Question

The ABC Manufacturing Co. has made a decision to replace an existing production line with new...

The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with precedence relationships and duration (days) as shown in the following table. The project will be finished when activities A-J are all finished.

Activity

predecessor

Optimistic

Most likely

Pessimistic

Expected

A

-

4

5

12

B

A

3

4.5

15

C

A

2

3

4

D

C

6

8

22

E

B

4

6

8

F

C

3

4

5

G

D,E

1.5

3

4.5

H

B

5

7

15

I

H

3

4

5

J

G, I

2

4

6

  1. Calculate the expected time for each activity

Expected times (t) = a + 4m + b) / 6

a = Optimistic time, m= most likely, b= pessimistic time

  1. Create an Activity-On-Arrow network diagram for this Project.
  2. Sketch Gantt chart for this project
  3. Construct the PERT Network for this using this legend (you need to calculate the earliest start (ES) and finish (EF) times and latest start (LS) and finish (LF) times, the slack (S) for each of the activities in the network).

            ES

D

EF

Activity name

LS

S

LF

ES: Early start, EF: early finish, LS: Late start, LF: late finish

D: Duration or Expected time

S: Slack

  1. Identify the critical path(s).
  2. What is the project completion duration?
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1 B C D E F G
2 Activity predecessor Optimistic Most likely Pessimistic Expected
3 A - 4 5 12 6
4 B A 3 4.5 15 6
5 C A 2 3 4 3
6 D C 6 8 22 10
7 E B 4 6 8 6
8 F C 3 4 5 4
9 G D,E 1.5 3 4.5 3
10 H B 5 7 15 8
11 I H 3 4 5 4
12 J G, I 2 4 6 4

Formula

1 B C D E F G
2 Activity predecessor Optimistic Most likely Pessimistic Expected
3 A - 4 5 12 =(D3+(4*E3)+F3)/6
4 B A 3 4.5 15 =(D4+(4*E4)+F4)/6
5 C A 2 3 4 =(D5+(4*E5)+F5)/6
6 D C 6 8 22 =(D6+(4*E6)+F6)/6
7 E B 4 6 8 =(D7+(4*E7)+F7)/6
8 F C 3 4 5 =(D8+(4*E8)+F8)/6
9 G D,E 1.5 3 4.5 =(D9+(4*E9)+F9)/6
10 H B 5 7 15 =(D10+(4*E10)+F10)/6
11 I H 3 4 5 =(D11+(4*E11)+F11)/6
12 J G, I 2 4 6 =(D12+(4*E12)+F12)/6

From the Network diagram, It can be concluded that Critical Path is A– B –H - I - J and it is shown with Bold Line, again Project Need at least 28 Days to finish,

Activity ES LS EF LF Slack Critical Path activity Yes or No
A 0 0 6 6 0 Yes
B 6 6 12 12 0 Yes
C 6 8 9 11 2 No
D 9 11 19 21 2 No
E 12 15 18 21 3 No
F 9 24 13 28 15 No
G 19 21 22 24 2 No
H 12 12 20 20 0 Yes
I 20 20 24 24 0 Yes
J 24 24 28 28 0 Yes
Add a comment
Know the answer?
Add Answer to:
The ABC Manufacturing Co. has made a decision to replace an existing production line with new...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • tual code de a Activity Predecessor Normal time A 2 B 3 C B A С...

    tual code de a Activity Predecessor Normal time A 2 B 3 C B A С 5 G. F H 15 HH 2 D И N M, J 1 - Calculate early start (ES), early finish (EF), late start (LS) and late finish (LF) for each activity - Draw Activity on Arrow network (AOA) - Draw Activity on Node network (AON) - Calculate slack of each activity - Determine the critical paths. There must be at least 2 critical paths...

  • (3) Determine the critical path and critical time of the network shown below. Use the critical...

    (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B А 7...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • 4. A project manager calculated early and late start and finish times for all activities in...

    4. A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries. The remaining legible entries are correct. Activity Predecessor Duration ES EF LS LF Slack A -- B A 12 12 C A 5 18 D B 8 E C 9 0 F D,E 27 34 0 G E 6 33...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max            Crash cost             Activity                           Predecessors          Time (weeks)             Crash*    per week                   A                                none                                    7                          7         N/A                   B                                none                                    3                          2        $500                   C                                A                                       5                          3      $1000                   D                                A, B                                    6                          4      $2000                   E                                 C, D                                    4                          3      $1250                   F                                D                                       3                          2      $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

    Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....

  • QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questio...

    QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT