| Answer 1 | |
| Cost and profits in excess of billings | $ 900,000 |
| Add: Progress billings during the year | $ 2,850,000 |
| Total of cost and profits | $ 3,750,000 |
| Revenue = Total of cost and profits | $ 3,750,000 |
| Answer 2 | |
| Progress billings during the year | $ 2,850,000 |
| Less: Accounts receivable at the end | $ 427,500 |
| Cash collections during the year | $ 2,422,500 |
| Answer 3 | |
| Revenue | $ 3,750,000 |
| Divided by: Total contract value | $ 10,000,000 |
| Percentage of completion | 37.50% |
| Cumulative cost incurred at end of year | $ 3,000,000 |
| Divided by: Percentage of completion | 37.50% |
| Estimated total costs | $ 8,000,000 |
| Estimated total costs | $ 8,000,000 |
| Less: Cumulative cost incurred at end of year | $ 3,000,000 |
| Estimated costs to complete as of year-end | $ 5,000,000 |
| Answer 4 | |
| Percentage of completion | 37.50% |
| Percentage of completion | 0.3750 |
| Percentage of completion (Rounded) | 0.38 |
Nam Construction, a sub-contractor, entered into a contract with the main contractor, Ming Company, on March 6, 2018 to provide civil engineering services at the contract fee of $10,000,000. The contract spans three years from 2018 to 2020. Costs incurred, estimated costs to complete at year-end, billings and cash collections for the life of the contract are shown below: 2018 2019 2020 Costs incurred during the year $ 4,800,000 $ 2,200,000 $ 1,800,000 Estimated costs to complete as of year-end...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....
MakaGood Construction Corp.
please show work or formulas. thanks
B С D E F G H MakaGood Contruction Corp. MakaGood Construction Corp. agreed to construct the new Texas Stadium for $ 1,200,000 K. Originally construction costs were expected to be $ 925,000 K and the project was expected to take four years. The results for the construction project are as follows: 2016 2017 Actual costs incurred Anticipated cost to complete Current year billings Current year collections Actual costs incurred Anticipated...
In February 2020, Crane Construction signed a contract and
commenced construction on a parking garage. The total contract
price was $89.8 million and was expected to be completed in July
2024 at a total estimated cost of $82.0 million. Payment by the
customer was to be made in several stages, based on significant
events and dates throughout the construction timeline. The customer
was to have control over the parking garage and was able to make
major changes to the project...
Prachce Problem 9 In Year 1, Amber Construction Corporation began construction work under a three-year contract. The contract price is $1,610,000. Long uses the percentage-of-completion method for financial reporting purposes. The financial statement presentation relating to this contract at December 31, year 1, is as follows: Balance Sheet $30,000 Accounts receivable (from construction progress billings) Construction in progress Less: Billings on Construction Contract $100,000 (93,000) 7,000 Cost of uncompleted contracts in excess of billings Income Statement $24,000 Income (before tax)...
During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
Question 12 --/1 View Policies Current Attempt in Progress During 2020, Headland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date Estimated costs to complete $410,000 $901,180 $1,067,000 590,000 197,820 -O- 297,000 903,000 1,590,000 271,000 805,000 1,434,000 Billings to date Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used....
During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...