Answer is option 5
101075 equivalent units
Total equivalent units for conversion under the FIFO method = units complete and transferred + ending Work in process inventory (conversion) - beginning work in process inventory (conversion) = 108500+(26000*55%)-(39500*55%)= 101075 equivalent units
Matrix Inc. calculates cost for an equivalent unit of production using the FIFO method. Data for...
Matrix Inc. calculates cost for an equivalent unit of production using the FIFO method. Data for July: Work-in-process inventory, July 1 (36,000 units): Direct materials (100% completed) Conversion (50% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (100% completed) Conversion (50% completed) Cost incurred during July: Direct materials Conversion costs $122,400 76,800 $199,200 90,000 102,000 24,000 $180,000 288,000 Cost per equivalent unit for conversion under...
Matrix Inc. calculates cost for an equivalent unit of production using the weighted-average method. Data for July: Work-in-process inventory, July 1 (36,000 units): Direct materials (100% completed) Conversion (50% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (100% completed) Conversion (50% completed) Cost incurred during July: Direct materials Conversion costs $122,400 76,800 $199, 200 90,000 102,000 24,000 $180,000 288,000 Total equivalent units for materials under...
Matrix Inc. calculates cost for an equivalent unit of production using the weighted-average method. Data for July: Work-in-process inventory, July 1 (35,500 units): Direct materials (96% completed) $ 123,000 Conversion (47% completed) 77,450 Balance in work in process inventory, July 1 $ 200,450 Units started during July 86,500 Units completed and transferred 96,800 Work-in-process inventory, July 31: Direct materials (96% completed) 25,200 Conversion (47% completed) Cost incurred during July: Direct materials $ 186,000 Conversion costs 266,500 Total equivalent units for...
Matrix Inc. calculates cost for an equivalent unit of production using the weighted average method. Data for July: Work-in-process inventory, July 1 (38,500 units): Direct materials (90% completed) $122,250 Conversion (53% completed) 77,750 Balance in work in process inventory, July 1 $200,000 Units started during July 89,500 Units completed and transferred 102,200 Work-in-process inventory, July 31: Direct materials (90% completed) 25,800 Conversion (53% completed) Cost incurred during July: Direct materials $172,000 Conversion costs 269,500 The cost of goods completed and...
Matrix Inc. calculates cost for an equivalent unit of production using the weighted average method. Data for July: Work-in-process inventory, July 1 (38,000 units): Direct materials (91% completed) Conversion (52% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (91% completed) Conversion (52% completed) Cost incurred during July: Direct materials Conversion costs $122,200 77,700 $199,900 89,000 101,300 25,700 $171,500 269,000 The cost of goods completed and...
ABC Inc. calculates cost for an equivalent unit of production using the weighted-average method. Data for July: Work-in-process inventory, July 1 (37,000 units): Direct materials (98% completed) $ 122,500 Conversion (52% completed) 76,950 Balance in work in process inventory, July 1 $ 199,450 Units started during July 91,000 Units completed and transferred 103,800 Work-in-process inventory, July 31: Direct materials (98% completed) 24,200 Conversion (52% completed) Cost incurred during July: Direct materials $ 181,000 Conversion costs 289,000 The cost of goods...
dule 3 Quiz Served Matrix Inc. calculates cost for an equivalent unit of production using the weighted average method. 6 Data for July: Work-in-process inventory, July 1 (36,000 units): Direct materials (100% completed) Conversion (50% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (100% completed) Conversion (50% completed) Cost incurred during July: Direct materials Conversion costs $122,400 76,800 $199, 200 90,000 102,000 24,000 $180,000 288,000...
Pablo Company calculates the cost for an equivalent unit of
production using process costing.
Data for June
Work-in-process inventory, June 1: 16,000
units
Direct materials: 100% complete
$
32,000
Conversion: 40% complete
12,800
Balance in work-in-process, June 1
$
44,800
Units started during June
39,200
Units completed and transferred out
39,200
Work-in-process inventory, June 30
16,000
Direct materials: 100% complete
Conversion: 80% complete
Costs incurred during June
Direct materials
$
90,160
Conversion costs
Direct labor
90,160
Applied overhead
121,520
Total...
Pablo Company calculates the cost for an equivalent unit of production using process costing. Data for June Work-in-process inventory, June 1: 21,000 units Direct materials: 100% complete Conversion: 40% complete Balance in work-in-process, June 1 Units started during June Units completed and transferred out Work-in-process inventory, June 30 Direct materials: 100% complete Conversion: 80% complete Costs incurred during June Direct materials Conversion costs Direct labor Applied overhead Total conversion costs $ 42,000 16,800 $ 58,800 50,200 50,200 21,000 $140,560 140,560...
Pablo Company calculates the cost for an equivalent unit of
production using process costing.
Data for June
Work-in-process inventory, June 1: 15,000
units
Direct materials: 100% complete
$
30,000
Conversion: 40% complete
12,000
Balance in work-in-process, June 1
$
42,000
Units started during June
37,000
Units completed and transferred out
37,000
Work-in-process inventory, June 30
15,000
Direct materials: 100% complete
Conversion: 80% complete
Costs incurred during June
Direct materials
$
81,400
Conversion costs
Direct labor
81,400
Applied overhead
111,000
Total...