Cost A, is same at the two different activity levels, So Cost A is a Fixed cost
Cost B, Variable cost per unit = [$60,000 - $36,000] / [15000-9000] = $4 per Machine hour, fixed cost in it is [$60,000 - (15,000*4)] = $0. So, cost B is completely a variable cost
Cost C, Variable cost per unit = [$85,000 - $55,000] /[15,000- 9,000] = $5 per machine hour and fixed element in it is [$85,000 - ($5 * 15000)] = $10,000
Computation of Expected total costs at 12,000 machine hours.
Cost A = $66,000
Cost B = 12,000 * 4 = $48,000
Cost C = [$10,000 + ($5 * 12,000)] = $70,000
Total expected costs = $184,000
So, The total expected cost at 12,000 machine hours activity level = $184,000
Vaughan Company had the following costs at two different levels of activity: MH Used 9,000 MH...
Vaughan Company had the following costs at two different levels of activity: MH Used 10,000 MH 15,000 MH September October Cost A $ 80,000 $120,000 Cost B $ 50,000 $ 65,000 Cost C $50,000 $50,000 If Vaughan Company expected to used 14,000 machine hours (MH) next month, what would they expect total costs (Cost A+ Cost B+ Cost C) to be?
Vaughan Company had the following costs at two different levels of activity: MH Used 8,000 MH 15,000 MH October September $ 40,000 Cost A $ 75,000 Cost B $ 68,000 $ 117,000 Cost C $ 32,000 $ 32,000 Which of the following statements are true? 1. Cost A and Care variable costs 2. In a month where 10,000 machine hours (MH) are expected to be used, Cost B would be estimated to be $85,000 3. In a month where 12,000...
Brona Company makes treadmills. The company controller wants to calculate the fixed and variable costs associated with the janitorial costs incurred in the factory. Data for the past four months were as follows: Month Janitorial costs Machine hours September JC:$12,500 mh:770 October JC:15,000 MH:800 November JC:12,000 MH:600 December JC:13,200 MH:630 MH: machine hours Options: A. $6,000 B. None of these C. $5,230 D. $3,000 JC:janitorial cost
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 46,000 36,000 56,000 66,000 Total Overhead Cost $ 186,020 $ 161,820 $ 210,220 $ 234, 420 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 43, 200 60,000 58,620 $ 161,...
Problem 2 East Coast Colorworks produces modular office space units. The company uses a job order costing system to accumulate product costs. Because much of the production process is automated, East Coast has selected machine hours as its overhead application rate In October, East Coast worked on four jobs. Job 105 and Job 106 were started in September and completed and delivered to customers in October. Job 107 and Job 108 were started in October and Job 107 was finished...
Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $175,050 $ 151,550 $198,550 $ 222,050 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000-machine-hour level of activity in May is as follows: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 42,000 55,000 54,550 Total overhead cost $ 151,550 The company wants...
Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $204,360 $180,060 $228,660 $252,960 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 54,600 60,000 65,460 Total overhead cost $ 180,060 The company wants to...
2-Golden Company's total overhead cost at various levels of activity are presented below: Total Overhead Cost $194,000 $170,200 $217,800 $241,600 Month Machine Hours March 50,000 40,000 60,000 70,000 April May June Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 40,000 machine-hour level of activity is as follows: $52,000 Utilities (variable) Supervisory Salaries (fixed) $60,000 Maintenance (mixed) $58,200 $170,200 Total Overhead Cost A-Estimate how much of the $241,600 overhead...
Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Maintenance. ... Materials handling Machine setups Inspections .. $ 20,000 30,000 70,000 $10,000 15,000 5,000 25,000 $55,000 Cost Driver Machine hours Material moves Machine setups Inspection hours $120,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours .. Materials moves.. Machine setups Inspection hours. 10,000 3,000 700 5,000...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $ 192,900 $ 166,900 $ 218,900 $ 244,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,000 60,000 57,900 $ 166,900 Nova Company's...