The company's supplier, Rich Blue Chip Manufacturing, Inc., decides to offer price concessions in order to attract larger orders. The price structure is shown below Rich Blue Chip's Price Structure Quantity Purchased 1-99 units 100-199 units 200 or more units Price/Unit $350 $325...

  • A provincial government uses massive quantities of computer printer paper, which it buys centrally. The purchasing...

    A provincial government uses massive quantities of computer printer paper, which it buys centrally. The purchasing department calculates an economic order quantity based on an assumed carrying rate of 30% per year. A box of printer paper costs $40, it costs $60 to process an order, and an annual demand is for 36000 boxes of paper. a) What is the economic order quantity? How much is the total inventory holding and ordering cost? b) The buyer wishes to determine how...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT