11. In CPM/PERT, an activity that is on the critical path
A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES )
B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF )
C. is used in calculating total project duration
D. has slack equal to zero
E. all of the above
12. In CPM/PERT, the critical path through the network
A. will require the most time of any path
B. will require the least time of any path
C. will contain the most activities of any path
D. will contain the least activities of any path
E. both A and C
11-activity in critical path have all the above four activities.
E) All of the above
12) -here critical path will require most time of the path and contains most of the activities
E) both A and C
11. In CPM/PERT, an activity that is on the critical path A. has equal values for...
(3) Determine the critical path and critical time of the network
shown below. Use the critical path method (the table of ES, EF,
etc.).
(3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...
The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with precedence relationships and duration (days) as shown in the following table. The project will be finished when activities A-J are all finished. Activity predecessor Optimistic Most likely Pessimistic Expected A - 4 5 12 B A 3 4.5 15 C A 2 3 4 D C 6 8 22 E B 4 6 8 F...
QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B А 7...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 7 7 N/A B none 3 2 $500 C A 5 3 $1000 D A, B 6 4 $2000 E C, D 4 3 $1250 F D 3 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
also needs daves latest start and latest finish:
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...
For the following, draw the node network, perform the CPM
calculations, mark the critical Path, and complete the table.
IAAB 745 00 ABCDE Make possibility of rejection. Also show procurement activities CHAPTER 4 EXERCISES 1. For the following schedule, draw the node network, perform the CPM tions, mark the critical path, and complete the table. Activity Duration IPA ES EF LS LF TF FF В 8 B, C For the following schedule, draw the node network, perform the CPM tions,...
for each problem I have this setup so far. I need help on each
part and im not too sure if I am on the right track for each
question on the picture. this chapter is on project management for
statistics
1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...