Mean and variance values are given below.
| Task | O | M | P | Te | Var^0.5 | Variance |
| J | 8 | 10 | 15 | 10.5 | 1.166667 | 1.361111 |
| K | 7 | 8 | 9 | 8 | 0.333333 | 0.111111 |
| L | 5 | 6 | 10 | 6.5 | 0.833333 | 0.694444 |
| M | 3 | 3 | 3 | 3 | 0 | 0 |
| N | 1 | 5 | 9 | 5 | 1.333333 | 1.777778 |
| O | 4 | 7 | 10 | 7 | 1 | 1 |
| P | 3 | 8 | 10 | 7.5 | 1.166667 | 1.361111 |
| Activity | ES | EF | LS | LF | Slack |
| J | 0 | 10.5 | 0 | 10.5 | 0 |
| K | 0 | 8 | 5.5 | 13.5 | 5.5 |
| L | 10.5 | 17 | 12 | 18.5 | 1.5 |
| M | 10.5 | 13.5 | 10.5 | 13.5 | 0 |
| N | 13.5 | 18.5 | 13.5 | 18.5 | 0 |
| O | 13.5 | 20.5 | 19 | 26 | 5.5 |
| P | 18.5 | 26 | 18.5 | 26 |

Critical path is JMKP with duration 26.
Variance of critical path = 2.8333
SD of critical path = (2.8333)^0.5 =1.6832
2. Consider the network described in the table below. Immediate Predecessor(s) Activity J K L M...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....
2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10 8 K 9 8 7 L 10 6 5 M 3 3 3 N KM 9 5 1 O KM 10 7 4 P LN 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will...
tual code de a Activity Predecessor Normal time A 2 B 3 C B A С 5 G. F H 15 HH 2 D И N M, J 1 - Calculate early start (ES), early finish (EF), late start (LS) and late finish (LF) for each activity - Draw Activity on Arrow network (AOA) - Draw Activity on Node network (AON) - Calculate slack of each activity - Determine the critical paths. There must be at least 2 critical paths...
Question 3 1 pts Consider the network described in the table below. Activity Preceding Optimistic Probable Pessimistic 11 14 |A,B 7 11 13 G D, E 10 DE Calculate the Variance of the project 1.78 1.36 4.14 5.82 None of the above
Consider the following project activities:
Calculate the expected time (te) for each
activity.
Draw an Activity on Node (AON) diagram to reflect the flow of
these activities.
Calculate the Early Start (ES), Early Finish (EF), Late Start
(LS), and Late Finish (LF) for each activity.
Calculate the slack for each activity.
Identify all activities on the Critical Path.
Use the data to calculate the probability the project will
finish in 20 weeks (Hint: z-score).
Activity A 8 с D E...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with precedence relationships and duration (days) as shown in the following table. The project will be finished when activities A-J are all finished. Activity predecessor Optimistic Most likely Pessimistic Expected A - 4 5 12 B A 3 4.5 15 C A 2 3 4 D C 6 8 22 E B 4 6 8 F...
Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable Pessimistic A 5 7 B 3 5 7 C 1 2 9 5 E 3 4 2 3 10 G 6 7 14 H 4 12 B G E H. C A. Finish Start F D Using the three time estimate approach, what is the value of uC? O 6 O4 None of the above are correct Use the network activity diagram and table...
1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...
Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...