Solution:
| Activity | Immediate Predecessors | Duration |
| A | - | 6 |
| B | A | 7 |
| C | A | 8 |
| D | B,C | 5 |
| E | C | 6 |
| F | D,E | 6 |
Edge and it's preceded and succeeded node
| Edge | Node1 → Node2 |
| A | 1→2 |
| B | 2→3 |
| C | 2→4 |
| D | 3→5 |
| d | 4→3 |
| E | 4→5 |
| F | 5→6 |
The network
diagram for the project, along with activity time, is

Forward
Pass Method
E1=0
E2=E1+t1,2
[t1,2=A=6]=0+6=6
E3=Max{Ei+ti,3}[i=2,4]
=Max{E2+t2,3;E4+t4,3}
=Max{6+7;14+0}
=Max{13;14}
=14
E4=E2+t2,4
[t2,4=C=8]=6+8=14
E5=Max{Ei+ti,5}[i=3,4]
=Max{E3+t3,5;E4+t4,5}
=Max{14+5;14+6}
=Max{19;20}
=20
E6=E5+t5,6
[t5,6=F=6]=20+6=26
Backward
Pass Method
L6=E6=26
L5=L6-t5,6
[t5,6=F=6]=26-6=20
L4=Min{Lj-t4,j}[j=5,3]
=Min{L5-t4,5;L3-t4,3}
=Min{20-6;15-0}
=Min{14;15}
=14
L3=L5-t3,5
[t3,5=D=5]=20-5=15
L2=Min{Lj-t2,j}[j=4,3]
=Min{L4-t2,4;L3-t2,3}
=Min{14-8;15-7}
=Min{6;8}
=6
L1=L2-t1,2
[t1,2=A=6]=6-6=0
The
critical path in the network diagram has been shown. This has been
done by double lines by joining all those events where E-values and
L-values are equal.
The
critical path of the project is : 1-2-4-5-6 and critical activities
are A,C,E,F
The
total project time is 26
The network
diagram for the project, along with E-values and L-values,
is

For each non-critical activity, the total float, free float and independent float calculations are shown in Table
Activity (i,j) (1) |
Duration (tij) (2) |
Earliest time Start (Ei) (3) |
(Ej) (4) |
(Li) (5) |
Latest time Finish (Lj) (6) |
Earliest time Finish (Ei+tij) (7)=(3)+(2) |
Latest time Start (Lj-tij) (8)=(6)-(2) |
Total Float (Lj-tij)-Ei (9)=(8)-(3) |
Free Float (Ej-Ei)-tij (10)=((4)-(3))-(2) |
Independent Float (Ej-Li)-tij (11)=((4)-(5))-(2) |
| 2-3 | 7 | 6 | 14 | 6 | 15 | 13 | 8 | 2 | 1 | 1 |
| 3-5 | 5 | 14 | 20 | 15 | 20 | 19 | 15 | 1 | 1 | 0 |
| 4-3 | 0 | 14 | 14 | 14 | 15 | 14 | 15 | 1 | 0 | 0 |
If you liked the answer please give an up-vote, it will be quite encouraging to me. Thank you and have a nice day!!!
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...
(3) Determine the critical path and critical time of the network
shown below. Use the critical path method (the table of ES, EF,
etc.).
(3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...
11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...
Paragraph HOMEWORK Number 8 a) Construct a CPM network for the project shown in a tabular form b) Calculate ES(early start) and LS (Late Start) of each activity c) Find critical path and its duration, make it bold or red color. Activity Immediate Predecessor Activity Duration(weeks}} А А A B.C 12 D CB н EEG
21. Using the CPM method, calculate early start (ES), late start (LS), early finish (EF), late finish (LF) and total float (TF) for each activity in the following network and answer the questions 21-1. The ES of activity His: a) 18 b) 22C) 5 d) 2 21-2. The LF of activity B is: a) 20 b) 22c) 18d) 19 ) 13 d) 59 21-3. The TF of activity A is: a) 5 b ) 17 c) 18 21-4. The project...
For the following, draw the node network, perform the CPM
calculations, mark the critical Path, and complete the table.
IAAB 745 00 ABCDE Make possibility of rejection. Also show procurement activities CHAPTER 4 EXERCISES 1. For the following schedule, draw the node network, perform the CPM tions, mark the critical path, and complete the table. Activity Duration IPA ES EF LS LF TF FF В 8 B, C For the following schedule, draw the node network, perform the CPM tions,...
The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with precedence relationships and duration (days) as shown in the following table. The project will be finished when activities A-J are all finished. Activity predecessor Optimistic Most likely Pessimistic Expected A - 4 5 12 B A 3 4.5 15 C A 2 3 4 D C 6 8 22 E B 4 6 8 F...
1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...
Construction Management Assignment on "Critical Path Method (CPM)" Do the following tasks for each of the questions (a) Draw both the activity-on-arrow (AOA) network and the activity-on-node (AON) network. (b) Calculate the early start time (ES), early finish time (EF), late start time (LS), and late finish time (LF) of each activity, and identify the critical path. (c) Compute the total float (TF), free float (FF), interfering float (IF), and independent float (IDF) for each activity (Note: The duration of...
Consider the following project activities:
Calculate the expected time (te) for each
activity.
Draw an Activity on Node (AON) diagram to reflect the flow of
these activities.
Calculate the Early Start (ES), Early Finish (EF), Late Start
(LS), and Late Finish (LF) for each activity.
Calculate the slack for each activity.
Identify all activities on the Critical Path.
Use the data to calculate the probability the project will
finish in 20 weeks (Hint: z-score).
Activity A 8 с D E...