Question

1 2 3 5 6 7 8 9 10 4 40 Total Normal 39 28 27 25 28 42 35 34 37 335 Polka-dot 28 29 30 28 33 37 30 32 42 29 318 Use the chi-s
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The values given in the question are being inserted into the following table to calculate the chi-square value:

Observed value Expected ratio Expected value (O-E)2/E
Normal 335 1 326.5 0.221
Polka-dot 318 1 326.5 0.221
Total 653 653 X2 = 0.442

Hence the calculated chisquare value is less than the critical chi-square value.

If you have any query kindly comment before giving thumbs up. Thank you.

Add a comment
Know the answer?
Add Answer to:
1 2 3 5 6 7 8 9 10 4 40 Total Normal 39 28 27...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Window Help 12 2 Secion Exencise 9-10 (oritical vaue For the given table of observed frequencies: A 15 7 10 B 3 109 c 16 6 11 (a) Compute the row totals, the column totals, and the grand total (b...

    Window Help 12 2 Secion Exencise 9-10 (oritical vaue For the given table of observed frequencies: A 15 7 10 B 3 109 c 16 6 11 (a) Compute the row totals, the column totals, and the grand total (b) Construct the corresponding table of expected frequencies. (c) Compute the value of the chi-square statistic (d) How mamy degrees of freedom are there? (e) tf appropriate, perform a test of independence, using the α-0.05 level of significance, trot appropriate, explain...

  • Excel was asked to generate 50 Poisson random numbers with mean λ = 5. x Frequency 0 1         1 1         2 4         3 7         4 7         5 8         6 10         7 3        ...

    Excel was asked to generate 50 Poisson random numbers with mean λ = 5. x Frequency 0 1         1 1         2 4         3 7         4 7         5 8         6 10         7 3         8 3         9 4         10 1         11 1         (a) Calculate the sample mean. (Round your sample mean value to 2 decimal places.) Sample mean             (b) Carry out the chi-square test at α = .05, combining end categories as needed to ensure that all expected frequencies are at least...

  • Week 1 2 3 4 5 6 7 8 9 10 Demand 41 44 84 42...

    Week 1 2 3 4 5 6 7 8 9 10 Demand 41 44 84 42 84 86 7 18 49 30 End item A has a planned lead time of two weeks. There are currently 120 units on hand and no scheduled receipts. a. Compute the planned order releases using lot-for-lot b. Compute the planned order releases using part-period balancing where the ratio of the setup cost to the holding cost is 200 c. Compute the planned order releases...

  • 1 0.6248 2 0.652 3 0.6226 4 0.623 5 0.6237 6 0.6368 7 0.628 8 0.6131...

    1 0.6248 2 0.652 3 0.6226 4 0.623 5 0.6237 6 0.6368 7 0.628 8 0.6131 9 0.6118 10 0.622 11 0.6096 12 0.6223 13 0.6159 14 0.6151 15 0.63 16 0.6297 17 0.6298 18 0.6121 19 0.6107 20 0.6435 21 0.6192 22 0.6548 23 0.6392 24 0.5978 25 0.6351 26 0.6128 27 0.6134 28 0.6275 29 0.6403 30 0.631 31 0.6261 32 0.6521 33 0.6065 34 0.6262 35 0.6049 36 0.6214 37 0.6262 38 0.617 39 0.6141 40 0.6314...

  • 2 3 4 Student Work Area 2-18B 7 8 9 10 (a) Piecework eamings (b) Regular...

    2 3 4 Student Work Area 2-18B 7 8 9 10 (a) Piecework eamings (b) Regular hourly rate.. Overtime hourly rate.. (c) Overtime eamings. (d) Total camings..... Instructor Comment/Grade Area 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 42 43 Excel Instructions 2-4B 2-18B 2-20B Chapter Problems + 2-17B. LO 5 See Example 2-23 on page 2-28 During...

  • 1. 2. A E 3 4 5 6 7 8 9 B D Budget Assumptions For...

    1. 2. A E 3 4 5 6 7 8 9 B D Budget Assumptions For the months of January, February, and March January February Selling price per unit $200 $200 Budgeted sales (units) 12,000 15,000 Budgeted sales (units) April Budgeted production (units) April Ratio of ending finished goods inventory to next month's sales Ratio of ending raw materials inventory to next month's requirements Number of units in finished goods inventory, January 1 Number of pounds in raw materials inventory,...

  • Consider total cost and total revenue given in the following: (Quantity/Total Cost/Total Revenue): (0/8/0), (1/9/8), (2/10/16), (3/11/24), (4/13/32), (5/19/40), (6/27/48), (7/37/56) Can you tell whether this firm is in a competitive industry

    Consider total cost and total revenue given in the following: (Quantity/Total Cost/Total Revenue): (0/8/0), (1/9/8), (2/10/16), (3/11/24), (4/13/32), (5/19/40), (6/27/48), (7/37/56) Can you tell whether this firm is in a competitive industry? If so, can you tell whether the industry is in a long-run equilibrium? Isn't this firm a competitive industry since the price is equal to the marginal revenue? This is obviously a competitive industry because the average revenue is always the same. But the euqilibrium is not the...

  • questions by number 1 2 3 4 5 6 7 8 9 10 Submit Quiz Total...

    questions by number 1 2 3 4 5 6 7 8 9 10 Submit Quiz Total time remaining: 1:16 Question #2 / 10 Round 0.657 to the nearest tenth. Clear ee Prev. Question Ne Type here to search

  • Suggested Data Table (Partially completed) 1 2 3 4 5 6 7 8 9 10 11...

    Suggested Data Table (Partially completed) 1 2 3 4 5 6 7 8 9 10 11 Vol HX Init., mL Vol OH– added for this increment, mL Total Vol OH–, mL Total Vol Soln, mL [HX]i [X–]eq [HX]eq [X–]/[HX] log Meas'd pH Calc'd pKa 0 50.0 0.0 0.0 50.0 --- --- --- --- --- --- --- 1 50.0 10.0 10.0 60.0 2 50.0 5.0 15.0 65.0 3 50.0 5.0 20.0 70.0 4 50.0 10.0 5 50.0 6 50.0 please help...

  • please help. thank you! Total Question 12 3 4 5 6 7 8 9 10 11...

    please help. thank you! Total Question 12 3 4 5 6 7 8 9 10 11 1213 14 15 16 | 435(11.4%) 12 -/1 -/1 -8-6-6-/1 -3-13 ㅢ1-1 0/3 1/1 0,1 Points Assignment Submission For this assignment, you submit answers by question parts. The number of submissions remaining for each question part only cha Assignment Scoring Your last submission is used for your score. 4. 0/1 points I Previous Answers OSPreCalc1 8.1.041 Find the measure of angle x, If possible....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT