ABC Inc. calculates cost for an equivalent unit of production using the weighted-average method.
| Data for July: | |||
| Work-in-process inventory, July 1 (37,000 units): | |||
| Direct materials (98% completed) | $ | 122,500 | |
| Conversion (52% completed) | 76,950 | ||
| Balance in work in process inventory, July 1 | $ | 199,450 | |
| Units started during July | 91,000 | ||
| Units completed and transferred | 103,800 | ||
| Work-in-process inventory, July 31: | |||
| Direct materials (98% completed) | 24,200 | ||
| Conversion (52% completed) | |||
| Cost incurred during July: | |||
| Direct materials | $ | 181,000 | |
| Conversion costs | 289,000 | ||
The cost of goods completed and transferred out under the
weighted-average method is calculated to be--------------:
$583,610.
$572,976.
$607,200.
$96,344.
$584,630.
Solution:
| Equivalent units of production (EUP) - Weighted Average method | |||||
| Units | %Material | EUP-Material | % Conversion | EUP- Conversion | |
| Units transferred out | 103800 | 100% | 103800 | 100% | 103800 |
| units of Ending work in process | 24200 | 98% | 23716 | 52% | 12584 |
| Equivalent units of production | 127516 | 116384 | |||
| Cost per EUP | Material | Conversion | |||
| Cost of Beginning Work in process | $1,22,500 | $76,950 | |||
| Costs incurred this period | $1,81,000 | $2,89,000 | |||
| Total Costs | Costs | $3,03,500 | Costs | $3,65,950 | |
| /Equivalent units of Production | EUP | 127516 | EUP | 116384 | |
| Cost per Equivalent unit of Production | $2.38 | $3.14 |
| Cost of Units Transferred out | EUP | Cost per EUP | Total Cost |
| Direct Material | 103800 | $2.38 | $2,47,044 |
| Conversion | 103800 | $3.14 | $3,25,932 |
| Total Cost transferred out | $5,72,976 |
Hence second option $572,976 is correct.
ABC Inc. calculates cost for an equivalent unit of production using the weighted-average method. Data for...
Matrix Inc. calculates cost for an equivalent unit of production using the weighted average method. Data for July: Work-in-process inventory, July 1 (38,000 units): Direct materials (91% completed) Conversion (52% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (91% completed) Conversion (52% completed) Cost incurred during July: Direct materials Conversion costs $122,200 77,700 $199,900 89,000 101,300 25,700 $171,500 269,000 The cost of goods completed and...
Matrix Inc. calculates cost for an equivalent unit of production using the weighted average method. Data for July: Work-in-process inventory, July 1 (38,500 units): Direct materials (90% completed) $122,250 Conversion (53% completed) 77,750 Balance in work in process inventory, July 1 $200,000 Units started during July 89,500 Units completed and transferred 102,200 Work-in-process inventory, July 31: Direct materials (90% completed) 25,800 Conversion (53% completed) Cost incurred during July: Direct materials $172,000 Conversion costs 269,500 The cost of goods completed and...
Matrix Inc. calculates cost for an equivalent unit of production using the weighted-average method. Data for July: Work-in-process inventory, July 1 (36,000 units): Direct materials (100% completed) Conversion (50% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (100% completed) Conversion (50% completed) Cost incurred during July: Direct materials Conversion costs $122,400 76,800 $199, 200 90,000 102,000 24,000 $180,000 288,000 Total equivalent units for materials under...
Matrix Inc. calculates cost for an equivalent unit of production using the weighted-average method. Data for July: Work-in-process inventory, July 1 (35,500 units): Direct materials (96% completed) $ 123,000 Conversion (47% completed) 77,450 Balance in work in process inventory, July 1 $ 200,450 Units started during July 86,500 Units completed and transferred 96,800 Work-in-process inventory, July 31: Direct materials (96% completed) 25,200 Conversion (47% completed) Cost incurred during July: Direct materials $ 186,000 Conversion costs 266,500 Total equivalent units for...
Matrix Inc. calculates cost for an equivalent unit of production using the FIFO method. Data for July: Work-in-process inventory, July 1 (36,000 units): Direct materials (100% completed) Conversion (50% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (100% completed) Conversion (50% completed) Cost incurred during July: Direct materials Conversion costs $122,400 76,800 $199,200 90,000 102,000 24,000 $180,000 288,000 Cost per equivalent unit for conversion under...
dule 3 Quiz Served Matrix Inc. calculates cost for an equivalent unit of production using the weighted average method. 6 Data for July: Work-in-process inventory, July 1 (36,000 units): Direct materials (100% completed) Conversion (50% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (100% completed) Conversion (50% completed) Cost incurred during July: Direct materials Conversion costs $122,400 76,800 $199, 200 90,000 102,000 24,000 $180,000 288,000...
Matrix Inc. calculates cost for an equivalent unit of production using the FIFO method. Data for July: Work-in-process inventory, July 1 (39,500 units): Direct materials (88% completed) Conversion (55% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (88% completed) Conversion (55% completed) Cost incurred during July: Direct materials Conversion costs $122,350 77,850 $200,200 95,000 108,500 26,000 $173,000 270,500 Total equivalent units for conversion under the...
Pablo Company calculates the cost for an equivalent unit of
production using process costing.
Data for June
Work-in-process inventory, June 1: 15,000
units
Direct materials: 100% complete
$
30,000
Conversion: 40% complete
12,000
Balance in work-in-process, June 1
$
42,000
Units started during June
37,000
Units completed and transferred out
37,000
Work-in-process inventory, June 30
15,000
Direct materials: 100% complete
Conversion: 80% complete
Costs incurred during June
Direct materials
$
81,400
Conversion costs
Direct labor
81,400
Applied overhead
111,000
Total...
Pablo Company calculates the cost for an equivalent unit of production using costing. Data For June Work in process inventory, June 1: 30,000 units Direct materials: 100% complete 60,000 Conversation: 40% complete 25,000 Balance in work process 85,000 Units started during June 70,000 Units completed and transferred out 70,000 Work in process inventory, June 30 30,000 Direct materials: 100% complete Conservation: 80% complete Costs incurred during June Direct materials 122,500 Conversation costs Direct labor 119,720 Applied overhead 179,580 Total conversation...
Pablo Company calculates the cost for an equivalent unit of production using process costing. $ 30,000 12,000 $ 42,000 37,000 37,000 15,000 Data for June Work-in-process inventory, June 1: 15,000 units Direct materials: 100% complete Conversion: 40% complete Balance in work-in-process, June 1 Units started during June Units completed and transferred out Work-in-process inventory, June 30 Direct materials: 100% complete Conversion: 80% complete Costs incurred during June Direct materials Conversion costs Direct labor Applied overhead Total conversion costs $ 81,400...